Deck 12: Resource Management

Full screen (f)
exit full mode
Question
The resource usage table tells us the project team members,their assigned tasks,and the time each task is expected to take.
Use Space or
up arrow
down arrow
to flip the card.
Question
There is,for almost all projects,usually a dominant constraint that serves as the final arbiter of project decisions.
Question
In-process inventory represents the amount of work waiting to be completed but delayed due to unavailable resources.
Question
The concept of ________ refers to the amounts of individual resources that a schedule requires during specific time periods.
Question
Once Pussy Galore's Flying Circus had put the baby to sleep,the demolition experts had only one hour to access the vault at Fort Knox in order for Operation Grand Slam to be a success.Mr.Goldfinger's ambitious project was ________-constrained.
Question
The first step in the resource leveling process is to create the resource loading table.
Question
The work breakdown structure and activity networks are needed to create a resource ________ or ________.
Question
The best method for establishing the existence of resource conflicts across project activities uses resource-loading charts.
Question
Resource loading charts are used to display the amount of resources required as a function of time on a graph.
Question
If an activity can be split,only the functional portion of the original activity needs to be accomplished for the project to be fully completed.
Question
A resource loading table is created through identifying the project activities and the resources required for completion and applying this information to the project schedule baseline.
Question
In a resource constrained project,the work must be finished by a certain time,or date,as efficiently as possible.
Question
Because resource management is typically a multivariate,combinatorial problem (i.e. ,one that is characterized by multiple solutions involving literally dozens,hundreds,or even thousands of activity variables)truly correct answers are not possible.
Question
If resources have been over-allocated,the loading table must be reconfigured to eliminate resource contention points.The project manager can focus solely on the original point of contention since the activities in a project are separate entities.
Question
The ________ is primarily limited by availability of a type of labor or productive asset but may also contain some activities of work package elements that must be finished by a certain date.
Question
The idea behind resource leveling is to avoid huge swings in utilization of labor and equipment.
Question
Operation Main Strike required several tons of dynamite and a significant amount of manual labor.Max Zorin knew he had a(n)________-constrained project and also had James Bond to contend with.
Question
The problem of resource underutilization that a project manager faces when managing a single project disappears in the multi-project environment.
Question
The best method for establishing the existence of resource conflicts across project activities uses ________ to analyze project resources against scheduled activities over the project's baseline schedule.
Question
All that is needed to create a resource loading calendar is the work breakdown structure and the activity network.
Question
Which of these statements about resource management is best?

A)A mathematically optimal solution is almost always attainable and should be pursued.
B)The project manager should level resources as to maximize fluctuations from time period to time period.
C)A common approach to analyzing resource-leveling problems is to apply heuristics.
D)Resource management is usually a univariate,combinatorial problem.
Question
Which of the following would NOT typically be displayed in a resource loading table?

A)the project team members
B)the tasks the project team members have been assigned
C)the time the activities are expected to take
D)the expenses allocated to the activities
Question
A project that must be finished by December 31st is:

A)time-constrained.
B)resource-constrained.
C)mix-constrained.
D)capacity-constrained.
Question
It had been a busy week at the restaurant and as the weekend approached,the assistant manager needed to schedule seven sandwich artists during each afternoon.The only problem that he saw was that there were only five sandwich artists available,a very serious case of resource ________.
Question
One heuristic for prioritizing resource allocation is to apply resources to activities with the smallest ________,which proponents say results in the smallest schedule slippage in the overall project.
Question
Use the resource loading table to determine which of the Yaki sisters is over-allocated. <strong>Use the resource loading table to determine which of the Yaki sisters is over-allocated.  </strong> A)Suki B)Terri C)both D)Can't be determined from the information provided. <div style=padding-top: 35px>

A)Suki
B)Terri
C)both
D)Can't be determined from the information provided.
Question
The bulldozer was unavailable which meant a few critical tasks could not be completed.This resulted in an increase in ________.
Question
________ are used to display the amount of resources required as a function of time on a graph.
Question
The best method for establishing the existence of resource conflicts across project activities uses:

A)Gantt charts.
B)network diagrams.
C)Pareto diagrams.
D)resource loading charts.
Question
A resource loading form is also known as a(n):

