Deck 9: Project Scheduling: Pertcpm

Full screen (f)
exit full mode
Question
The earliest start time rule

A)compares the starting times of all activities for successors of an activity.
B)compares the finish times for all immediate predecessors of an activity.
C)determines when the project can begin.
D)determines when the project must begin.
Use Space or
up arrow
down arrow
to flip the card.
Question
Activities G, P, and R are the immediate predecessors for activity W.If the earliest finish times for the three are 12, 15, and 10, then the earliest start time for W

A)is 10.
B)is 12.
C)is 15.
D)cannot be determined.
Question
Activities following a node

A)can begin as soon as any activity preceding the node has been completed.
B)have an earliest start time equal to the largest of the earliest finish times for all activities entering the node.
C)have a latest start time equal to the largest of the earliest finish times for all activities entering the node.
D)None of the alternatives is correct.
Question
PERT and CPM

A)are most valuable when a small number of activities must be scheduled.
B)have different features and are not applied to the same situation.
C)do not require a chronological relationship among activities.
D)have been combined to develop a procedure that uses the best of each.
Question
PERT and CPM are applicable only when there is no dependence among activities.
Question
To determine how to crash activity times

A)normal activity costs and costs under maximum crashing must be known.
B)shortest times with crashing must be known.
C)realize that new paths may become critical.
D)All of the alternatives are true.
Question
A path through a project network must reach every node.
Question
When activity times are uncertain,

A)assume they are normally distributed.
B)calculate the expected time, using (a + 4m + b)/6.
C)use the most likely time.
D)calculate the expected time, using (a + m + b)/3.
Question
For an activity with more than one immediate predecessor activity, which of the following is used to compute its earliest finish (EF) time?

A)the largest EF among the immediate predecessors.
B)the average EF among the immediate predecessors.
C)the largest LF among the immediate predecessors.
D)the difference in EF among the immediate predecessors.
Question
Arcs in a project network indicate

A)completion times.
B)precedence relationships.
C)activities.
D)the critical path.
Question
Which of the following is always true about a critical activity?

A)LS = EF.
B)LF = LS.
C)ES = LS.
D)EF = ES.
Question
Critical activities are those that can be delayed without delaying the entire project.
Question
For an activity with more than one immediate successor activity, its latest-finish time is equal to the

A)largest latest-finish time among its immediate successors.
B)smallest latest-finish time among its immediate successors.
C)largest latest-start time among its immediate successors.
D)smallest latest-start time among its immediate successors.
Question
In deciding which activities to crash, one must

A)crash all critical activities.
B)crash largest-duration activities.
C)crash lowest-cost activities.
D)crash activities on the critical path(s) only.
Question
Which is not a significant challenge of project scheduling?

A)deadlines exist.
B)activities are independent.
C)many employees could be required.
D)delays are costly.
Question
Activities K, M and S immediately follow activity H, and their latest start times are 14, 18, and 11.The latest finish time for activity H

A)is 11.
B)is 14.
C)is 18.
D)cannot be determined.
Question
The critical path

A)is any path that goes from the starting node to the completion node.
B)is a combination of all paths.
C)is the shortest path.
D)is the longest path.
Question
Slack equals

A)LF - EF.
B)EF - LF.
C)EF - LS.
D)LF - ES.
Question
Activities with zero slack

A)can be delayed.
B)must be completed first.
C)lie on a critical path.
D)have no predecessors.
Question
Which of the following is a general rule for crashing activities?

A)Crash only non-critical activities.
B)Crash activities with zero slack.
C)Crash activities with the greatest number of predecessors.
D)Crash the path with the fewest activities.
Question
Crashing refers to an unanticipated delay in a critical path activity that causes the total time to exceed its limit.
Question
The length of time an activity can be delayed without affecting the project completion time is the slack.
Question
The earliest start time for an activity is equal to the smallest of the earliest finish times for all its immediate predecessors.
Question
The linear programming model for crashing presented in the textbook assumes that any portion of the activity crash time can be achieved for a corresponding portion of the activity crashing cost.
Question
The earliest finish time for the final activity is the project duration.
Question
A critical activity can be part of a noncritical path.
Question
The latest finish time for an activity is the largest of the latest start times for all activities that immediately follow the activity.
Question
When activity times are uncertain, total project time is normally distributed with mean equal to the sum of the means of all of the critical activities.
Question
The project manager should monitor the progress of any activity with a large time variance even if the expected time does not identify the activity as a critical activity.
Question
When activity times are uncertain, an activity's most likely time is the same as its expected time.
Question
The variance in the project completion time is the sum of the variances of all activities in the project.
Question
Constraints in the LP models for crashing decisions are required to compare the activity's earliest finish time with the earliest finish time of each predecessor.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/32
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 9: Project Scheduling: Pertcpm
1
The earliest start time rule

