Deck 14: Short-Term Scheduling
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/124
Play
Full screen (f)
Deck 14: Short-Term Scheduling
1
Which of the following is NOT a key direct benefit from effective internal or external scheduling?
A) lower cost
B) greater use of assets
C) more dependable delivery
D) higher quality
E) added flexibility
A) lower cost
B) greater use of assets
C) more dependable delivery
D) higher quality
E) added flexibility
D
2
What is the objective of scheduling?
A) maximize quality
B) minimize cost
C) minimize response time
D) prioritize and allocate demand to available facilities
E) minimize lead time
A) maximize quality
B) minimize cost
C) minimize response time
D) prioritize and allocate demand to available facilities
E) minimize lead time
D
3
Which of the following statements regarding scheduling at Alaska Airlines is FALSE?
A) Flying into Alaska complicates scheduling.
B) Schedule changes at one airport have a ripple effect that may have impacts in many others.
C) Alaska Airlines' high-tech computer and communications system is located in Seattle.
D) Alaska Airlines' rapid rescheduling uses mathematical scheduling models.
E) Alaska Airlines' rapid rescheduling promotes air safety and limits traveler inconvenience, but it has not resulted in money savings for Alaska Airlines.
A) Flying into Alaska complicates scheduling.
B) Schedule changes at one airport have a ripple effect that may have impacts in many others.
C) Alaska Airlines' high-tech computer and communications system is located in Seattle.
D) Alaska Airlines' rapid rescheduling uses mathematical scheduling models.
E) Alaska Airlines' rapid rescheduling promotes air safety and limits traveler inconvenience, but it has not resulted in money savings for Alaska Airlines.
E
4
The correct sequence from longest to smallest duration scheduling is:
A) capacity planning, aggregate planning, master schedule, short-term scheduling.
B) aggregate planning, capacity planning, master schedule, short-term scheduling.
C) master schedule, capacity planning, aggregate planning, short-term scheduling.
D) master schedule, aggregate planning, capacity planning, short-term scheduling.
E) capacity planning, master schedule, aggregate planning, short-term scheduling.
A) capacity planning, aggregate planning, master schedule, short-term scheduling.
B) aggregate planning, capacity planning, master schedule, short-term scheduling.
C) master schedule, capacity planning, aggregate planning, short-term scheduling.
D) master schedule, aggregate planning, capacity planning, short-term scheduling.
E) capacity planning, master schedule, aggregate planning, short-term scheduling.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
5
Alaska Airlines uses mathematical short-term scheduling techniques and a high-tech Flight Operations Department to manage the rapid rescheduling necessary to cope with weather delays and similar disruptions.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
6
Techniques that load work without regard for the capacity of the process are:
A) aggregate planning.
B) backward scheduling.
C) forward scheduling.
D) finite loading.
E) infinite loading.
A) aggregate planning.
B) backward scheduling.
C) forward scheduling.
D) finite loading.
E) infinite loading.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
7
Short-term schedules are prepared:
A) directly from the aggregate plans.
B) directly from the capacity plans.
C) from inventory records for items that have been used up.
D) from master schedules, which are derived from aggregate plans.
E) from the purchasing plans.
A) directly from the aggregate plans.
B) directly from the capacity plans.
C) from inventory records for items that have been used up.
D) from master schedules, which are derived from aggregate plans.
E) from the purchasing plans.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
8
What makes short-term scheduling of strategic importance?
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
9
The short-term scheduling activity called "loading":
A) assigns dates to specific jobs or operations steps.
B) specifies the order in which jobs should be done at each center.
C) assigns jobs to work centers.
D) assigns workers to jobs.
E) assigns workers to machines.
A) assigns dates to specific jobs or operations steps.
B) specifies the order in which jobs should be done at each center.
C) assigns jobs to work centers.
D) assigns workers to jobs.
E) assigns workers to machines.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
10
Forward scheduling is used in manufacturing environments, as well as service environments such as catering a banquet or scheduling surgery.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
11
Which of the following considers process capacity when scheduling?
A) cap loading
B) constrained loading
C) capacitated loading
D) backward loading
E) finite loading
A) cap loading
B) constrained loading
C) capacitated loading
D) backward loading
E) finite loading
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
12
Briefly describe how "the unexpected" makes short-term scheduling at Alaska Airlines a challenge. Also describe how Alaska Airlines meets that challenge and achieves competitive advantage through short-term scheduling.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