A)load schedule.
B)resource usage calendar.
C)activity resource schedule.
D)network resource profile.
Question
________ an activity means interrupting the continuous stream of work on an activity at some midpoint in its development process and applying that resource to another activity for some time period before returning the resource to complete the original task.
Question
The amounts of individual resources that a schedule requires during specific time periods is referred to as the resource's:

A)loading.
B)capacity.
C)constraint.
D)drag.
Question
As resource leveling proceeds,a(n)________ commonly occurs when the resource schedule is reworked to eliminate sources of resource conflict.
Question
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the shortest duration? <strong>The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the shortest duration?  </strong> A)Activity A B)Activity B C)Activity C D)Activity D <div style=padding-top: 35px>

A)Activity A
B)Activity B
C)Activity C
D)Activity D
Question
The One Shovel Construction Company is hired by the City of Edmond to lay sewer pipe from the east end of town to the west end of town.While the crew would like to begin at both ends simultaneously and have a dramatic ceremony when both ends meet,they find themselves with a bit of a:

A)time constraint.
B)resource constraint.
C)mixed constraint.
D)partial network.
Question
________ is the process that addresses the complex challenges of project constraints as to minimize the effects of resource demands across the project's life cycle.
Question
The assistant professor frantically prepared his tenure and promotion dossier for the personnel committee.The deadline loomed and he had several other things to accomplish - deadlines for papers and key correspondence that demanded replies.By his reckoning,he probably didn't have enough toner,paper,or computing time available to accomplish all that he had left to do.His project is unfortunately a:

A)time constrained one.
B)resource constrained one.
C)mix-constrained one.
D)personally constrained one.
Question
The process that addresses the complex challenges of project constraints is known as:

A)TOC.
B)resource leveling.
C)constraint scheduling.
D)resource scheduling.
Question
A resource loading form can be generated once you have developed:

A)the activity network and productivity profile.
B)the work breakdown structure and the project budget.
C)the activity network and the work breakdown structure.
D)the project budget and the productivity profile.
Question
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the smallest amount of slack? <strong>The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the smallest amount of slack?  </strong> A)Activity A B)Activity B C)Activity C D)Activity D <div style=padding-top: 35px>

A)Activity A
B)Activity B
C)Activity C
D)Activity D
Question
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage?  </strong> A)week 3 B)week 2 C)week 9 D)week 8 <div style=padding-top: 35px>

A)week 3
B)week 2
C)week 9
D)week 8
Question
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage?  </strong> A)week 6 B)week 2 C)week 4 D)week 3 <div style=padding-top: 35px>

A)week 6
B)week 2
C)week 4
D)week 3
Question
A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the lowest resource requirements? <strong>A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the lowest resource requirements?  </strong> A)day 21 B)day 18 C)day 24 D)day 15 <div style=padding-top: 35px>

A)day 21
B)day 18
C)day 24
D)day 15
Question
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage?  </strong> A)week 6 B)week 2 C)week 4 D)week 3 <div style=padding-top: 35px>

A)week 6
B)week 2
C)week 4
D)week 3
Question
Use the project described in the table to determine the total resources required for this project during week 2 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis. <strong>Use the project described in the table to determine the total resources required for this project during week 2 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis.  </strong> A)30 hours B)20 hours C)40 hours D)36 hours <div style=padding-top: 35px>

A)30 hours
B)20 hours
C)40 hours
D)36 hours
Question
Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day)on this project. <strong>Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day)on this project.  </strong> A)6 hours B)40 hours C)24 hours D)48 hours <div style=padding-top: 35px>

A)6 hours
B)40 hours
C)24 hours
D)48 hours
Question
Use the project described in the table to determine the total resources required for this project if a worker is expected to devote half-time (four hours per day)to this project. <strong>Use the project described in the table to determine the total resources required for this project if a worker is expected to devote half-time (four hours per day)to this project.  </strong> A)36 hours B)40 hours C)64 hours D)128 hours <div style=padding-top: 35px>

A)36 hours
B)40 hours
C)64 hours
D)128 hours
Question
Use the project described in the table to determine the total resources required for this project during week 1 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis. <strong>Use the project described in the table to determine the total resources required for this project during week 1 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis.  </strong> A)40 hours B)20 hours C)28 hours D)36 hours <div style=padding-top: 35px>

A)40 hours
B)20 hours
C)28 hours
D)36 hours
Question
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the lowest activity identification number? <strong>The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the lowest activity identification number?  </strong> A)Activity A B)Activity B C)Activity C D)Activity D <div style=padding-top: 35px>

