Deck 18: Standard Costing and Variance Analysis 2: Further Aspects

Full screen (f)
exit full mode
Question
Figure 18-2
Allende Company has developed capacity standards. Information is as follows for a value-added activity:  Activity capacity acquired 60 Activity capacity used 50 Actual activity usage 30 Standard fixed activity rate £2,000\begin{array}{lr}\text { Activity capacity acquired } & 60 \\\text { Activity capacity used } & 50 \\\text { Actual activity usage } & 30 \\\text { Standard fixed activity rate } & £ 2,000\end{array}

-Refer to Figure 18-2. The unused capacity variance is

A)£20,000 favourable.
B)£40,000 favourable.
C)£60,000 favourable.
D)There is no variance.
Use Space or
up arrow
down arrow
to flip the card.
Question
Figure 18-1
Froelech Company has developed capacity standards. Information is as follows:  Standard cost of the activity capacity acquired £150,000 Standard cost of the activity capacity used 100,000 Standard cost of the actual activity used 120,000\begin{array}{lr}\text { Standard cost of the activity capacity acquired } & £ 150,000 \\\text { Standard cost of the activity capacity used } & 100,000 \\\text { Standard cost of the actual activity used } & 120,000\end{array}

-Refer to Figure 18-1. The unused capacity variance is

A)£20,000 favourable.
B)£30,000 favourable.
C)£50,000 favourable.
D)There is no variance.
Question
When should variances be investigated?

A)when they fall out of the accepted range or the control limit
B)when the variances are unfavourable
C)when the variances are over £10,000
D)All variances should be investigated.
Question
Figure 18-4
Regis Ltd. uses two materials in the production of its product. The materials, X and Y, have the following standards:  Material  Standard Mix  Standard Unit Price  Standard Cost X3,500 units £1.00 per unit £3,500Y1,500 units 3.00 per unit £4,500 Yield 4,000 units \begin{array}{cccc}\text { Material } & \text { Standard Mix } & \text { Standard Unit Price } & \text { Standard Cost } \\\mathrm{X} & 3,500 \text { units } & £ 1.00 \text { per unit } & £ 3,500 \\\mathrm{Y} & 1,500 \text { units } & 3.00 \text { per unit } & £ 4,500\\\text { Yield }& 4,000 \text { units }\end{array} During April, the following actual production information was provided:  Material  Actual Mix X30,000 units Y20,000 units  Yield 36,000 units \begin{array}{cc}\text { Material } & \text { Actual Mix } \\\mathrm{X} & 30,000 \text { units } \\\mathrm{Y} & 20,000 \text { units } \\& \\\text { Yield } & 36,000 \text { units }\end{array}

-Refer to Figure 18-4. What is the materials yield variance?

A)£4,000 (F)
B)£8,000 (F)
C)£8,000 (U)
D)£9,000 (U)
Question
Roberts Company uses a standard costing system. The following information pertains to direct materials for the month of July:  Standard price per lb. £18.00 Actual purchase price per 1 b.£16.50 Quantity purchased 3,100lbs. Quantity used 2,950lbs Standard quantity allowed for actual output 3,000lbs Actual output 1,000 units \begin{array}{lr}\text { Standard price per lb. } & £ 18.00 \\\text { Actual purchase price per } 1 \mathrm{~b} . & £ 16.50 \\\text { Quantity purchased } & 3,100 \mathrm{lbs} . \\\text { Quantity used } & 2,950 \mathrm{lbs} \text {. } \\\text { Standard quantity allowed for actual output } & 3,000 \mathrm{lbs} \text {. } \\\text { Actual output } & 1,000 \text { units }\end{array} Roberts Company reports its material price variances at the time of purchase. What is the journal entry to record material purchases?
a.
 Materials 55,800 Accounta Payable 55,800\begin{array}{llr} \text { Materials } &55,800\\ \text { Accounta Payable } &&55,800\\\end{array}


b.
 Accesunts Payable55,800 Materials 55,800\begin{array}{llr} \text { Accesunts Payable} &55,800\\ \text { Materials } &&55,800\\\end{array}

c.
 Materials55,800 Materials price Variance 4,650 Accounta Payable 51,150\begin{array}{llr} \text { Materials} &55,800\\ \text { Materials price Variance } &&4,650\\ \text { Accounta Payable } &&51,150\end{array}