13
Short-term scheduling is important to efficiency and to cost reduction, but its impact is not of strategic importance.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
14
One criterion for developing effective schedules is maximizing completion time.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
15
Process-focused facilities and repetitive facilities generate forward-looking schedules, but process-focused facilities do this with JIT and kanban while repetitive facilities generally use MRP.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
16
Forward scheduling is the scheduling of:
A) the end items or finished products.
B) jobs as soon as the requirements are known.
C) the start items or component parts.
D) the final operation first beginning with the due date.
E) jobs according to their profit contributions.
A) the end items or finished products.
B) jobs as soon as the requirements are known.
C) the start items or component parts.
D) the final operation first beginning with the due date.
E) jobs according to their profit contributions.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
17
The benefits of effective scheduling include lower cost, faster throughput, and dependable delivery.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
18
Forward scheduling:
A) begins with a delivery date, then offsets each operation one at a time, in reverse order.
B) has the same meaning as "finite loading."
C) is often used in service environments such as catering a banquet or scheduling surgery.
D) starts the schedule as soon as the job requirements are known.
E) produces a schedule only if it meets the due date.
A) begins with a delivery date, then offsets each operation one at a time, in reverse order.
B) has the same meaning as "finite loading."
C) is often used in service environments such as catering a banquet or scheduling surgery.
D) starts the schedule as soon as the job requirements are known.
E) produces a schedule only if it meets the due date.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
19
With forward scheduling, jobs are scheduled as late as possible within the time allowed by the customer due dates.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
20
Which of the following is NOT an effectiveness criterion for scheduling?
A) minimizing customer waiting time
B) minimizing completion time
C) minimizing WIP inventory
D) maximizing utilization
E) maximizing flow time
A) minimizing customer waiting time
B) minimizing completion time
C) minimizing WIP inventory
D) maximizing utilization
E) maximizing flow time
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
21
What is a scheduling technique used to achieve an optimum, one-to-one matching of tasks and resources?
A) the assignment method
B) Johnson's rule
C) the CDS algorithm
D) the appointment method
E) the reservation method
A) the assignment method
B) Johnson's rule
C) the CDS algorithm
D) the appointment method
E) the reservation method
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
22
One of the major limitations of the Gantt load chart is that it doesn't account for production variability such as unexpected breakdowns or human errors.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
23
Compare short-term scheduling at process-focused, repetitive, and product-focused facilities.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
24
The constant work-in-process (ConWIP) card aids input-output control by limiting the amount of work in a work center.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
25
A Gantt load chart shows the loading and idle time of several departments, machines, or facilities.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
26
The assignment method provides an optimum, one-to-one assignment of jobs to resources.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
27
Explain, in your own words, how backward scheduling and forward scheduling differ.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
28
In the sequence of decisions that affect scheduling, ________ is (are) the immediate follower(s) of the master schedule (or master production schedule).
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
29
Gantt charts are useful for scheduling jobs, but not for loading them.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
30
A work center had actual input of 280 hours and actual output of 290 hours. What is the change in backlog?
A) 10
B) -10
C) 0
D) 1.037
E) Unable to determine with the given information
A) 10
B) -10
C) 0
D) 1.037
E) Unable to determine with the given information
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
31
There are two jobs to be assigned to two workers. The cost for worker A on job 1 is $5 and on job 2 is $8. The cost for worker B on job 1 is $10 and on job 2 is $12. How should the work be divided using the assignment method?
A) worker A assigned to job 1 and worker B assigned to job 2
B) worker A assigned to job 2 and worker B assigned to job 1
C) worker A gets both jobs 1 and 2
D) worker B gets both jobs 1 and 2
E) unable to determine
A) worker A assigned to job 1 and worker B assigned to job 2