A)Activity A
B)Activity B
C)Activity C
D)Activity D
Question
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for activity G? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for activity G?  </strong> A)22 hours B)88 hours C)44 hours D)132 hours <div style=padding-top: 35px>

A)22 hours
B)88 hours
C)44 hours
D)132 hours
Question
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.If the project manager is told that the total number of hours per week cannot exceed 48,what is the first week that some resource leveling must occur? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.If the project manager is told that the total number of hours per week cannot exceed 48,what is the first week that some resource leveling must occur?  </strong> A)week 2 B)week 6 C)week 4 D)week 5 <div style=padding-top: 35px>

A)week 2
B)week 6
C)week 4
D)week 5
Question
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the greatest number of successor tasks? <strong>The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the greatest number of successor tasks?  </strong> A)Activity A B)Activity B C)Activity C D)Activity D <div style=padding-top: 35px>

A)Activity A
B)Activity B
C)Activity C
D)Activity D
Question
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage?  </strong> A)week 4 B)week 5 C)week 6 D)week 7 <div style=padding-top: 35px>

A)week 4
B)week 5
C)week 6
D)week 7
Question
A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.Which activity should be left alone if at all possible in the adjustment process among the candidates? <strong>A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.Which activity should be left alone if at all possible in the adjustment process among the candidates?  </strong> A)Activity D B)Activity C C)Activity F D)Activity E <div style=padding-top: 35px>

A)Activity D
B)Activity C
C)Activity F
D)Activity E
Question
Use the project described in the table to determine the total resources required for this project on day 2 if a worker is expected to devote half-time (four hours per day)to this project. <strong>Use the project described in the table to determine the total resources required for this project on day 2 if a worker is expected to devote half-time (four hours per day)to this project.  </strong> A)4 hours B)2 hours C)8 hours D)6 hours <div style=padding-top: 35px>

A)4 hours
B)2 hours
C)8 hours
D)6 hours
Question
Use the project described in the table to determine the total resources required for this project on day 10 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis. <strong>Use the project described in the table to determine the total resources required for this project on day 10 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis.  </strong> A)5 hours B)10 hours C)4 hours D)8 hours <div style=padding-top: 35px>

A)5 hours
B)10 hours
C)4 hours
D)8 hours
Question
A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.What activities are involved in the first resource problem in this schedule? <strong>A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.What activities are involved in the first resource problem in this schedule?  </strong> A)Activities A,B,and C B)Activities B,C,and D C)Activities C,D,and E D)Activities D,E,and F <div style=padding-top: 35px>

A)Activities A,B,and C
B)Activities B,C,and D
C)Activities C,D,and E
D)Activities D,E,and F
Question
A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the lowest resource requirements? <strong>A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the lowest resource requirements?  </strong> A)day 15 B)day 19 C)day 24 D)day 29 <div style=padding-top: 35px>

A)day 15
B)day 19
C)day 24
D)day 29
Question
A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the highest resource requirements? <strong>A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the highest resource requirements?  </strong> A)day 21 B)day 18 C)day 24 D)day 15 <div style=padding-top: 35px>

A)day 21
B)day 18
C)day 24
D)day 15
Question
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for the project? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for the project?  </strong> A)365 hours B)335 hours C)320 hours D)310 hours <div style=padding-top: 35px>

A)365 hours
B)335 hours
C)320 hours
D)310 hours
Question
A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the highest resource requirements? <strong>A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the highest resource requirements?  </strong> A)day 5 B)day 10 C)day 15 D)day 20 <div style=padding-top: 35px>

A)day 5
B)day 10
C)day 15
D)day 20
Question
A resource loading chart displays:

A)the amount of time needed as a function of resource limits.
B)the amount of resources required as a function of time.
C)the amount of time needed as a function of money.
D)the amount of resources needed as a function of money.
Question
Use this activity precedence table to create a resource loading profile.Activity lengths are given in days and an 8-hour day is assumed.
Use this activity precedence table to create a resource loading profile.Activity lengths are given in days and an 8-hour day is assumed.  <div style=padding-top: 35px>
Question
What are any four heuristics for prioritizing resource allocation to activities? Why would a project manager choose one above another?
Question
Consider the portfolio of projects described in the table.The resource requirements are in numbers of labor hours.The Greatest Resource Utilization rule would begin work with project: <strong>Consider the portfolio of projects described in the table.The resource requirements are in numbers of labor hours.The Greatest Resource Utilization rule would begin work with project:  </strong> A)A. B)B. C)C. D)D. <div style=padding-top: 35px>