d.
Materials 51,150 Materials price Variance 4,650 Accounta Payable 55,800\begin{array}{llr} \text {Materials } &51,150\\ \text { Materials price Variance } &4,650\\ \text { Accounta Payable } &&55,800\end{array}
Question
Figure 18-4
Regis Ltd. uses two materials in the production of its product. The materials, X and Y, have the following standards:  Material  Standard Mix  Standard Unit Price  Standard Cost X3,500 units £1.00 per unit £3,500Y1,500 units 3.00 per unit £4,500 Yield 4,000 units \begin{array}{cccc}\text { Material } & \text { Standard Mix } & \text { Standard Unit Price } & \text { Standard Cost } \\\mathrm{X} & 3,500 \text { units } & £ 1.00 \text { per unit } & £ 3,500 \\\mathrm{Y} & 1,500 \text { units } & 3.00 \text { per unit } & £ 4,500\\\text { Yield }& 4,000 \text { units }\end{array} During April, the following actual production information was provided:  Material  Actual Mix X30,000 units Y20,000 units  Yield 36,000 units \begin{array}{cc}\text { Material } & \text { Actual Mix } \\\mathrm{X} & 30,000 \text { units } \\\mathrm{Y} & 20,000 \text { units } \\& \\\text { Yield } & 36,000 \text { units }\end{array}

-Refer to Figure 18-4. What is the materials mix variance?

A)£5,000 (F)
B)£10,000 (U)
C)£10,000 (F)
D)£15,000 (F)
Question
Figure 18-4
Regis Ltd. uses two materials in the production of its product. The materials, X and Y, have the following standards:  Material  Standard Mix  Standard Unit Price  Standard Cost X3,500 units £1.00 per unit £3,500Y1,500 units 3.00 per unit £4,500 Yield 4,000 units \begin{array}{cccc}\text { Material } & \text { Standard Mix } & \text { Standard Unit Price } & \text { Standard Cost } \\\mathrm{X} & 3,500 \text { units } & £ 1.00 \text { per unit } & £ 3,500 \\\mathrm{Y} & 1,500 \text { units } & 3.00 \text { per unit } & £ 4,500\\\text { Yield }& 4,000 \text { units }\end{array} During April, the following actual production information was provided:  Material  Actual Mix X30,000 units Y20,000 units  Yield 36,000 units \begin{array}{cc}\text { Material } & \text { Actual Mix } \\\mathrm{X} & 30,000 \text { units } \\\mathrm{Y} & 20,000 \text { units } \\& \\\text { Yield } & 36,000 \text { units }\end{array}

-Refer to Figure 18-4. What is the materials usage variance?

A)£10,000 (U)
B)£ 8,000 (U)
C)£ 8,000 (F)
D)£18,000 (U)
Question
Laune Co.'s standard cost is £200,000, and its allowable deviation is £20,000. Laune's upper and lower control limits are

A)£220,000 and £200,000.
B)£200,000 and £180,000.
C)£220,000 and £180,000.
D)£210,000 and £190,000.
Question
Figure 18-3
Pippen Company's activity-based performance report revealed that actual inspection costs totaled £100,000 at an actual activity level of 50 inspections. Further analysis of inspection costs revealed the following:  Actual Cost  Budgeted Cost  Inspection costs:  Fixed £30,000£28,500 Variable 20,00017,500\begin{array}{l}&\text { Actual Cost } & \text { Budgeted Cost } \\\text { Inspection costs: }\\\text { Fixed } & £ 30,000 & £ 28,500 \\\text { Variable } & 20,000 & 17,500\end{array} Fixed inspection costs consist of the salaries of two inspectors, who are paid £14,250. Each inspector is capable of efficiently conducting inspections of 30 batches.
Variable inspection costs consist of materials used during the inspections.

-Refer to Figure 18-3. The fixed spending variance is

A)£1,500 U.
B)£1,500 F.
C)£2,100 U.
D)£2,100 F.
Question
Figure 18-1
Froelech Company has developed capacity standards. Information is as follows:  Standard cost of the activity capacity acquired £150,000 Standard cost of the activity capacity used 100,000 Standard cost of the actual activity used 120,000\begin{array}{lr}\text { Standard cost of the activity capacity acquired } & £ 150,000 \\\text { Standard cost of the activity capacity used } & 100,000 \\\text { Standard cost of the actual activity used } & 120,000\end{array}