B) worker A assigned to job 2 and worker B assigned to job 1
C) worker A gets both jobs 1 and 2
D) worker B gets both jobs 1 and 2
E) unable to determine
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
32
________ scheduling begins with the due date and schedules the final operation first and the other job steps in reverse order.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
33
A work center had planned outputs of 10, 15, 13, and 20 hours with actual outputs of 12, 14, 15, and 18 hours. What is the cumulative deviation in output?
A) 0
B) 1
C) −1
D) 58
E) Unable to determine with the given information
A) 0
B) 1
C) −1
D) 58
E) Unable to determine with the given information
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
34
The assignment method is:
A) a method to highlight overloads in a given work center.
B) a computerized method of determining appropriate tasks for an operation.
C) a form of linear programming for optimally assigning tasks or jobs to resources.
D) the same thing as the Gantt schedule chart.
E) a method for achieving a balance between forward and backward scheduling.
A) a method to highlight overloads in a given work center.
B) a computerized method of determining appropriate tasks for an operation.
C) a form of linear programming for optimally assigning tasks or jobs to resources.
D) the same thing as the Gantt schedule chart.
E) a method for achieving a balance between forward and backward scheduling.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
35
If job 5 takes 3, 4, or 6 hours to be completed by workers A, B, and C, respectively, what would the row values for job 5 be after performing Step 1A of the assignment method?
A) 0, 1, 3
B) 8, 9, 11
C) 0, 1, 2
D) 6, 7, 9
E) 1, 4/3, 1/2
A) 0, 1, 3
B) 8, 9, 11
C) 0, 1, 2
D) 6, 7, 9
E) 1, 4/3, 1/2
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
36
Which of the following is NOT required to be known in order to schedule process-focused facilities?
A) the sequence of work
B) which workers are assigned to each work center
C) the time required for each item
D) the capacity of each work center
E) the availability of each work center
A) the sequence of work
B) which workers are assigned to each work center
C) the time required for each item
D) the capacity of each work center
E) the availability of each work center
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
37
A work center is interested in limiting work-in-process by not allowing production to start again until the current batch is finished. The best solution most likely involves:
A) MRP.
B) ConWIP cards.
C) Gantt charts.
D) Johnson's rule.
E) the assignment method.
A) MRP.
B) ConWIP cards.
C) Gantt charts.
D) Johnson's rule.
E) the assignment method.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
38
________ is the assignment of jobs to work or processing centers.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
39
What is a method of input-output control that uses a system of cards to limit the amount of work at a work center and also to control lead time and monitor backlog?
A) the assignment method
B) backward scheduling
C) forward scheduling
D) ConWIP cards
E) level material use
A) the assignment method
B) backward scheduling
C) forward scheduling
D) ConWIP cards
E) level material use
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
40
Which of the following is an aid used to monitor jobs in progress?
A) a Gantt load chart
B) the assignment method
C) a Gantt schedule chart
D) Johnson's rule
E) a Gantt progress chart
A) a Gantt load chart
B) the assignment method
C) a Gantt schedule chart
D) Johnson's rule
E) a Gantt progress chart
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
41
The ________ is a special class of linear programming models that involves assigning tasks or jobs to resources.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
42
If an assignment problem consists of 5 workers and 4 projects:
A) one worker will not get a project assignment.
B) one project will be assigned two workers.
C) the fifth worker will split time among the four projects.
D) one project will not get a worker assigned.
E) The problem cannot be solved by assignment method.
A) one worker will not get a project assignment.
B) one project will be assigned two workers.
C) the fifth worker will split time among the four projects.
D) one project will not get a worker assigned.
E) The problem cannot be solved by assignment method.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
43
What is the difference between a Gantt load chart and a Gantt scheduling chart?
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
44
Three jobs are to be assigned to three machines. Cost for each job-machine combination appears in the table below. Perform the first two steps of the assignment method (subtract the smallest number in each row and subtract the smallest number in each column; then cover with straight lines). At this point in the problem-solving process: 
A) the row for Job 1 contains the values 5, 6, and 0.
B) calculations are complete, and the problem is ready for an optimal set of assignments.
C) the column for Machine B indicates that it should be retired.
D) Job 1 should be performed on Machine B.
E) Job 1 should be performed on Machine A.