A)A.
B)B.
C)C.
D)D.
Question
Consider the portfolio of projects described in the table.The resource requirements are in numbers of labor hours.The First in Line rule would begin work with project: <strong>Consider the portfolio of projects described in the table.The resource requirements are in numbers of labor hours.The First in Line rule would begin work with project:  </strong> A)A. B)B. C)C. D)D. <div style=padding-top: 35px>

A)A.
B)B.
C)C.
D)D.
Question
Excessive in-process inventory is often caused by:

A)schedule slippage.
B)over-ordering supplies.
C)lack of available resources.
D)too much labor.
Question
Consider the portfolio of projects described in the table.The resource requirements are in numbers of labor hours.The Greatest Resource Demand rule would begin work with project: <strong>Consider the portfolio of projects described in the table.The resource requirements are in numbers of labor hours.The Greatest Resource Demand rule would begin work with project:  </strong> A)A. B)B. C)C. D)D. <div style=padding-top: 35px>

A)A.
B)B.
C)C.
D)D.
Question
The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.The first activities that are strong candidates for shifting are: <strong>The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.The first activities that are strong candidates for shifting are:  </strong> A)Activity A B)Activities B and C C)Activities D and E D)Activity E and F <div style=padding-top: 35px>

A)Activity A
B)Activities B and C
C)Activities D and E
D)Activity E and F
Question
The Minimum Late Finish Time rule stipulates that:

A)the earliest late finishers are scheduled last.
B)the latest early finishers are scheduled first.
C)the earliest late finishers are scheduled first.
D)the latest late finishers are scheduled first.
Question
The amount of work waiting to be completed but delayed due to unavailable resources is known as:

A)resource utilization.
B)in-process inventory.
C)resource underutilization.
D)efficiency.
Question
A project consisting of six activities is shown in the table.The project manager must achieve the lowest possible maximum resource requirement while adhering to a 34-day deadline.The lowest possible peak resource demand occurs: <strong>A project consisting of six activities is shown in the table.The project manager must achieve the lowest possible maximum resource requirement while adhering to a 34-day deadline.The lowest possible peak resource demand occurs:  </strong> A)on days 19 through 20 for an early start schedule. B)on days 17 through 20 for a late start schedule. C)on days 13 through 18 for an early start schedule. D)on days 21 through 22 for a late start schedule. <div style=padding-top: 35px>

A)on days 19 through 20 for an early start schedule.
B)on days 17 through 20 for a late start schedule.
C)on days 13 through 18 for an early start schedule.
D)on days 21 through 22 for a late start schedule.
Question
The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.Which activity could be split to help the project team finish on time and meet the resource cap? <strong>The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.Which activity could be split to help the project team finish on time and meet the resource cap?  </strong> A)Activity A B)Activities B and C C)Activities D and E D)Activity E and F <div style=padding-top: 35px>

A)Activity A
B)Activities B and C
C)Activities D and E
D)Activity E and F
Question
Use this resource load chart to determine which activity uses the fewest resources. <strong>Use this resource load chart to determine which activity uses the fewest resources.  </strong> A)Activity A B)Activity B C)Activity C D)Activity D <div style=padding-top: 35px>

A)Activity A
B)Activity B
C)Activity C
D)Activity D
Question
Splitting activities refers to:

A)assigning the work to two or more workers.
B)assigning the work to two or more days.
C)starting an activity,interrupting it to use a resource elsewhere,and then returning to work on the activity.
D)breaking each non-critical activity into two or more components and subdividing the resources they use by a similar divisor.
Question
Use this resource load chart to determine which activity is the longest in duration. <strong>Use this resource load chart to determine which activity is the longest in duration.  </strong> A)Activity A B)Activity B C)Activity C D)Activity D <div style=padding-top: 35px>

A)Activity A
B)Activity B
C)Activity C
D)Activity D
Question
Describe resource leveling;its objectives and the basic five-step technique to perform it.
Question
Mathematical programming is sometimes used to generate optimal solutions to resource constrained problems in a multi-project setting but suffers from:

