Deck 13: Progress and Performance Measurement and Evaluation

Full screen (f)
exit full mode
Question
The baseline is derived from merging information from the work packages with the project network.
Use Space or
up arrow
down arrow
to flip the card.
Question
Two major reasons for creating a baseline are to monitor and report progress and to estimate cash flow.
Question
Because of their easy-to-understand visual format, tracking Gantt charts are the most favored, used, and understandable option for reporting project status.
Question
The only accurate method for determining the true time progress of the project is to compare the project network schedule against the actual network schedule to measure if the project is on time.
Question
A "rubber baseline" occurs when, in an effort to disguise poor performance, the baseline changes to constantly match results.
Question
In calculating schedule variance and cost variance, a negative variance indicates a desirable condition, and a positive variance suggests problems.
Question
The PV, AC and CV are all required to assess the current status of the project.
Question
A project manager notices that the current EV for his project is lower than both the PV and the AC. He has reason to be concerned about the underperforming project.
Question
A CPI index of 1.11 indicates that the project has spent less money than earned.
Question
Baseline costs typically include labor, equipment, materials and direct overhead cost.
Question
Progress and performance can be measured quantitatively as well as qualitatively.
Question
Most changes will not result in serious scope changes and should be absorbed as positive or negative variances.
Question
Schedule variance measures progress in time units.
Question
The best method for assigning costs to the baseline under the 50 / 50 rule is to establish frequent checkpoints over the duration of the work package and assign completion percentages in dollar terms.
Question
In some cases, conditions or scope can change, which, in turn, will require a change in the baseline plan to recognize new information.
Question
An undesirable schedule variance always indicates that the project is running behind schedule.
Question
The PCIC index measures the project percent complete in relation to the actual resources used so far on the project.
Question
Earned value is defined as the budgeted cost of the actual work performed.
Question
A project control system allows for comparing actual performance against plan to identify deviations; however, the system doesn't impact the quality of communication between stakeholders.
Question
When revising the estimated cost at completion, there are two approaches. The EACre is determined by experts in the field and the EACf is a mathematical approach which assumes the CPI as the basis for forecasting cost at completion.
Question
The second step in the project control process for measuring and evaluating project performance is to

A) review the baseline plan with top management.
B) analyze inputs to control system.
C) compare plan against actual.
D) measure progress and performance.
E) review spending with team members.
Question
For a more complex project, statistical analysis can be applied to a control chart to identify potential causes of schedule deviation.
Question
The first step in the project control process for measuring and evaluating project performance is to

A) set a baseline plan.
B) determine the project objectives.
C) determine the project deliverables.
D) analyze the project budget.
E) review the project priority matrix.
Question
A team leader tells the project manager that as of right now, $1.20 worth of work has been accomplished for each $1 worth of scheduled work. The team leader got this information from viewing the

A) SV.
B) TCPI.
C) CPI.
D) SPI.
E) PCIB.
Question
A project manager would be glad to see a TCPI of 1.2.
Question
A common project practice is to ignore straight labor hours when calculating earned value.
Question
A ___________ Gantt chart is a simple and effective way to depict progress on a project.

A) baseline
B) control
C) variance
D) tracking
E) simple
Question
A positive VAC indicates that the project will be completed under budget.
Question
All scope changes that result in increased costs should be avoided.
Question
The final step in the project control process for measuring and evaluating project performance is to

A) take appropriate action.
B) prepare a report to top management.
C) follow up on corrective action.
D) measure progress and performance.
E) review spending with team members.
Question
The third step in the project control process for measuring and evaluating project performance is to

A) review the baseline plan with top management.
B) analyze inputs to the control system.
C) compare the plan against actual performance.
D) measure both progress and performance.
E) review spending with team members.
Question
Although it is very difficult to measure, measuring technical performance is as important as measuring schedule and cost performance.
Question
A Control Chart can be used to estimate schedule trends.
Question
Deciding what data to collect, collecting the data and analyzing it, and reporting this data are all parts of structuring a project monitoring information system.
Question
A project manager just received the following information on her project: PV = 300, EV = 300, AC = 200. In terms of cost at completion,

A) the project will currently finish under budget, assuming the project continues to perform in this way.
B) the project will currently finish over budget, assuming the project continues to perform in this way.
C) the project will currently finish on budget, assuming the project continues to perform in this way.
D) the project will currently finish behind schedule, assuming the project continues to perform in this way.
E) there is insufficient information to draw conclusions.
Question
A tool used to monitor past project schedule performance and current performance, and to estimate future schedule trends is a simple line chart known as a