A) the row for Job 1 contains the values 5, 6, and 0.
B) calculations are complete, and the problem is ready for an optimal set of assignments.
C) the column for Machine B indicates that it should be retired.
D) Job 1 should be performed on Machine B.
E) Job 1 should be performed on Machine A.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
45
Three jobs are to be assigned to three machines. Profits for each job-machine combination appear in the table below. Find the total profit using the assignment method. 
A) 28
B) 40
C) 36
D) 39
E) 41

A) 28
B) 40
C) 36
D) 39
E) 41
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
46
What is the assignment method?
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
47
________ cards are used to control the amount of work in a work center, aiding input-output control.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
48
Identify the major disadvantages of the Gantt load chart.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
49
The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are sequenced according to the shortest processing time rule, what is the lateness of job A? 
A) 0.0 days
B) 23.0 days
C) 7.4 days
D) 9.0 days
E) 11.6 days

A) 0.0 days
B) 23.0 days
C) 7.4 days
D) 9.0 days
E) 11.6 days
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
50
Lockport Marine Services, Inc. wishes to assign a set of jobs to a set of machines. The following table provides data on the cost of production of each job when performed on a specific machine.
(a) Determine the set of assignments that minimizes production cost.
(b) What is the total production cost of your assignments?

(a) Determine the set of assignments that minimizes production cost.
(b) What is the total production cost of your assignments?

Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
51
________ are planning charts used to schedule resources and allocate time.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
52
Dispatching rules are typically judged by four effectiveness criteria: average completion time, utilization, average number of jobs in the system, and average customer satisfaction.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
53
The critical ratio sequencing rule prioritizes the jobs based on the importance or value of the customers who have placed the orders.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
54
Johnson's rule sequences a set of jobs through two different machines or work centers in the same order.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
55
If an assignment problem consists of 6 workers and 7 projects:
A) one worker will not get a project assignment.
B) one worker will be assigned two projects.
C) each worker will contribute work toward the seventh project.
D) one project will not get a worker assigned.
E) The problem cannot be solved by assignment method.
A) one worker will not get a project assignment.
B) one worker will be assigned two projects.
C) each worker will contribute work toward the seventh project.
D) one project will not get a worker assigned.
E) The problem cannot be solved by assignment method.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
56
Machines A, B, C, and D have been in use for several years, while machine E is new. The following table provides data on the value of production of each job when performed on a specific machine.
(a) Determine the set of assignments that maximizes production value.
(b) What is the total production value of your assignments?
(c) Which machine should be retired (i.e., gets no assignment)?

(a) Determine the set of assignments that maximizes production value.
(b) What is the total production value of your assignments?
(c) Which machine should be retired (i.e., gets no assignment)?

Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
57
Earliest due date is a shop floor dispatching (sequencing) rule that relates the time available to complete a job to the amount of work left to be completed.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
58
The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Gerald, Johnny, and Rick-to complete any of the four projects, as follows:
(a) What is the total number of hours required by the following arbitrary assignment?
Charlie→B; Gerald→A; Johnny→C; Rick→D
(b) What is the optimal assignment of consultants to projects? (Use the assignment method.)
(c) For the optimal schedule, what is the total number of hours it will take these consultants to complete these projects?

