Exam 9: Project Scheduling: Pertcpm
Exam 1: Introduction30 Questions
Exam 2: Introduction to Linear Programming28 Questions
Exam 3: LP Sensitivity Analysis and Interpretation of Solution31 Questions
Exam 4: Linear Programming Applications21 Questions
Exam 5: Advanced Linear Programming Applications24 Questions
Exam 6: Distribution and Network Problems31 Questions
Exam 7: Integer Linear Programming30 Questions
Exam 8: Nonlinear Optimization Models33 Questions
Exam 9: Project Scheduling: Pertcpm32 Questions
Exam 10: Inventory Models33 Questions
Exam 11: Waiting Line Models33 Questions
Exam 12: Simulation33 Questions
Exam 13: Decision Analysis24 Questions
Exam 14: Multicriteria Decisions30 Questions
Exam 15: Forecasting34 Questions
Exam 16: Markov Processes25 Questions
Exam 17: LP: Simplex Method29 Questions
Exam 18: Simplex-Based Sensitivity Analysis and Duality20 Questions
Exam 19: Solution Procedures for Transportation and Assignment Problems23 Questions
Exam 20: Minimal Spanning Tree12 Questions
Exam 21: Dynamic Programming19 Questions
Select questions type
A critical activity can be part of a noncritical path.
Free
(True/False)
4.8/5
(27)
Correct Answer:
True
Critical activities are those that can be delayed without delaying the entire project.
Free
(True/False)
4.9/5
(35)
Correct Answer:
False
The earliest finish time for the final activity is the project duration.
(True/False)
4.8/5
(27)
The latest finish time for an activity is the largest of the latest start times for all activities that immediately follow the activity.
(True/False)
4.9/5
(41)
Activities K, M and S immediately follow activity H, and their latest start times are 14, 18, and 11.The latest finish time for activity H
(Multiple Choice)
4.9/5
(41)
Which of the following is a general rule for crashing activities?
(Multiple Choice)
4.9/5
(31)
Activities G, P, and R are the immediate predecessors for activity W.If the earliest finish times for the three are 12, 15, and 10, then the earliest start time for W
(Multiple Choice)
4.7/5
(27)
Which of the following is always true about a critical activity?
(Multiple Choice)
5.0/5
(34)
PERT and CPM are applicable only when there is no dependence among activities.
(True/False)
4.8/5
(40)
When activity times are uncertain, an activity's most likely time is the same as its expected time.
(True/False)
4.9/5
(34)
The length of time an activity can be delayed without affecting the project completion time is the slack.
(True/False)
4.9/5
(30)
The linear programming model for crashing presented in the textbook assumes that any portion of the activity crash time can be achieved for a corresponding portion of the activity crashing cost.