A) Gantt chart.
B) network diagram.
C) PERT chart.
D) milestone chart.
E) project control chart.
Question
The earned value system starts with the time-phased costs that provide the project baseline, which is called the

A) planned budgeted value of work scheduled.
B) planned budgeted value of work completed.
C) earned value of work scheduled.
D) scheduled value of work scheduled.
E) scheduled value of work completed.
Question
If the cost of labor and materials has not been separated there is additional analysis required to determine the cause of the calculated variance.
Question
In monitoring project time (schedule) performance, actual performance should be compared to

A) budgets for the current year.
B) top management's targets.
C) project network schedule derived from the WBS / OBS.
D) progress on similar past projects.
E) previous status reports.
Question
The schedule variance is the best way to get an accurate assessment of schedule performance.
Question
Which of the following methods of variance analysis is the best indicator of how far off the budget a project will be at completion?

A) BAC
B) EAC
C) ETC
D) VAC
E) TCPI
Question
The cost variance for a project is calculated by

A) EV − AC.
B) AC − SV.
C) PV − EV.
D) CV − EV.
E) EV − PV.
Question
A project manager receives the following information on his project: PV = 4,500, AC =4,000, EV = 5,000. How well is the project doing in terms of budget?

A) Right on budget
B) 1,000 under budget
C) 1,000 over budget
D) 500 under budget
E) 500 over budget
Question
The chief financial officer receives the following information on a project: PV = 10,000, EV = 12,000, AC = 8,000, BAC = 20,000, EAC = 13,333. How is the project doing in terms of schedule?

A) More work has been done than planned
B) Less work has been done than planned
C) The same amount of work has been done than planned
D) The project has cost more than planned
E) There is not enough information to draw a conclusion
Question
A program financial accountant learns that a project is currently earning $1.15 for each dollar actually spent. The accountant is able to determine this by looking at the

A) EV.
B) BAC.
C) SV.
D) SPI.
E) CPI.
Question
Which performance index is the most potentially misleading?

A) CPI
B) EV
C) CV
D) SV
E) EAC
Question
When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the

A) 0 / 100 percent rule.
B) task complete rule.
C) degree complete rule.
D) work complete rule.
E) percent complete rule.
Question
Of the following costs, which are NOT included in baseline?

A) Suppliers
B) Equipment
C) Labor
D) Budget reserves
E) Contractors
Question
Which of the following methods will measure the scheduling efficiency of the work accomplished to date?

A) SV / CV
B) EV / PV
C) EV / AC
D) AC / SV
E) AC / CV
Question
The value that tells you the planned value of work that has actually been completed is the

A) SV.
B) PV.
C) EV.
D) AC.
E) CV.
Question
Baseline project budgets are derived from

A) the organization's overall budget.
B) time-phasing the work packages.
C) top management directions.
D) the total direct, direct project overhead and G&A overhead costs.
E) the earned value system.
Question
Which of the following methods will measure the cost efficiency of the work accomplished to date?

A) SV / CV
B) EV / PV
C) EV / AC
D) AC / SV
E) AC / CV
Question
The earned value of a project is the

A) project cost to date adjusted for project scope changes.
B) total project cost to date.
C) cost incurred minus the planned cost.
D) percent of the original budget that has been earned by work that is completed.
E) the planned time-phased baseline of the value of work scheduled.
Question
The indicator that tells you the amount each remaining dollar must earn for the project to stay within budget is the

A) PCIC.
B) VAC.
C) CPI.
D) SPI.
E) TCPI.
Question
The schedule variance for a project is calculated by:

A) EV − AC
B) AC − SV
C) PV − EV
D) CV − EV
E) EV − PV
Question
A CPI or SPI value less than one indicates that the project is currently

A) under cost or behind schedule.
B) over cost or ahead of schedule.
C) under cost or ahead of schedule.
D) over cost or behind schedule.
E) on cost or on schedule.
Question
A project manager notices that $5,560 worth of work that was scheduled to be completed at this time has not been accomplished. She knows this by looking at the

A) EV.
B) TCPI.
C) SV.
D) PCIB.
E) EAC.
Question
A reason that the duration on a task may differ from an original duration on a tracking Gantt chart could be

A) an expected delay.
B) new information on the task.
C) the task has been cancelled.
D) a new budget cycle.
E) an unexpected delay.
Question
Which of the following is NOT true regarding scope creep?