A)an inability to model project and activity due dates.
B)resource substitution.
C)resource constraints.
D)problem complexity.
Question
Use this resource load chart to determine which activity uses the greatest number of resources. <strong>Use this resource load chart to determine which activity uses the greatest number of resources.  </strong> A)Activity A B)Activity B C)Activity C D)Activity D <div style=padding-top: 35px>

A)Activity A
B)Activity B
C)Activity C
D)Activity D
Question
What are the three types of constraints that projects face;provide examples and suggest ways to address these constraints?
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/93
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 12: Resource Management
1
The resource usage table tells us the project team members,their assigned tasks,and the time each task is expected to take.
True
2
There is,for almost all projects,usually a dominant constraint that serves as the final arbiter of project decisions.
True
3
In-process inventory represents the amount of work waiting to be completed but delayed due to unavailable resources.
True
4
The concept of ________ refers to the amounts of individual resources that a schedule requires during specific time periods.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
5
Once Pussy Galore's Flying Circus had put the baby to sleep,the demolition experts had only one hour to access the vault at Fort Knox in order for Operation Grand Slam to be a success.Mr.Goldfinger's ambitious project was ________-constrained.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
6
The first step in the resource leveling process is to create the resource loading table.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
7
The work breakdown structure and activity networks are needed to create a resource ________ or ________.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
8
The best method for establishing the existence of resource conflicts across project activities uses resource-loading charts.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
9
Resource loading charts are used to display the amount of resources required as a function of time on a graph.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
10
If an activity can be split,only the functional portion of the original activity needs to be accomplished for the project to be fully completed.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
11
A resource loading table is created through identifying the project activities and the resources required for completion and applying this information to the project schedule baseline.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
12
In a resource constrained project,the work must be finished by a certain time,or date,as efficiently as possible.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
13
Because resource management is typically a multivariate,combinatorial problem (i.e. ,one that is characterized by multiple solutions involving literally dozens,hundreds,or even thousands of activity variables)truly correct answers are not possible.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
14
If resources have been over-allocated,the loading table must be reconfigured to eliminate resource contention points.The project manager can focus solely on the original point of contention since the activities in a project are separate entities.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
15
The ________ is primarily limited by availability of a type of labor or productive asset but may also contain some activities of work package elements that must be finished by a certain date.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
16
The idea behind resource leveling is to avoid huge swings in utilization of labor and equipment.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
17
Operation Main Strike required several tons of dynamite and a significant amount of manual labor.Max Zorin knew he had a(n)________-constrained project and also had James Bond to contend with.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
18
The problem of resource underutilization that a project manager faces when managing a single project disappears in the multi-project environment.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
19
The best method for establishing the existence of resource conflicts across project activities uses ________ to analyze project resources against scheduled activities over the project's baseline schedule.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
20
All that is needed to create a resource loading calendar is the work breakdown structure and the activity network.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
21
Which of these statements about resource management is best?

A)A mathematically optimal solution is almost always attainable and should be pursued.
B)The project manager should level resources as to maximize fluctuations from time period to time period.
C)A common approach to analyzing resource-leveling problems is to apply heuristics.
D)Resource management is usually a univariate,combinatorial problem.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
22
Which of the following would NOT typically be displayed in a resource loading table?

A)the project team members
B)the tasks the project team members have been assigned
C)the time the activities are expected to take
D)the expenses allocated to the activities
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
23
A project that must be finished by December 31st is:

A)time-constrained.
B)resource-constrained.
C)mix-constrained.
D)capacity-constrained.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
24
It had been a busy week at the restaurant and as the weekend approached,the assistant manager needed to schedule seven sandwich artists during each afternoon.The only problem that he saw was that there were only five sandwich artists available,a very serious case of resource ________.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
25
One heuristic for prioritizing resource allocation is to apply resources to activities with the smallest ________,which proponents say results in the smallest schedule slippage in the overall project.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
26
Use the resource loading table to determine which of the Yaki sisters is over-allocated. <strong>Use the resource loading table to determine which of the Yaki sisters is over-allocated.  </strong> A)Suki B)Terri C)both D)Can't be determined from the information provided.

