Deck 9: Project Scheduling: Networks, duration Estimation, and Critical Path
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/118
Play
Full screen (f)
Deck 9: Project Scheduling: Networks, duration Estimation, and Critical Path
1
Preceding activities are those that must occur before others can be done.
True
2
Laddering is a technique that allows the project manager to redraw the network to more closely sequence project subtasks to make the overall network sequence more efficient.
True
3
The late finish times are determined by taking a(n)________ through the network.
backward pass
4
A(n)________ is a point when an activity is either started or completed.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
5
A backward pass is performed when it is necessary to undo some work that has been performed in order to complete it properly.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
6
The amount of time that an activity may be delayed from its early start without delaying the entire project is ________.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
7
Burst activities are those with two or more successor activities.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
8
A(n)________ is a project schedule whose start and finish dates reflect expected resource availability.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
9
Float is always measured in exactly the same way as slack.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
10
________ is the identification of the project objectives and the ordered activity necessary to complete the project.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
11
At a burst point in a backward pass,the largest succeeding late start becomes the late finish for that node.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
12
In assigning a value for the most pessimistic (b)duration,the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
13
Negative float exists when a project's critical path has been completed more quickly than anticipated.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
14
Hammock activities break a task into greater levels of detail so that each task is represented as two or more subtasks that each have their own duration and precedence requirements.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
15
Activity float is the difference between the late finish and early finish for the activity in question.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
16
A merge activity has two or more immediate predecessors.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
17
The PERT technique assumes that durations are more deterministic.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
18
The late start time should be calculated using a forward pass through the network.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
19
At a merge point in a forward pass,the largest preceding early finish becomes the early start for that node.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
20
You must know the mean of an activity in order to determine its standard deviation.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
21
Activities that can be worked on simultaneously are ________ activities.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
22
________ activities have two or more immediate successors.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
23
Pessimistic and optimistic values are estimated at the ________% confidence level.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
24
Concurrent activities are:
A)activities that must be done one after the other.
B)activities that can be performed at the same time.
C)activities that use labor from the same group of workers.
D)activities that use resources from the same resource pool.
A)activities that must be done one after the other.
B)activities that can be performed at the same time.
C)activities that use labor from the same group of workers.
D)activities that use resources from the same resource pool.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
25
An activity with two or more immediate predecessors is a(n):
A)merge activity.
B)burst activity.
C)float activity.
D)event.
A)merge activity.
B)burst activity.
C)float activity.
D)event.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
26
The longest route through the network is the ________.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
27
The term ordered activity means:
A)tasks must either precede or follow other tasks in project planning and management.
B)tasks cannot be performed unless the project manager issues a specific command to perform the work.
C)prior project planning removes the need for any rush so that tasks can be performed in a methodical fashion.
D)tasks are not performed unless the customer issues a specific request to perform the work.
A)tasks must either precede or follow other tasks in project planning and management.
B)tasks cannot be performed unless the project manager issues a specific command to perform the work.
C)prior project planning removes the need for any rush so that tasks can be performed in a methodical fashion.
D)tasks are not performed unless the customer issues a specific request to perform the work.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
28