-Refer to Figure 18-1. The volume variance is

A)£20,000 unfavourable.
B)£30,000 unfavourable.
C)£50,000 unfavourable.
D)There is no variance.
Question
Davis Industries' activity-based performance report revealed that actual inspection costs totaled £225,000 at an actual activity level of 80 inspections. Further analysis of inspection costs revealed the following: Davis Industries' activity-based performance report revealed that actual inspection costs totaled £225,000 at an actual activity level of 80 inspections. Further analysis of inspection costs revealed the following:   Fixed inspection costs consist of the salaries of four inspectors, paid £21,000 each. Each inspector is capable of efficiently conducting inspections of 50 batches. Variable inspection costs consist of materials used during the inspections. a.Calculate the following fixed activity budget variances for inspection:Total fixed activity varianceFixed spending varianceVolume varianceUnused capacity variance b.Calculate the following variable activity budget variances for inspection:Spending varianceEfficiency variance<div style=padding-top: 35px> Fixed inspection costs consist of the salaries of four inspectors, paid £21,000 each. Each inspector is capable of efficiently conducting inspections of 50 batches. Variable inspection costs consist of materials used during the inspections.
a.Calculate the following fixed activity budget variances for inspection:Total fixed activity varianceFixed spending varianceVolume varianceUnused capacity variance
b.Calculate the following variable activity budget variances for inspection:Spending varianceEfficiency variance
Question
Figure 18-3
Pippen Company's activity-based performance report revealed that actual inspection costs totaled £100,000 at an actual activity level of 50 inspections. Further analysis of inspection costs revealed the following:  Actual Cost  Budgeted Cost  Inspection costs:  Fixed £30,000£28,500 Variable 20,00017,500\begin{array}{l}&\text { Actual Cost } & \text { Budgeted Cost } \\\text { Inspection costs: }\\\text { Fixed } & £ 30,000 & £ 28,500 \\\text { Variable } & 20,000 & 17,500\end{array} Fixed inspection costs consist of the salaries of two inspectors, who are paid £14,250. Each inspector is capable of efficiently conducting inspections of 30 batches.
Variable inspection costs consist of materials used during the inspections.

-Refer to Figure 18-3. The volume variance is

A)£26,250 U.
B)£26,250 F.
C)£28,500 U.
D)£28,500 F.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/12
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 18: Standard Costing and Variance Analysis 2: Further Aspects
1
Figure 18-2
Allende Company has developed capacity standards. Information is as follows for a value-added activity:  Activity capacity acquired 60 Activity capacity used 50 Actual activity usage 30 Standard fixed activity rate £2,000\begin{array}{lr}\text { Activity capacity acquired } & 60 \\\text { Activity capacity used } & 50 \\\text { Actual activity usage } & 30 \\\text { Standard fixed activity rate } & £ 2,000\end{array}

-Refer to Figure 18-2. The unused capacity variance is

A)£20,000 favourable.
B)£40,000 favourable.
C)£60,000 favourable.
D)There is no variance.
£60,000 favourable.
2
Figure 18-1
Froelech Company has developed capacity standards. Information is as follows:  Standard cost of the activity capacity acquired £150,000 Standard cost of the activity capacity used 100,000 Standard cost of the actual activity used 120,000\begin{array}{lr}\text { Standard cost of the activity capacity acquired } & £ 150,000 \\\text { Standard cost of the activity capacity used } & 100,000 \\\text { Standard cost of the actual activity used } & 120,000\end{array}

-Refer to Figure 18-1. The unused capacity variance is

A)£20,000 favourable.
B)£30,000 favourable.
C)£50,000 favourable.
D)There is no variance.
£30,000 favourable.
3
When should variances be investigated?

A)when they fall out of the accepted range or the control limit
B)when the variances are unfavourable
C)when the variances are over £10,000
D)All variances should be investigated.
when they fall out of the accepted range or the control limit
4
Figure 18-4
Regis Ltd. uses two materials in the production of its product. The materials, X and Y, have the following standards:  Material  Standard Mix  Standard Unit Price  Standard Cost X3,500 units £1.00 per unit £3,500Y1,500 units 3.00 per unit £4,500 Yield 4,000 units \begin{array}{cccc}\text { Material } & \text { Standard Mix } & \text { Standard Unit Price } & \text { Standard Cost } \\\mathrm{X} & 3,500 \text { units } & £ 1.00 \text { per unit } & £ 3,500 \\\mathrm{Y} & 1,500 \text { units } & 3.00 \text { per unit } & £ 4,500\\\text { Yield }& 4,000 \text { units }\end{array} During April, the following actual production information was provided:  Material  Actual Mix X30,000 units Y20,000 units  Yield 36,000 units \begin{array}{cc}\text { Material } & \text { Actual Mix } \\\mathrm{X} & 30,000 \text { units } \\\mathrm{Y} & 20,000 \text { units } \\& \\\text { Yield } & 36,000 \text { units }\end{array}

-Refer to Figure 18-4. What is the materials yield variance?

