Exam 10: The Basics of Capital Budgeting: Evaluating Cash Flows

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

McGlothin Inc.is considering a project that has the following cash flow data.What is the project's payback? Year 0 1 2 3 Cash flows -\ 1,150 \ 500 \ 500 \ 500

(Multiple Choice)
4.8/5
(38)

Conflicts between two mutually exclusive projects occasionally occur, where the NPV method ranks one project higher but the IRR method ranks the other one first.In theory, such conflicts should be resolved in favor of the project with the higher positive NPV.

(True/False)
4.7/5
(40)

Suzanne's Cleaners is considering a project that has the following cash flow data.What is the project's payback? Year 0 1 2 3 4 5 Cash flows -\ 1,100 \ 300 \ 310 \ 320 \ 330 \ 340

(Multiple Choice)
4.8/5
(33)

Assume a project has normal cash flows.All else equal, which of the following statements is CORRECT?

(Multiple Choice)
4.9/5
(35)

Robbins Inc.is considering a project that has the following cash flow and cost of capital (r) data.What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected. r: 10.25\% Year 0 1 2 3 4 5 Cash flows -\ 1,000 \ 300 \ 300 \ 300 \ 300 \ 300

(Multiple Choice)
4.8/5
(35)

One advantage of the payback method for evaluating potential investments is that it provides information about a project's liquidity and risk.

(True/False)
4.8/5
(38)

Current Design Co.is considering two mutually exclusive, equally risky, and not repeatable projects, S and L.Their cash flows are shown below.The CEO believes the IRR is the best selection criterion, while the CFO advocates the NPV.If the decision is made by choosing the project with the higher IRR rather than the one with the higher NPV, how much, if any, value will be forgone, i.e., what's the chosen NPV versus the maximum possible NPV? Note that (1) "true value" is measured by NPV, and (2) under some conditions the choice of IRR vs.NPV will have no effect on the value gained or lost. r: 7.50\% Y ear 0 1 2 3 4 -\ 1,100 \ 550 \ 600 \ 100 \ 100 -\ 2,700 \ 650 \ 725 \ 800 \ 1,400

(Multiple Choice)
4.8/5
(38)

Projects S and L are both normal projects with an initial cost of $10,000, followed by a series of positive cash inflows.Project S's undiscounted net cash flows total $20,000, while L's total undiscounted flows are $30,000.At a cost of capital of 10%, the two projects have identical NPVs.Which project's NPV is more sensitive to changes in the cost of capital?

(Multiple Choice)
4.7/5
(36)

Lancaster Corp.is considering two equally risky, mutually exclusive projects, both of which have normal cash flows.Project A has an IRR of 11%, while Project B's IRR is 14%.When the cost of capital is 8%, the projects have the same NPV.Given this information, which of the following statements is CORRECT?

(Multiple Choice)
4.9/5
(34)

For a project with one initial cash outflow followed by a series of positive cash inflows, the modified IRR (MIRR) method involves compounding the cash inflows out to the end of the project's life, summing those compounded cash flows to form a terminal value (TV), and then finding the discount rate that causes the PV of the TV to equal the project's cost.

(True/False)
4.9/5
(39)

Which of the following statements is CORRECT?

(Multiple Choice)
4.9/5
(30)

Which of the following statements is CORRECT?

(Multiple Choice)
4.8/5
(35)

Consider projects S and L.Both have normal cash flows, and the projects have the same risk, hence both are evaluated with the same cost of capital, 10%.However, S has a higher IRR than L.Which of the following statements is CORRECT?

(Multiple Choice)
4.7/5
(35)

Which of the following statements is CORRECT?

(Multiple Choice)
4.8/5
(44)

Both the regular and the modified IRR (MIRR) methods have wide appeal to professors, but most business executives prefer the NPV method to either of the IRR methods.

(True/False)
4.7/5
(28)

Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows.

(Multiple Choice)
4.8/5
(42)

The NPV method is based on the assumption that projects' cash flows are reinvested at the project's risk-adjusted cost of capital.

(True/False)
4.8/5
(36)

If the IRR of normal Project X is greater than the IRR of mutually exclusive (and also normal) Project Y, we can conclude that the firm should always select X rather than Y if X has NPV > 0.

(True/False)
5.0/5
(43)

Shannon Co.is considering a project that has the following cash flow and cost of capital (r) data.What is the project's discounted payback? r=10.00\% Year 0 1 2 3 4 Cash flows -\ 950 \ 525 \ 485 \ 445 \ 405

(Multiple Choice)
4.8/5
(36)

The IRR method is based on the assumption that projects' cash flows are reinvested at the project's risk-adjusted cost of capital.

(True/False)
4.8/5
(31)
Showing 61 - 80 of 107
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)