In the beta distribution,the longer tail is located ________.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
29
________ activities have two or more immediate predecessors.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
30
Because an activity's pessimistic estimate may represent a much greater deviation from the most likely time than its optimistic estimate,the ________ better represents the distribution of possible alternative durations.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
31
Thanks to excessive dilly dallying,the subcontractor grossly exceeded the slack on his portion of the project,resulting in ________.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
32
Serial activities are those that:
A)flow from one to the next in sequence.
B)have sequential numbers.
C)have the same numbers.
D)should be performed simultaneously.
A)flow from one to the next in sequence.
B)have sequential numbers.
C)have the same numbers.
D)should be performed simultaneously.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
33
The amount of time an activity may be delayed from its early start without delaying the finish of the project is the:
A)delay.
B)float.
C)late start.
D)late finish.
A)delay.
B)float.
C)late start.
D)late finish.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
34
These can be located by doing a backward pass through a network.
A)critical paths
B)merge activities
C)successors
D)burst activities
A)critical paths
B)merge activities
C)successors
D)burst activities
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
35
The least amount of float is found:
A)in a resource-limited schedule.
B)after a burst activity.
C)on the critical path.
D)after a merge activity.
A)in a resource-limited schedule.
B)after a burst activity.
C)on the critical path.
D)after a merge activity.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
36
Prior to creating a network,it is important to:
A)identify all loops through activities.
B)identify the party responsible for each activity.
C)calculate the float for each activity.
D)understand the activity precedence.
A)identify all loops through activities.
B)identify the party responsible for each activity.
C)calculate the float for each activity.
D)understand the activity precedence.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
37
A sequence of activities defined by the project network logic is a(n):
A)event.
B)path.
C)node.
D)route.
A)event.
B)path.
C)node.
D)route.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
38
________ activities can be used as summaries for some subsets of the activities identified in the overall project network.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
39
There is no slack on the project ________.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
40
One of the defining points of a network,a junction point joined to some or all of the others by dependency lines,is called a(n):
A)event.
B)path.
C)node.
D)burst.
A)event.
B)path.
C)node.
D)burst.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
41
The variance of an activity is given by:
A)[1/6(b-a)]2.
B)1/6[b-a].
C)[1/36(b-a)]2.
D)1/36[b-a].
A)[1/6(b-a)]2.
B)1/6[b-a].
C)[1/36(b-a)]2.
D)1/36[b-a].
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
42
An activity has a pessimistic time that is three times as long as its most likely time and five times as long as its optimistic time.If the activity variance is 10,what is the expected time?
A)about 10 days
B)about 14 days
C)about 19 days
D)about 23 days
A)about 10 days
B)about 14 days
C)about 19 days
D)about 23 days
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
43
Ray's shipment of materials hit every red light and traffic jam on the way to the site.Upon arrival,half of the material was judged defective,necessitating a trip back to the supplier,and then the same arduous journey back to the site once the new materials were loaded.Traffic was a little better on the second round but the flat tire and subsequent repair caused as much if not more delay than the first trip.In the final analysis:
A)the project activity of Material Delivery was pretty close to the optimistic estimate.
B)the project activity of Material Delivery was pretty close to the most likely estimate.
C)the project activity of Material Delivery had a much higher variance than anticipated.
D)the project activity of Material Delivery was pretty close to the pessimistic estimate.
A)the project activity of Material Delivery was pretty close to the optimistic estimate.
B)the project activity of Material Delivery was pretty close to the most likely estimate.
C)the project activity of Material Delivery had a much higher variance than anticipated.
D)the project activity of Material Delivery was pretty close to the pessimistic estimate.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
44
The length of time expected to complete an activity assuming that its development proceeds normally is called the:
A)optimistic duration.
B)pessimistic duration.
C)most likely duration.
D)normal duration.
A)optimistic duration.
B)pessimistic duration.
C)most likely duration.
D)normal duration.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
45
What is the late start time for Activity E given the activity times and precedence requirements shown in the table? 
A)12
B)13
C)14
D)15

