Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

What is the early start time for Activity G given the activity times and precedence requirements shown in the table? What is the early start time for Activity G given the activity times and precedence requirements shown in the table?

Free
(Multiple Choice)
4.8/5
(30)
Correct Answer:
Verified

D

A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the probability that the project is completed in 31 days? A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the probability that the project is completed in 31 days?

Free
(Multiple Choice)
4.9/5
(38)
Correct Answer:
Verified

A

An activity with two or more immediate predecessors is a(n):

Free
(Multiple Choice)
4.9/5
(31)
Correct Answer:
Verified

A

In assigning a value for the most pessimistic (b)duration,the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.

(True/False)
4.9/5
(24)

Use the information in the table to determine the late finish time for Activity B. Use the information in the table to determine the late finish time for Activity B.

(Multiple Choice)
4.9/5
(39)

A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities E and F can be represented by a hammock activity.What are the duration and the early start time associated with this hammock activity? A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities E and F can be represented by a hammock activity.What are the duration and the early start time associated with this hammock activity?

(Multiple Choice)
4.9/5
(37)

What is the slack time for activity E? What is the slack time for activity E?

(Multiple Choice)
4.8/5
(22)

Activity Z has estimates a = 5,b = 10,m = 7;activity X has estimates a = 4,b = 11,m = 6;and activity Y has estimates a = 3,b = 12,m = 8.Which of the following statements is best?

(Multiple Choice)
4.9/5
(34)

What is the early start time for Activity D given the activity times and precedence requirements shown in the table? What is the early start time for Activity D given the activity times and precedence requirements shown in the table?

(Multiple Choice)
4.9/5
(34)

The amount of time that an activity may be delayed from its early start without delaying the entire project is ________.

(Essay)
4.9/5
(33)

Preceding activities are those that must occur before others can be done.

(True/False)
4.7/5
(39)

Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration,so activity C in the original project becomes two activities,C1 and C2,each of which lasts 7 days.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the difference in the late start time for activity C in the original project and activity C1 in the laddered project? Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration,so activity C in the original project becomes two activities,C1 and C2,each of which lasts 7 days.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the difference in the late start time for activity C in the original project and activity C1 in the laddered project?

(Multiple Choice)
4.8/5
(39)

Ray's shipment of materials hit every red light and traffic jam on the way to the site.Upon arrival,half of the material was judged defective,necessitating a trip back to the supplier,and then the same arduous journey back to the site once the new materials were loaded.Traffic was a little better on the second round but the flat tire and subsequent repair caused as much if not more delay than the first trip.In the final analysis:

(Multiple Choice)
4.7/5
(38)

The term ordered activity means:

(Multiple Choice)
4.9/5
(33)

Use the network diagram and activity lengths in the nodes to determine the early start time for activity D. Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.

(Multiple Choice)
4.8/5
(35)

Based on the activity network pictured,what is the best statement? Based on the activity network pictured,what is the best statement?

(Multiple Choice)
4.8/5
(32)

________ activities have two or more immediate predecessors.

(Essay)
4.9/5
(28)

Activities C,D,and E in the project represented by the network are to be hammocked.What are the early start and late finish times of the hammock activity? Activities C,D,and E in the project represented by the network are to be hammocked.What are the early start and late finish times of the hammock activity?

(Multiple Choice)
4.8/5
(39)

Use the information in the table to determine the early start time for Activity B. Use the information in the table to determine the early start time for Activity B.

(Multiple Choice)
4.8/5
(49)

Activity float is the difference between the late finish and early finish for the activity in question.

(True/False)
4.9/5
(41)
Showing 1 - 20 of 118