Charlie→B; Gerald→A; Johnny→C; Rick→D
(b) What is the optimal assignment of consultants to projects? (Use the assignment method.)
(c) For the optimal schedule, what is the total number of hours it will take these consultants to complete these projects?
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
59
What is input-output control?
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
60
Three jobs are to be assigned to three machines. Costs for each job-machine combination appear in the table below. Find the total cost using the assignment method. 
A) 25
B) 28
C) 29
D) 21
E) 34

A) 25
B) 28
C) 29
D) 21
E) 34
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
61
Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Sigma before work center Delta. According to Johnson's rule, what sequence of jobs will minimize the completion time for all jobs? 
A) R-S-T-U-V
B) V-S-U-T-R
C) S-U-T-V-R
D) V-R-U-S-T
E) R-T-V-S-U

A) R-S-T-U-V
B) V-S-U-T-R
C) S-U-T-V-R
D) V-R-U-S-T
E) R-T-V-S-U
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
62
Five welding jobs are waiting to be processed. Their processing times and due dates are given below. Using the critical ratio dispatching rule, in which order should the jobs be processed? All dates are specified as days from today. 
A) B, D, A, E, C
B) C, D, A, B, E
C) C, E, A, D, B
D) E, B, A, D, C
E) B, D, A, C, E

A) B, D, A, E, C
B) C, D, A, B, E
C) C, E, A, D, B
D) E, B, A, D, C
E) B, D, A, C, E
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
63
EDD stands for what?
A) earliest due date
B) earliest design date
C) earliest detrimental date
D) earliest decision date
E) economic date determination
A) earliest due date
B) earliest design date
C) earliest detrimental date
D) earliest decision date
E) economic date determination
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
64
Average completion time for a schedule sequence at a work center is the ratio of:
A) total processing time to the number of jobs.
B) total flow time to total processing time.
C) total flow time to the number of jobs.
D) total processing time plus total late time to the number of jobs.
E) total flow time plus total late time to the number of jobs.
A) total processing time to the number of jobs.
B) total flow time to total processing time.
C) total flow time to the number of jobs.
D) total processing time plus total late time to the number of jobs.
E) total flow time plus total late time to the number of jobs.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
65
Eight jobs have been sequenced at a single work center. Total processing time for the eight jobs is 34 hours, and total flow time for the sequence is 85 hours. For this schedule, utilization is ________ and the average number of jobs in the system is ________.
A) 100 percent; 10.625
B) low; .0941
C) 0.400 or 40 percent; 2.5
D) 0.235 or 23.5 percent; 4.25
E) maximized; minimized
A) 100 percent; 10.625
B) low; .0941
C) 0.400 or 40 percent; 2.5
D) 0.235 or 23.5 percent; 4.25
E) maximized; minimized
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
66
What does the use of the shortest processing time sequencing rule generally produce?
A) maximum average lateness
B) maximum utilization
C) maximum effectiveness
D) minimum average flow time
E) B and D
A) maximum average lateness
B) maximum utilization
C) maximum effectiveness
D) minimum average flow time
E) B and D
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
67
Sequencing (or dispatching):
A) assigns dates to specific jobs or operations steps.
B) assigns jobs to work centers.
C) specifies the order in which jobs should be done at each center.
D) assigns workers to jobs.
E) assigns workers to machines.
A) assigns dates to specific jobs or operations steps.
B) assigns jobs to work centers.
C) specifies the order in which jobs should be done at each center.
D) assigns workers to jobs.
E) assigns workers to machines.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
68
Which of the following dispatching rules ordinarily gives the best results when the criterion is quickest time for completion of the full sequence of jobs?
A) shortest processing time (SPT)
B) critical ratio (CR)
C) first in, first out (FIFO)
D) first come, first served (FCFS)
E) longest processing time (LPT)
A) shortest processing time (SPT)
B) critical ratio (CR)
C) first in, first out (FIFO)
D) first come, first served (FCFS)
E) longest processing time (LPT)
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
69
Which of the following dispatching rules tends to minimize job flow time?
A) FCFS: first come, first served
B) SPT: shortest processing time
C) EDD: earliest due date
D) LPT: longest processing time
E) FCLS: first come, last served
A) FCFS: first come, first served
B) SPT: shortest processing time
C) EDD: earliest due date
D) LPT: longest processing time
E) FCLS: first come, last served
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
70
Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the earliest due date dispatching rule, in which order should the jobs be processed? 
A) C, E, A, D, B
B) A, B, C, D, E
C) B, D, A, E, C
D) C, B, A, E, D
E) B, D, A, C, E