A)12
B)13
C)14
D)15
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
46
An activity has an optimistic time estimate of 15 days,a most likely estimate of 24 days,and a pessimistic estimate of 40 days.What is the variance of the activity?
A)4.17
B)25.17
C)17.36
D)10.33
A)4.17
B)25.17
C)17.36
D)10.33
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
47
Based on the activity network pictured,what is the best statement? 
A)Before starting Activity C,Activity A and Activity B must be completed.
B)Before starting Activity D,Activity A and Activity B need to be completed.
C)Before starting Activity E,Activity A and Activity B need to be completed.
D)Before starting Activity C,Activity A and Activity D must be completed.

A)Before starting Activity C,Activity A and Activity B must be completed.
B)Before starting Activity D,Activity A and Activity B need to be completed.
C)Before starting Activity E,Activity A and Activity B need to be completed.
D)Before starting Activity C,Activity A and Activity D must be completed.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
48
An activity has an optimistic time estimate of 7 days,a most likely estimate of 12 days,and a pessimistic estimate of 20 days.What is the expected duration of the activity?
A)13 days
B)13.5 days
C)12 days
D)12.5 days
A)13 days
B)13.5 days
C)12 days
D)12.5 days
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
49
What is the early start time for Activity D given the activity times and precedence requirements shown in the table? 
A)5
B)9
C)13
D)18

A)5
B)9
C)13
D)18
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
50
Network logic suggests that: 
A)Activity D can start any time.
B)Activity A must be complete before Activity B can be done.
C)Activities A,B and C must be complete before Activity D can be done.
D)Activity C must begin before Activity B begins.

A)Activity D can start any time.
B)Activity A must be complete before Activity B can be done.
C)Activities A,B and C must be complete before Activity D can be done.
D)Activity C must begin before Activity B begins.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
51
An activity has an optimistic time estimate of 15 days,a most likely estimate of 24 days,and a pessimistic estimate of 40 days.What is the expected duration of the activity?
A)less than 27 days but greater than or equal to 26 days
B)less than 26 days but greater than or equal to 25 days
C)less than 25 days but greater than or equal to 24 days
D)less than 24 days
A)less than 27 days but greater than or equal to 26 days
B)less than 26 days but greater than or equal to 25 days
C)less than 25 days but greater than or equal to 24 days
D)less than 24 days
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
52
Which of these statements about this network is best? 
A)Activities A and B are serial activities.
B)Activities B and C are serial activities.
C)Activities A and C are serial activities.
D)Activity D is a merge activity.

A)Activities A and B are serial activities.
B)Activities B and C are serial activities.
C)Activities A and C are serial activities.
D)Activity D is a merge activity.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
53
What is the late finish time for Activity D given the activity times and precedence requirements shown in the table? 
A)14
B)13
C)12
D)11

A)14
B)13
C)12
D)11
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
54
Based on the activity network pictured,what is the best statement? 
A)Activity C is a burst activity.
B)Activity E has one predecessor,Activity B.
C)Activity A and Activity C are merge activities.
D)There are no serial activities in this network.

A)Activity C is a burst activity.
B)Activity E has one predecessor,Activity B.
C)Activity A and Activity C are merge activities.
D)There are no serial activities in this network.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
55
What is the late start time for Activity B given the activity times and precedence requirements shown in the table? 
A)18
B)9
C)13
D)5

A)18
B)9
C)13
D)5
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
56
What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days? 
A)day 15
B)day 7
C)day 5
D)day 3

A)day 15
B)day 7
C)day 5
D)day 3
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
57
An activity has an optimistic time estimate of 7 days,a most likely estimate of 12 days,and a pessimistic estimate of 20 days.What is the expected standard deviation of the activity?
A)between 2 and 3 days
B)between 3 and 4 days
C)between 4 and 5 days
D)between 5 and 6 days
A)between 2 and 3 days
B)between 3 and 4 days
C)between 4 and 5 days
D)between 5 and 6 days
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
58
Activity Z has estimates a = 5,b = 10,m = 7;activity X has estimates a = 4,b = 11,m = 6;and activity Y has estimates a = 3,b = 12,m = 8.Which of the following statements is best?
A)Activity X is longer than Activity Y.
B)Activity X has a higher standard deviation than Activity Z.
C)Activity Z is shorter than Activity Y.
D)Activity Y has a smaller variance than Activity Z.
A)Activity X is longer than Activity Y.
B)Activity X has a higher standard deviation than Activity Z.
C)Activity Z is shorter than Activity Y.
D)Activity Y has a smaller variance than Activity Z.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
59
What is the early start time for Activity G given the activity times and precedence requirements shown in the table? 
A)14
B)15
C)16
D)17