A)£4,000 (F)
B)£8,000 (F)
C)£8,000 (U)
D)£9,000 (U)
Unlock Deck
Unlock for access to all 12 flashcards in this deck.
Unlock Deck
k this deck
5
Roberts Company uses a standard costing system. The following information pertains to direct materials for the month of July:  Standard price per lb. £18.00 Actual purchase price per 1 b.£16.50 Quantity purchased 3,100lbs. Quantity used 2,950lbs Standard quantity allowed for actual output 3,000lbs Actual output 1,000 units \begin{array}{lr}\text { Standard price per lb. } & £ 18.00 \\\text { Actual purchase price per } 1 \mathrm{~b} . & £ 16.50 \\\text { Quantity purchased } & 3,100 \mathrm{lbs} . \\\text { Quantity used } & 2,950 \mathrm{lbs} \text {. } \\\text { Standard quantity allowed for actual output } & 3,000 \mathrm{lbs} \text {. } \\\text { Actual output } & 1,000 \text { units }\end{array} Roberts Company reports its material price variances at the time of purchase. What is the journal entry to record material purchases?
a.
 Materials 55,800 Accounta Payable 55,800\begin{array}{llr} \text { Materials } &55,800\\ \text { Accounta Payable } &&55,800\\\end{array}


b.
 Accesunts Payable55,800 Materials 55,800\begin{array}{llr} \text { Accesunts Payable} &55,800\\ \text { Materials } &&55,800\\\end{array}

c.
 Materials55,800 Materials price Variance 4,650 Accounta Payable 51,150\begin{array}{llr} \text { Materials} &55,800\\ \text { Materials price Variance } &&4,650\\ \text { Accounta Payable } &&51,150\end{array}

d.
Materials 51,150 Materials price Variance 4,650 Accounta Payable 55,800\begin{array}{llr} \text {Materials } &51,150\\ \text { Materials price Variance } &4,650\\ \text { Accounta Payable } &&55,800\end{array}
Unlock Deck
Unlock for access to all 12 flashcards in this deck.
Unlock Deck
k this deck
6
Figure 18-4
Regis Ltd. uses two materials in the production of its product. The materials, X and Y, have the following standards:  Material  Standard Mix  Standard Unit Price  Standard Cost X3,500 units £1.00 per unit £3,500Y1,500 units 3.00 per unit £4,500 Yield 4,000 units \begin{array}{cccc}\text { Material } & \text { Standard Mix } & \text { Standard Unit Price } & \text { Standard Cost } \\\mathrm{X} & 3,500 \text { units } & £ 1.00 \text { per unit } & £ 3,500 \\\mathrm{Y} & 1,500 \text { units } & 3.00 \text { per unit } & £ 4,500\\\text { Yield }& 4,000 \text { units }\end{array} During April, the following actual production information was provided:  Material  Actual Mix X30,000 units Y20,000 units  Yield 36,000 units \begin{array}{cc}\text { Material } & \text { Actual Mix } \\\mathrm{X} & 30,000 \text { units } \\\mathrm{Y} & 20,000 \text { units } \\& \\\text { Yield } & 36,000 \text { units }\end{array}

-Refer to Figure 18-4. What is the materials mix variance?

A)£5,000 (F)
B)£10,000 (U)
C)£10,000 (F)
D)£15,000 (F)
Unlock Deck
Unlock for access to all 12 flashcards in this deck.
Unlock Deck
k this deck
7
Figure 18-4
Regis Ltd. uses two materials in the production of its product. The materials, X and Y, have the following standards:  Material  Standard Mix  Standard Unit Price  Standard Cost X3,500 units £1.00 per unit £3,500Y1,500 units 3.00 per unit £4,500 Yield 4,000 units \begin{array}{cccc}\text { Material } & \text { Standard Mix } & \text { Standard Unit Price } & \text { Standard Cost } \\\mathrm{X} & 3,500 \text { units } & £ 1.00 \text { per unit } & £ 3,500 \\\mathrm{Y} & 1,500 \text { units } & 3.00 \text { per unit } & £ 4,500\\\text { Yield }& 4,000 \text { units }\end{array} During April, the following actual production information was provided:  Material  Actual Mix X30,000 units Y20,000 units  Yield 36,000 units \begin{array}{cc}\text { Material } & \text { Actual Mix } \\\mathrm{X} & 30,000 \text { units } \\\mathrm{Y} & 20,000 \text { units } \\& \\\text { Yield } & 36,000 \text { units }\end{array}

-Refer to Figure 18-4. What is the materials usage variance?