A) It commonly occurs late in projects.
B) It is frequently unnoticed until time delays or cost overruns are observed.
C) It wears down team motivation and cohesiveness.
D) Project suppliers resent frequent changes.
E) Scope changes can represent significant opportunity.
Question
Which of the following are required to assess the current status of a project using the earned-value cost / schedule system?

A) BAC, EAC, and ETC
B) VAC, EAC, and BAC
C) CV, SV, and BAC
D) PV, EV, and AC
E) TCPI, EV, and PV
Question
________ is simply the percent complete times the original budget.

A) Actual cost
B) Earned value
C) Cost Performance Index
D) Schedule Performance Index
E) Budget at Completion
Question
Causes for scope creep can include

A) newly identified features.
B) incorrect design assumptions.
C) new technology.
D) users want more functionality.
E) All of these alternatives are correct.
Question
Because of their easy-to-understand visual format, ________ charts are the most favored, used, and understandable tool used to report project schedule status.

A) Network
B) Work breakdown structure
C) Gantt
D) Burndown
E) Cost / schedule
Question
The indicator that tells you the planned time-phased value of the work that is scheduled is the _______________.

A) planned value (PV)
B) earned value (EV)
C) schedule variance (SV)
D) cost variance (CV)
E) None of these alternatives is correct.
Question
The ________ rule assumes credit is earned for having performed the work once it is completed. This rule is usually used for work packages having very short durations.

A) one-to-ten
B) one-to-one
C) 50 / 100
D) 0 / 100
E) 50 / 50
Question
When reviewing the cost variance on a project, you compare Earned Value with

A) actual cost.
B) realized risks.
C) planned value.
D) Both actual cost and planned value.
E) All of these alternatives are correct.
Question
The ________ variance is the difference between the earned value to date and the baseline schedule.

A) schedule
B) cost
C) budget
D) time
E) performance
Question
Baseline project budgets are derived from time-phasing the work ________.

A) products
B) milestones
C) packages
D) modules
E) resources
Question
A project can have a negative schedule variance and still be ahead of schedule when

A) all budget targets have been achieved.
B) earned value exceeds planned value.
C) progress on the critical path is faster than non-critical path tasks.
D) actual cost exceeds earned value.
E) None of these alternatives is correct.
Question
A Cost / Schedule graph can be interpreted using ___________ for its vertical axis and _______ for its horizontal axis.

A) Earned Value; Schedule.
B) Dates; Actual Cost.
C) Baseline; Deadline.
D) Dollar Amounts; Time.
E) None of these alternatives is correct.
Question
Conditions or scope can change during execution, which, in turn, will require a change to the __________ plan to recognize the new information.

A) project
B) budget
C) schedule
D) overall
E) baseline
Question
A negative CV indicates the project is currently ________ budget.

A) over
B) under
C) on track with
D) ahead of
E) behind
Question
When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the ____________ rule.

A) estimated completion
B) estimated cost
C) percent complete
D) estimation
E) estimation method
Question
The value that tells you how much work has been completed in dollars of value is ___________.

A) earned value
B) planned value
C) actual cost
D) budgeted cost of work scheduled
E) baseline plan
Question
Which of the following is not one of the four steps for measuring and evaluating project performance?

A) Setting a baseline plan.
B) Setting a baseline budget.
C) Taking action.
D) Measuring progress and performance.
E) Comparing plan against actual.
Question
The ________ variance is the difference between the earned value and the actual costs for the work completed to date.

A) schedule
B) cost
C) budget
D) time
E) performance
Question
Taking action in the four steps for measuring and evaluating project performance can only happen after _________.

A) setting a baseline plan.
B) setting a baseline budget.
C) measuring progress and performance.
D) comparing plan against actual.
E) writing a progress and performance report.
Question
The project network schedule is derived from the _______ and it serves as the baseline to compare against actual performance.