A) C, E, A, D, B
B) A, B, C, D, E
C) B, D, A, E, C
D) C, B, A, E, D
E) B, D, A, C, E
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
71
Orders are processed in the sequence in which they arrive if (the) ________ rule sequences the jobs.
A) earliest due date
B) slack time remaining
C) first come, first served
D) critical ratio
E) Johnson's
A) earliest due date
B) slack time remaining
C) first come, first served
D) critical ratio
E) Johnson's
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
72
When a set of jobs must pass through two workstations whose sequence is fixed, ________ is the sequencing rule most commonly applied.
A) critical ratio
B) earliest due date
C) first come, first served
D) slack time remaining
E) Johnson's rule
A) critical ratio
B) earliest due date
C) first come, first served
D) slack time remaining
E) Johnson's rule
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
73
Which critical ratio value implies that a job is already late?
A) more than 100
B) 1
C) less than 1
D) 10
E) 3.4
A) more than 100
B) 1
C) less than 1
D) 10
E) 3.4
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
74
What is the priority rule that sequences jobs using the smallest ratio of due date from today to processing time?
A) critical ratio
B) earliest due date
C) first come, first served
D) longest processing time
E) shortest processing time
A) critical ratio
B) earliest due date
C) first come, first served
D) longest processing time
E) shortest processing time
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
75
Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to Johnson's rule, which job should be scheduled first in the sequence? 
A) R
B) S
C) T
D) U
E) V

A) R
B) S
C) T
D) U
E) V
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
76
Using SPT priority would result in what sequence for Jobs A, B, C, and D if their process times are 4, 6, 5, and 2 respectively?
A) ABCD
B) DCBA
C) DACB
D) DABC
E) BCAD
A) ABCD
B) DCBA
C) DACB
D) DABC
E) BCAD
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
77
Which of the following is an advantage of the FCFS dispatching rule when used in services?
A) FCFS maximizes utilization.
B) FCFS minimizes the average number of jobs in the system.
C) FCFS minimizes the average lateness of all jobs.
D) FCFS maximizes the number of jobs completed on time.
E) FCFS seems fair to customers.
A) FCFS maximizes utilization.
B) FCFS minimizes the average number of jobs in the system.
C) FCFS minimizes the average lateness of all jobs.
D) FCFS maximizes the number of jobs completed on time.
E) FCFS seems fair to customers.
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
78
The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are sequenced according to the longest processing time rule, what is the average completion time? 
A) 47.6 days
B) 65.2 days
C) 94.0 days
D) 2.5 days
E) 238.0 days

A) 47.6 days
B) 65.2 days
C) 94.0 days
D) 2.5 days
E) 238.0 days
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
79
Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the shortest processing time dispatching rule, in which order should the jobs be processed? 
A) D, B, E, A, C
B) C, A, E, B, D
C) B, D, A, E, C
D) D, A, E, B, C
E) C, E, A, B, D

A) D, B, E, A, C
B) C, A, E, B, D
C) B, D, A, E, C
D) D, A, E, B, C
E) C, E, A, B, D
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck
80
Flow time represents the time:
A) an order spends waiting for processing at a work center.
B) an order spends being processed at a work center.
C) an order spends moving from one work center to another.
D) to complete an order, including time spent in processing and in waiting.
E) none of the these
A) an order spends waiting for processing at a work center.
B) an order spends being processed at a work center.
C) an order spends moving from one work center to another.
D) to complete an order, including time spent in processing and in waiting.
E) none of the these
Unlock Deck
Unlock for access to all 124 flashcards in this deck.
Unlock Deck
k this deck