A)£10,000 (U)
B)£ 8,000 (U)
C)£ 8,000 (F)
D)£18,000 (U)
Unlock Deck
Unlock for access to all 12 flashcards in this deck.
Unlock Deck
k this deck
8
Laune Co.'s standard cost is £200,000, and its allowable deviation is £20,000. Laune's upper and lower control limits are

A)£220,000 and £200,000.
B)£200,000 and £180,000.
C)£220,000 and £180,000.
D)£210,000 and £190,000.
Unlock Deck
Unlock for access to all 12 flashcards in this deck.
Unlock Deck
k this deck
9
Figure 18-3
Pippen Company's activity-based performance report revealed that actual inspection costs totaled £100,000 at an actual activity level of 50 inspections. Further analysis of inspection costs revealed the following:  Actual Cost  Budgeted Cost  Inspection costs:  Fixed £30,000£28,500 Variable 20,00017,500\begin{array}{l}&\text { Actual Cost } & \text { Budgeted Cost } \\\text { Inspection costs: }\\\text { Fixed } & £ 30,000 & £ 28,500 \\\text { Variable } & 20,000 & 17,500\end{array} Fixed inspection costs consist of the salaries of two inspectors, who are paid £14,250. Each inspector is capable of efficiently conducting inspections of 30 batches.
Variable inspection costs consist of materials used during the inspections.

-Refer to Figure 18-3. The fixed spending variance is

A)£1,500 U.
B)£1,500 F.
C)£2,100 U.
D)£2,100 F.
Unlock Deck
Unlock for access to all 12 flashcards in this deck.
Unlock Deck
k this deck
10
Figure 18-1
Froelech Company has developed capacity standards. Information is as follows:  Standard cost of the activity capacity acquired £150,000 Standard cost of the activity capacity used 100,000 Standard cost of the actual activity used 120,000\begin{array}{lr}\text { Standard cost of the activity capacity acquired } & £ 150,000 \\\text { Standard cost of the activity capacity used } & 100,000 \\\text { Standard cost of the actual activity used } & 120,000\end{array}

-Refer to Figure 18-1. The volume variance is

A)£20,000 unfavourable.
B)£30,000 unfavourable.
C)£50,000 unfavourable.
D)There is no variance.
Unlock Deck
Unlock for access to all 12 flashcards in this deck.
Unlock Deck
k this deck
11
Davis Industries' activity-based performance report revealed that actual inspection costs totaled £225,000 at an actual activity level of 80 inspections. Further analysis of inspection costs revealed the following: Davis Industries' activity-based performance report revealed that actual inspection costs totaled £225,000 at an actual activity level of 80 inspections. Further analysis of inspection costs revealed the following:   Fixed inspection costs consist of the salaries of four inspectors, paid £21,000 each. Each inspector is capable of efficiently conducting inspections of 50 batches. Variable inspection costs consist of materials used during the inspections. a.Calculate the following fixed activity budget variances for inspection:Total fixed activity varianceFixed spending varianceVolume varianceUnused capacity variance b.Calculate the following variable activity budget variances for inspection:Spending varianceEfficiency variance Fixed inspection costs consist of the salaries of four inspectors, paid £21,000 each. Each inspector is capable of efficiently conducting inspections of 50 batches. Variable inspection costs consist of materials used during the inspections.
a.Calculate the following fixed activity budget variances for inspection:Total fixed activity varianceFixed spending varianceVolume varianceUnused capacity variance
b.Calculate the following variable activity budget variances for inspection:Spending varianceEfficiency variance
Unlock Deck
Unlock for access to all 12 flashcards in this deck.
Unlock Deck
k this deck
12
Figure 18-3
Pippen Company's activity-based performance report revealed that actual inspection costs totaled £100,000 at an actual activity level of 50 inspections. Further analysis of inspection costs revealed the following:  Actual Cost  Budgeted Cost  Inspection costs:  Fixed £30,000£28,500 Variable 20,00017,500\begin{array}{l}&\text { Actual Cost } & \text { Budgeted Cost } \\\text { Inspection costs: }\\\text { Fixed } & £ 30,000 & £ 28,500 \\\text { Variable } & 20,000 & 17,500\end{array} Fixed inspection costs consist of the salaries of two inspectors, who are paid £14,250. Each inspector is capable of efficiently conducting inspections of 30 batches.
Variable inspection costs consist of materials used during the inspections.

-Refer to Figure 18-3. The volume variance is

A)£26,250 U.
B)£26,250 F.
C)£28,500 U.
D)£28,500 F.
Unlock Deck
Unlock for access to all 12 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 12 flashcards in this deck.