A) Risk Breakdown Structure
B) Work Breakdown Structure
C) Gantt Chart
D) Organization Breakdown Structure
E) Risk Register
Question
A negative cost variance combined with a negative schedule variance is an indicator of

A) actual cost exceeding earned value.
B) planned value exceeding earned value.
C) budget over-runs.
D) behind schedule.
E) All of these alternatives are correct.
Question
The start of a task may be moved on a tracking Gantt due to

A) increase in earned value.
B) lack of an updated control chart.
C) a predecessor task starting late.
D) Both an increase in earned value and a lack of an updated control chart.
E) All of these alternatives are correct.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/98
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 13: Progress and Performance Measurement and Evaluation
1
The baseline is derived from merging information from the work packages with the project network.
True
2
Two major reasons for creating a baseline are to monitor and report progress and to estimate cash flow.
True
3
Because of their easy-to-understand visual format, tracking Gantt charts are the most favored, used, and understandable option for reporting project status.
True
4
The only accurate method for determining the true time progress of the project is to compare the project network schedule against the actual network schedule to measure if the project is on time.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
5
A "rubber baseline" occurs when, in an effort to disguise poor performance, the baseline changes to constantly match results.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
6
In calculating schedule variance and cost variance, a negative variance indicates a desirable condition, and a positive variance suggests problems.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
7
The PV, AC and CV are all required to assess the current status of the project.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
8
A project manager notices that the current EV for his project is lower than both the PV and the AC. He has reason to be concerned about the underperforming project.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
9
A CPI index of 1.11 indicates that the project has spent less money than earned.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
10
Baseline costs typically include labor, equipment, materials and direct overhead cost.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
11
Progress and performance can be measured quantitatively as well as qualitatively.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
12
Most changes will not result in serious scope changes and should be absorbed as positive or negative variances.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
13
Schedule variance measures progress in time units.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
14
The best method for assigning costs to the baseline under the 50 / 50 rule is to establish frequent checkpoints over the duration of the work package and assign completion percentages in dollar terms.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
15
In some cases, conditions or scope can change, which, in turn, will require a change in the baseline plan to recognize new information.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
16
An undesirable schedule variance always indicates that the project is running behind schedule.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
17
The PCIC index measures the project percent complete in relation to the actual resources used so far on the project.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
18
Earned value is defined as the budgeted cost of the actual work performed.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
19
A project control system allows for comparing actual performance against plan to identify deviations; however, the system doesn't impact the quality of communication between stakeholders.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
20
When revising the estimated cost at completion, there are two approaches. The EACre is determined by experts in the field and the EACf is a mathematical approach which assumes the CPI as the basis for forecasting cost at completion.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
21
The second step in the project control process for measuring and evaluating project performance is to

A) review the baseline plan with top management.
B) analyze inputs to control system.
C) compare plan against actual.
D) measure progress and performance.
E) review spending with team members.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
22
For a more complex project, statistical analysis can be applied to a control chart to identify potential causes of schedule deviation.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
23
The first step in the project control process for measuring and evaluating project performance is to

A) set a baseline plan.
B) determine the project objectives.
C) determine the project deliverables.
D) analyze the project budget.
E) review the project priority matrix.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
24
A team leader tells the project manager that as of right now, $1.20 worth of work has been accomplished for each $1 worth of scheduled work. The team leader got this information from viewing the

A) SV.
B) TCPI.
C) CPI.
D) SPI.
E) PCIB.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
25
A project manager would be glad to see a TCPI of 1.2.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
26
A common project practice is to ignore straight labor hours when calculating earned value.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
27
A ___________ Gantt chart is a simple and effective way to depict progress on a project.

A) baseline
B) control
C) variance
D) tracking
E) simple
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
28
A positive VAC indicates that the project will be completed under budget.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
29
All scope changes that result in increased costs should be avoided.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
30
The final step in the project control process for measuring and evaluating project performance is to

A) take appropriate action.
B) prepare a report to top management.
C) follow up on corrective action.
D) measure progress and performance.
E) review spending with team members.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
31
The third step in the project control process for measuring and evaluating project performance is to

A) review the baseline plan with top management.
B) analyze inputs to the control system.
C) compare the plan against actual performance.
D) measure both progress and performance.
E) review spending with team members.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
32
Although it is very difficult to measure, measuring technical performance is as important as measuring schedule and cost performance.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
33
A Control Chart can be used to estimate schedule trends.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
34
Deciding what data to collect, collecting the data and analyzing it, and reporting this data are all parts of structuring a project monitoring information system.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
35
A project manager just received the following information on her project: PV = 300, EV = 300, AC = 200. In terms of cost at completion,