A)Suki
B)Terri
C)both
D)Can't be determined from the information provided.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
27
The bulldozer was unavailable which meant a few critical tasks could not be completed.This resulted in an increase in ________.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
28
________ are used to display the amount of resources required as a function of time on a graph.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
29
The best method for establishing the existence of resource conflicts across project activities uses:

A)Gantt charts.
B)network diagrams.
C)Pareto diagrams.
D)resource loading charts.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
30
A resource loading form is also known as a(n):

A)load schedule.
B)resource usage calendar.
C)activity resource schedule.
D)network resource profile.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
31
________ an activity means interrupting the continuous stream of work on an activity at some midpoint in its development process and applying that resource to another activity for some time period before returning the resource to complete the original task.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
32
The amounts of individual resources that a schedule requires during specific time periods is referred to as the resource's:

A)loading.
B)capacity.
C)constraint.
D)drag.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
33
As resource leveling proceeds,a(n)________ commonly occurs when the resource schedule is reworked to eliminate sources of resource conflict.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
34
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the shortest duration? <strong>The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the shortest duration?  </strong> A)Activity A B)Activity B C)Activity C D)Activity D

A)Activity A
B)Activity B
C)Activity C
D)Activity D
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
35
The One Shovel Construction Company is hired by the City of Edmond to lay sewer pipe from the east end of town to the west end of town.While the crew would like to begin at both ends simultaneously and have a dramatic ceremony when both ends meet,they find themselves with a bit of a:

A)time constraint.
B)resource constraint.
C)mixed constraint.
D)partial network.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
36
________ is the process that addresses the complex challenges of project constraints as to minimize the effects of resource demands across the project's life cycle.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
37
The assistant professor frantically prepared his tenure and promotion dossier for the personnel committee.The deadline loomed and he had several other things to accomplish - deadlines for papers and key correspondence that demanded replies.By his reckoning,he probably didn't have enough toner,paper,or computing time available to accomplish all that he had left to do.His project is unfortunately a:

A)time constrained one.
B)resource constrained one.
C)mix-constrained one.
D)personally constrained one.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
38
The process that addresses the complex challenges of project constraints is known as:

A)TOC.
B)resource leveling.
C)constraint scheduling.
D)resource scheduling.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
39
A resource loading form can be generated once you have developed:

A)the activity network and productivity profile.
B)the work breakdown structure and the project budget.
C)the activity network and the work breakdown structure.
D)the project budget and the productivity profile.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
40
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the smallest amount of slack? <strong>The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the smallest amount of slack?  </strong> A)Activity A B)Activity B C)Activity C D)Activity D

A)Activity A
B)Activity B
C)Activity C
D)Activity D
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
41
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage?  </strong> A)week 3 B)week 2 C)week 9 D)week 8

A)week 3
B)week 2
C)week 9
D)week 8
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
42
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage?  </strong> A)week 6 B)week 2 C)week 4 D)week 3

A)week 6
B)week 2
C)week 4
D)week 3
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
43
A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the lowest resource requirements? <strong>A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the lowest resource requirements?  </strong> A)day 21 B)day 18 C)day 24 D)day 15

A)day 21
B)day 18
C)day 24
D)day 15
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
44
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage?  </strong> A)week 6 B)week 2 C)week 4 D)week 3

A)week 6
B)week 2
C)week 4
D)week 3
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
45
Use the project described in the table to determine the total resources required for this project during week 2 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis. <strong>Use the project described in the table to determine the total resources required for this project during week 2 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis.  </strong> A)30 hours B)20 hours C)40 hours D)36 hours

A)30 hours
B)20 hours
C)40 hours
D)36 hours
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
46
Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day)on this project. <strong>Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day)on this project.  </strong> A)6 hours B)40 hours C)24 hours D)48 hours

A)6 hours
B)40 hours
C)24 hours
D)48 hours
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
47
Use the project described in the table to determine the total resources required for this project if a worker is expected to devote half-time (four hours per day)to this project. <strong>Use the project described in the table to determine the total resources required for this project if a worker is expected to devote half-time (four hours per day)to this project.  </strong> A)36 hours B)40 hours C)64 hours D)128 hours

A)36 hours
B)40 hours
C)64 hours
D)128 hours
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
48
Use the project described in the table to determine the total resources required for this project during week 1 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis. <strong>Use the project described in the table to determine the total resources required for this project during week 1 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis.  </strong> A)40 hours B)20 hours C)28 hours D)36 hours

