A critical activity can be part of a noncritical path.

Free
(True/False)
4.8/5
(27)
Correct Answer:
Verified

True

Slack equals

Free
(Multiple Choice)
4.8/5
(39)
Correct Answer:
Verified

B

Critical activities are those that can be delayed without delaying the entire project.

Free
(True/False)
4.9/5
(35)
Correct Answer:
Verified

False

The earliest finish time for the final activity is the project duration.

(True/False)
4.8/5
(27)

Which is not a significant challenge of project scheduling?

(Multiple Choice)
4.8/5
(43)

The latest finish time for an activity is the largest of the latest start times for all activities that immediately follow the activity.

(True/False)
4.9/5
(41)

Activities K, M and S immediately follow activity H, and their latest start times are 14, 18, and 11.The latest finish time for activity H

(Multiple Choice)
4.9/5
(41)

Which of the following is a general rule for crashing activities?

(Multiple Choice)
4.9/5
(31)

Activities G, P, and R are the immediate predecessors for activity W.If the earliest finish times for the three are 12, 15, and 10, then the earliest start time for W

(Multiple Choice)
4.7/5
(27)

Which of the following is always true about a critical activity?

(Multiple Choice)
5.0/5
(34)

PERT and CPM

(Multiple Choice)
4.8/5
(45)

Activities with zero slack

(Multiple Choice)
4.8/5
(36)

Arcs in a project network indicate

(Multiple Choice)
4.9/5
(25)

In deciding which activities to crash, one must

(Multiple Choice)
4.8/5
(40)

PERT and CPM are applicable only when there is no dependence among activities.

(True/False)
4.8/5
(40)

When activity times are uncertain, an activity's most likely time is the same as its expected time.

(True/False)
4.9/5
(34)

The length of time an activity can be delayed without affecting the project completion time is the slack.

(True/False)
4.9/5
(30)

When activity times are uncertain,

(Multiple Choice)
5.0/5
(27)

The linear programming model for crashing presented in the textbook assumes that any portion of the activity crash time can be achieved for a corresponding portion of the activity crashing cost.

(True/False)
4.8/5
(43)

Activities following a node

(Multiple Choice)
4.9/5
(32)