Exam 23: Performance and Remedies

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Liquidated damages are not permitted under the UCC.

Free
(True/False)
4.8/5
(34)
Correct Answer:
Verified

False

If a contract does not provide for a time for inspection,the UCC allows inspection to take place

Free
(Multiple Choice)
4.8/5
(38)
Correct Answer:
Verified

A

Buyer Bob breaches his contract for the sale of goods with Seller Suzie.Suzie still has possession of the goods at the time of the breach.Suzie can refuse to deliver the goods and

Free
(Multiple Choice)
4.8/5
(46)
Correct Answer:
Verified

C

What is the "perfect tender rule" and what restrictions has the UCC put into place that limit the perfect tender rule's effect?

(Essay)
4.8/5
(35)

A court order requiring the seller to perform as promised is called

(Multiple Choice)
4.9/5
(29)

A buyer may revoke an acceptance of goods if

(Multiple Choice)
4.9/5
(41)

A seller may not make repairs or adjustments after the goods have been tendered,even if that action will bring the goods into conformity in order to "cure" nonconforming goods.

(True/False)
4.9/5
(40)

Bryson Hardware accepted delivery of the 50 door handles it ordered.If it later finds the handles do not conform to the contract specifications and it wants to revoke its acceptance,it may return the goods only if

(Multiple Choice)
4.8/5
(38)

If Chuck buys frozen cheese from Cheese,Inc. ,then fails to inspect the cheese within a reasonable amount of time and does not reject the shipment,Chuck has accepted the shipment even if there is non-conformity.

(True/False)
4.9/5
(36)

Reba orders a pair of custom-made cowboy boots,C.O.D.from Home on the Range Western Wear.When the boots arrive,Reba pays the carrier for the boots,then opens the package,only to discover that the boots are the wrong snake skin color and three sizes too big.At this point

(Multiple Choice)
4.9/5
(29)

Assume that Sherrie's Cherries contracts with Dessert World to sell and ship 600 pounds of cherries in three equal installments of 200 pounds each.If the first installment arrives with 5 pounds of spoilage,then Dessert World may

(Multiple Choice)
4.9/5
(28)

A baseball team ordered 500 wooden baseball bats from Bats,Inc. ,for delivery on June 1.On May 15,the ball team received 500 aluminum bats instead of the wooden ones.As of May 16,Bats,Inc.

(Multiple Choice)
4.7/5
(35)

Leonna orders five table settings of china from Elite China.Each set includes a dinner plate,cup & saucer,bowl,and dessert plate.The china is sold only in sets.When the delivery arrives,Leonna discovers that Elite China sent the wrong pattern.Leonna immediately calls Elite China and is instructed to send the shipment back.While repacking the shipment,Leonna changes her mind and decides to keep the cups and saucers.She returns everything else.Can she do this?

(Essay)
4.8/5
(28)

If applicable,course of dealing will

(Multiple Choice)
4.8/5
(32)

Wimble ordered 1,000 pro-quality luminescent orange tennis balls from Sports Unlimited at a cost of $800.On June 1,Sports Unlimited shipped standard white tennis balls,but Wimble rejected them.Wimble bought the same number of pro-quality luminescent orange balls from another supplier the same day for $650.In a suit against Sports Unlimited,Wimble may recover $800.

(True/False)
4.8/5
(33)

Family Time Restaurant has a contract with Prime Meats for Prime to deliver 100 pounds of ground sirloin twice a week for the next three months.If,on one delivery,Prime brings 95 pounds of ground chuck instead of 100 pounds of ground sirloin,

(Multiple Choice)
4.9/5
(30)

The UCC includes sections that limit the perfect tender rule's effect,and courts have a tendency to apply these limitations more enthusiastically than the rule itself.

(True/False)
4.9/5
(25)

Matson agrees to purchase 500 wooden chairs from Woodcarvers,Inc.After Woodcarvers sets the chairs aside in its warehouse,but before the risk of loss passes to Matson,the chairs are destroyed in a fire,which was not the fault of Woodcarvers.The contract between Matson and Woodcarvers is void.

(True/False)
4.7/5
(38)

Meister Bros.shipped 250 radiator belts to fill Braybon's order.Quality control measures had been in place in Meister's factory when the belts were manufactured.When Braybon received the order one day before it was due,it notified Meister that it rejected the belts because of a variation from the contract specifications.Meister,although it believed the original belts met the contract specifications,notified Braybon that it would supply conforming goods within one week.When the conforming goods arrive in one week,

(Multiple Choice)
4.7/5
(41)

Identify the possible remedies for a buyer when the seller breaches a contract.

(Essay)