A)40 hours
B)20 hours
C)28 hours
D)36 hours
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
49
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the lowest activity identification number? <strong>The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the lowest activity identification number?  </strong> A)Activity A B)Activity B C)Activity C D)Activity D

A)Activity A
B)Activity B
C)Activity C
D)Activity D
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
50
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for activity G? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for activity G?  </strong> A)22 hours B)88 hours C)44 hours D)132 hours

A)22 hours
B)88 hours
C)44 hours
D)132 hours
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
51
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.If the project manager is told that the total number of hours per week cannot exceed 48,what is the first week that some resource leveling must occur? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.If the project manager is told that the total number of hours per week cannot exceed 48,what is the first week that some resource leveling must occur?  </strong> A)week 2 B)week 6 C)week 4 D)week 5

A)week 2
B)week 6
C)week 4
D)week 5
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
52
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the greatest number of successor tasks? <strong>The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the greatest number of successor tasks?  </strong> A)Activity A B)Activity B C)Activity C D)Activity D

A)Activity A
B)Activity B
C)Activity C
D)Activity D
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
53
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage?  </strong> A)week 4 B)week 5 C)week 6 D)week 7

A)week 4
B)week 5
C)week 6
D)week 7
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
54
A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.Which activity should be left alone if at all possible in the adjustment process among the candidates? <strong>A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.Which activity should be left alone if at all possible in the adjustment process among the candidates?  </strong> A)Activity D B)Activity C C)Activity F D)Activity E

A)Activity D
B)Activity C
C)Activity F
D)Activity E
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
55
Use the project described in the table to determine the total resources required for this project on day 2 if a worker is expected to devote half-time (four hours per day)to this project. <strong>Use the project described in the table to determine the total resources required for this project on day 2 if a worker is expected to devote half-time (four hours per day)to this project.  </strong> A)4 hours B)2 hours C)8 hours D)6 hours

A)4 hours
B)2 hours
C)8 hours
D)6 hours
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
56
Use the project described in the table to determine the total resources required for this project on day 10 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis. <strong>Use the project described in the table to determine the total resources required for this project on day 10 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis.  </strong> A)5 hours B)10 hours C)4 hours D)8 hours

A)5 hours
B)10 hours
C)4 hours
D)8 hours
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
57
A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.What activities are involved in the first resource problem in this schedule? <strong>A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.What activities are involved in the first resource problem in this schedule?  </strong> A)Activities A,B,and C B)Activities B,C,and D C)Activities C,D,and E D)Activities D,E,and F

A)Activities A,B,and C
B)Activities B,C,and D
C)Activities C,D,and E
D)Activities D,E,and F
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
58
A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the lowest resource requirements? <strong>A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the lowest resource requirements?  </strong> A)day 15 B)day 19 C)day 24 D)day 29

A)day 15
B)day 19
C)day 24
D)day 29
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
59
A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the highest resource requirements? <strong>A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the highest resource requirements?  </strong> A)day 21 B)day 18 C)day 24 D)day 15

A)day 21
B)day 18
C)day 24
D)day 15
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
60
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for the project? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for the project?  </strong> A)365 hours B)335 hours C)320 hours D)310 hours

A)365 hours
B)335 hours
C)320 hours
D)310 hours
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
61
A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the highest resource requirements? <strong>A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the highest resource requirements?  </strong> A)day 5 B)day 10 C)day 15 D)day 20

A)day 5
B)day 10
C)day 15
D)day 20
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
62
A resource loading chart displays:

A)the amount of time needed as a function of resource limits.
B)the amount of resources required as a function of time.
C)the amount of time needed as a function of money.
D)the amount of resources needed as a function of money.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
63
Use this activity precedence table to create a resource loading profile.Activity lengths are given in days and an 8-hour day is assumed.
Use this activity precedence table to create a resource loading profile.Activity lengths are given in days and an 8-hour day is assumed.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
64
What are any four heuristics for prioritizing resource allocation to activities? Why would a project manager choose one above another?
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
65
Consider the portfolio of projects described in the table.The resource requirements are in numbers of labor hours.The Greatest Resource Utilization rule would begin work with project: <strong>Consider the portfolio of projects described in the table.The resource requirements are in numbers of labor hours.The Greatest Resource Utilization rule would begin work with project:  </strong> A)A. B)B. C)C. D)D.