A)14
B)15
C)16
D)17
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
60
What is the early finish time for Activity F given the activity times and precedence requirements shown in the table? 
A)17
B)12
C)13
D)26

A)17
B)12
C)13
D)26
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
61
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project? 
A)34
B)38
C)42
D)48

A)34
B)38
C)42
D)48
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
62
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D. 
A)8
B)13
C)14
D)21

A)8
B)13
C)14
D)21
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
63
Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C. 
A)12
B)13
C)14
D)15

A)12
B)13
C)14
D)15
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
64
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration,so activity C in the original project becomes two activities,C1 and C2,each of which lasts 7 days.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the difference in the late start time for activity C in the original project and activity C1 in the laddered project? 
A)3
B)5
C)7
D)9

A)3
B)5
C)7
D)9
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
65
Use the network diagram and activity lengths in the nodes to determine the late start time for activity F. 
A)21
B)24
C)26
D)23

A)21
B)24
C)26
D)23
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
66
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D. 
A)8
B)13
C)14
D)21

A)8
B)13
C)14
D)21
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
67
Use the information in the table to determine the slack time for Activity B. 
A)6 days
B)4 days
C)2 days
D)0 days

A)6 days
B)4 days
C)2 days
D)0 days
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
68
What is the float start time for Activity C given the activity times and precedence requirements shown in the table? 
A)1
B)2
C)3
D)4

A)1
B)2
C)3
D)4
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
69
What is the slack time for Activity B given the activity times and precedence requirements shown in the table? 
A)7
B)6
C)5
D)4

A)7
B)6
C)5
D)4
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
70
Use the information in the table to determine the late finish time for Activity B. 
A)day 17
B)day 26
C)day 20
D)day 23

A)day 17
B)day 26
C)day 20
D)day 23
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
71
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project? 
A)34
B)38
C)42
D)48

A)34
B)38
C)42
D)48
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
72
Use the information in the table to determine the late start time for Activity E. 
A)day 23
B)day 26
C)day 32
D)day 17

A)day 23
B)day 26
C)day 32
D)day 17
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
73
Use the information in the table to determine the early finish time for Activity D. 
A)day 23
B)day 26
C)day 29
D)day 32

A)day 23
B)day 26
C)day 29
D)day 32
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
74
What is the slack time for activity E? 
A)1 day
B)0 days
C)2 days
D)4 days

A)1 day
B)0 days
C)2 days
D)4 days
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
75
Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G. 
A)26
B)25
C)24
D)23

A)26
B)25
C)24
D)23
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
76
Use the information in the table to determine the early start time for Activity B. 
A)day 10
B)day 8
C)day 9
D)day 11

A)day 10
B)day 8
C)day 9
D)day 11
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
77
Use the network diagram and activity lengths in the nodes to determine the slack time for activity D. 
A)3
B)2
C)1
D)0

A)3
B)2
C)1
D)0
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
78
There's an old saying,"The job is not finished until the paperwork is done." From an activity network standpoint,this does not necessarily mean that the paperwork can't begin until the last non-paperwork activity is completed.It might be possible to work on some paperwork as early activities are completed.In order to depict this in an activity network:
A)hammock activities could be drawn.
B)subroutines could be added.
C)shortcuts can be added to the network.
D)laddering could be used to redraw the network.
A)hammock activities could be drawn.
B)subroutines could be added.
C)shortcuts can be added to the network.
D)laddering could be used to redraw the network.
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
79
What is the slack time for Activity C given the activity times and precedence requirements shown in the table? 
A)2
B)1
C)0
D)3

A)2
B)1
C)0
D)3
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck
80
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the expected completion time of the project? 
A)32 days
B)33 days
C)34 days
D)35 days

A)32 days
B)33 days
C)34 days
D)35 days
Unlock Deck
Unlock for access to all 118 flashcards in this deck.
Unlock Deck
k this deck