A)compares the starting times of all activities for successors of an activity.
B)compares the finish times for all immediate predecessors of an activity.
C)determines when the project can begin.
D)determines when the project must begin.
B
2
Activities G, P, and R are the immediate predecessors for activity W.If the earliest finish times for the three are 12, 15, and 10, then the earliest start time for W

A)is 10.
B)is 12.
C)is 15.
D)cannot be determined.
C
3
Activities following a node

A)can begin as soon as any activity preceding the node has been completed.
B)have an earliest start time equal to the largest of the earliest finish times for all activities entering the node.
C)have a latest start time equal to the largest of the earliest finish times for all activities entering the node.
D)None of the alternatives is correct.
B
4
PERT and CPM

A)are most valuable when a small number of activities must be scheduled.
B)have different features and are not applied to the same situation.
C)do not require a chronological relationship among activities.
D)have been combined to develop a procedure that uses the best of each.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
5
PERT and CPM are applicable only when there is no dependence among activities.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
6
To determine how to crash activity times

A)normal activity costs and costs under maximum crashing must be known.
B)shortest times with crashing must be known.
C)realize that new paths may become critical.
D)All of the alternatives are true.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
7
A path through a project network must reach every node.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
8
When activity times are uncertain,

A)assume they are normally distributed.
B)calculate the expected time, using (a + 4m + b)/6.
C)use the most likely time.
D)calculate the expected time, using (a + m + b)/3.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
9
For an activity with more than one immediate predecessor activity, which of the following is used to compute its earliest finish (EF) time?

A)the largest EF among the immediate predecessors.
B)the average EF among the immediate predecessors.
C)the largest LF among the immediate predecessors.
D)the difference in EF among the immediate predecessors.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
10
Arcs in a project network indicate

A)completion times.
B)precedence relationships.
C)activities.
D)the critical path.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
11
Which of the following is always true about a critical activity?

A)LS = EF.
B)LF = LS.
C)ES = LS.
D)EF = ES.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
12
Critical activities are those that can be delayed without delaying the entire project.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
13
For an activity with more than one immediate successor activity, its latest-finish time is equal to the

A)largest latest-finish time among its immediate successors.
B)smallest latest-finish time among its immediate successors.
C)largest latest-start time among its immediate successors.
D)smallest latest-start time among its immediate successors.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
14
In deciding which activities to crash, one must

A)crash all critical activities.
B)crash largest-duration activities.
C)crash lowest-cost activities.
D)crash activities on the critical path(s) only.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
15
Which is not a significant challenge of project scheduling?

A)deadlines exist.
B)activities are independent.
C)many employees could be required.
D)delays are costly.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
16
Activities K, M and S immediately follow activity H, and their latest start times are 14, 18, and 11.The latest finish time for activity H

A)is 11.
B)is 14.
C)is 18.
D)cannot be determined.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
17
The critical path

A)is any path that goes from the starting node to the completion node.
B)is a combination of all paths.
C)is the shortest path.
D)is the longest path.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
18
Slack equals

A)LF - EF.
B)EF - LF.
C)EF - LS.
D)LF - ES.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
19
Activities with zero slack

A)can be delayed.
B)must be completed first.
C)lie on a critical path.
D)have no predecessors.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
20
Which of the following is a general rule for crashing activities?

A)Crash only non-critical activities.
B)Crash activities with zero slack.
C)Crash activities with the greatest number of predecessors.
D)Crash the path with the fewest activities.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
21
Crashing refers to an unanticipated delay in a critical path activity that causes the total time to exceed its limit.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
22
The length of time an activity can be delayed without affecting the project completion time is the slack.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
23
The earliest start time for an activity is equal to the smallest of the earliest finish times for all its immediate predecessors.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
24
The linear programming model for crashing presented in the textbook assumes that any portion of the activity crash time can be achieved for a corresponding portion of the activity crashing cost.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
25
The earliest finish time for the final activity is the project duration.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
26
A critical activity can be part of a noncritical path.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
27
The latest finish time for an activity is the largest of the latest start times for all activities that immediately follow the activity.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
28
When activity times are uncertain, total project time is normally distributed with mean equal to the sum of the means of all of the critical activities.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
29
The project manager should monitor the progress of any activity with a large time variance even if the expected time does not identify the activity as a critical activity.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
30
When activity times are uncertain, an activity's most likely time is the same as its expected time.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
31
The variance in the project completion time is the sum of the variances of all activities in the project.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
32
Constraints in the LP models for crashing decisions are required to compare the activity's earliest finish time with the earliest finish time of each predecessor.
Unlock Deck
Unlock for access to all 32 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 32 flashcards in this deck.