A)A.
B)B.
C)C.
D)D.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
66
Consider the portfolio of projects described in the table.The resource requirements are in numbers of labor hours.The First in Line rule would begin work with project: <strong>Consider the portfolio of projects described in the table.The resource requirements are in numbers of labor hours.The First in Line rule would begin work with project:  </strong> A)A. B)B. C)C. D)D.

A)A.
B)B.
C)C.
D)D.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
67
Excessive in-process inventory is often caused by:

A)schedule slippage.
B)over-ordering supplies.
C)lack of available resources.
D)too much labor.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
68
Consider the portfolio of projects described in the table.The resource requirements are in numbers of labor hours.The Greatest Resource Demand rule would begin work with project: <strong>Consider the portfolio of projects described in the table.The resource requirements are in numbers of labor hours.The Greatest Resource Demand rule would begin work with project:  </strong> A)A. B)B. C)C. D)D.

A)A.
B)B.
C)C.
D)D.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
69
The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.The first activities that are strong candidates for shifting are: <strong>The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.The first activities that are strong candidates for shifting are:  </strong> A)Activity A B)Activities B and C C)Activities D and E D)Activity E and F

A)Activity A
B)Activities B and C
C)Activities D and E
D)Activity E and F
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
70
The Minimum Late Finish Time rule stipulates that:

A)the earliest late finishers are scheduled last.
B)the latest early finishers are scheduled first.
C)the earliest late finishers are scheduled first.
D)the latest late finishers are scheduled first.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
71
The amount of work waiting to be completed but delayed due to unavailable resources is known as:

A)resource utilization.
B)in-process inventory.
C)resource underutilization.
D)efficiency.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
72
A project consisting of six activities is shown in the table.The project manager must achieve the lowest possible maximum resource requirement while adhering to a 34-day deadline.The lowest possible peak resource demand occurs: <strong>A project consisting of six activities is shown in the table.The project manager must achieve the lowest possible maximum resource requirement while adhering to a 34-day deadline.The lowest possible peak resource demand occurs:  </strong> A)on days 19 through 20 for an early start schedule. B)on days 17 through 20 for a late start schedule. C)on days 13 through 18 for an early start schedule. D)on days 21 through 22 for a late start schedule.

A)on days 19 through 20 for an early start schedule.
B)on days 17 through 20 for a late start schedule.
C)on days 13 through 18 for an early start schedule.
D)on days 21 through 22 for a late start schedule.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
73
The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.Which activity could be split to help the project team finish on time and meet the resource cap? <strong>The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.Which activity could be split to help the project team finish on time and meet the resource cap?  </strong> A)Activity A B)Activities B and C C)Activities D and E D)Activity E and F

A)Activity A
B)Activities B and C
C)Activities D and E
D)Activity E and F
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
74
Use this resource load chart to determine which activity uses the fewest resources. <strong>Use this resource load chart to determine which activity uses the fewest resources.  </strong> A)Activity A B)Activity B C)Activity C D)Activity D

A)Activity A
B)Activity B
C)Activity C
D)Activity D
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
75
Splitting activities refers to:

A)assigning the work to two or more workers.
B)assigning the work to two or more days.
C)starting an activity,interrupting it to use a resource elsewhere,and then returning to work on the activity.
D)breaking each non-critical activity into two or more components and subdividing the resources they use by a similar divisor.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
76
Use this resource load chart to determine which activity is the longest in duration. <strong>Use this resource load chart to determine which activity is the longest in duration.  </strong> A)Activity A B)Activity B C)Activity C D)Activity D

A)Activity A
B)Activity B
C)Activity C
D)Activity D
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
77
Describe resource leveling;its objectives and the basic five-step technique to perform it.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
78
Mathematical programming is sometimes used to generate optimal solutions to resource constrained problems in a multi-project setting but suffers from:

A)an inability to model project and activity due dates.
B)resource substitution.
C)resource constraints.
D)problem complexity.
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
79
Use this resource load chart to determine which activity uses the greatest number of resources. <strong>Use this resource load chart to determine which activity uses the greatest number of resources.  </strong> A)Activity A B)Activity B C)Activity C D)Activity D

A)Activity A
B)Activity B
C)Activity C
D)Activity D
Unlock Deck
Unlock for access to all 93 flashcards in this deck.
Unlock Deck
k this deck
80
What are the three types of constraints that projects face;provide examples and suggest ways to address these constraints?