A) the project will currently finish under budget, assuming the project continues to perform in this way.
B) the project will currently finish over budget, assuming the project continues to perform in this way.
C) the project will currently finish on budget, assuming the project continues to perform in this way.
D) the project will currently finish behind schedule, assuming the project continues to perform in this way.
E) there is insufficient information to draw conclusions.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
36
A tool used to monitor past project schedule performance and current performance, and to estimate future schedule trends is a simple line chart known as a

A) Gantt chart.
B) network diagram.
C) PERT chart.
D) milestone chart.
E) project control chart.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
37
The earned value system starts with the time-phased costs that provide the project baseline, which is called the

A) planned budgeted value of work scheduled.
B) planned budgeted value of work completed.
C) earned value of work scheduled.
D) scheduled value of work scheduled.
E) scheduled value of work completed.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
38
If the cost of labor and materials has not been separated there is additional analysis required to determine the cause of the calculated variance.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
39
In monitoring project time (schedule) performance, actual performance should be compared to

A) budgets for the current year.
B) top management's targets.
C) project network schedule derived from the WBS / OBS.
D) progress on similar past projects.
E) previous status reports.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
40
The schedule variance is the best way to get an accurate assessment of schedule performance.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
41
Which of the following methods of variance analysis is the best indicator of how far off the budget a project will be at completion?

A) BAC
B) EAC
C) ETC
D) VAC
E) TCPI
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
42
The cost variance for a project is calculated by

A) EV − AC.
B) AC − SV.
C) PV − EV.
D) CV − EV.
E) EV − PV.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
43
A project manager receives the following information on his project: PV = 4,500, AC =4,000, EV = 5,000. How well is the project doing in terms of budget?

A) Right on budget
B) 1,000 under budget
C) 1,000 over budget
D) 500 under budget
E) 500 over budget
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
44
The chief financial officer receives the following information on a project: PV = 10,000, EV = 12,000, AC = 8,000, BAC = 20,000, EAC = 13,333. How is the project doing in terms of schedule?

A) More work has been done than planned
B) Less work has been done than planned
C) The same amount of work has been done than planned
D) The project has cost more than planned
E) There is not enough information to draw a conclusion
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
45
A program financial accountant learns that a project is currently earning $1.15 for each dollar actually spent. The accountant is able to determine this by looking at the

A) EV.
B) BAC.
C) SV.
D) SPI.
E) CPI.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
46
Which performance index is the most potentially misleading?

A) CPI
B) EV
C) CV
D) SV
E) EAC
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
47
When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the

A) 0 / 100 percent rule.
B) task complete rule.
C) degree complete rule.
D) work complete rule.
E) percent complete rule.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
48
Of the following costs, which are NOT included in baseline?

A) Suppliers
B) Equipment
C) Labor
D) Budget reserves
E) Contractors
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
49
Which of the following methods will measure the scheduling efficiency of the work accomplished to date?

A) SV / CV
B) EV / PV
C) EV / AC
D) AC / SV
E) AC / CV
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
50
The value that tells you the planned value of work that has actually been completed is the

A) SV.
B) PV.
C) EV.
D) AC.
E) CV.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
51
Baseline project budgets are derived from

A) the organization's overall budget.
B) time-phasing the work packages.
C) top management directions.
D) the total direct, direct project overhead and G&A overhead costs.
E) the earned value system.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
52
Which of the following methods will measure the cost efficiency of the work accomplished to date?

A) SV / CV
B) EV / PV
C) EV / AC
D) AC / SV
E) AC / CV
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
53
The earned value of a project is the

A) project cost to date adjusted for project scope changes.
B) total project cost to date.
C) cost incurred minus the planned cost.
D) percent of the original budget that has been earned by work that is completed.
E) the planned time-phased baseline of the value of work scheduled.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
54
The indicator that tells you the amount each remaining dollar must earn for the project to stay within budget is the

A) PCIC.
B) VAC.
C) CPI.
D) SPI.
E) TCPI.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
55
The schedule variance for a project is calculated by:

A) EV − AC
B) AC − SV
C) PV − EV
D) CV − EV
E) EV − PV
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
56
A CPI or SPI value less than one indicates that the project is currently

A) under cost or behind schedule.
B) over cost or ahead of schedule.
C) under cost or ahead of schedule.
D) over cost or behind schedule.
E) on cost or on schedule.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
57
A project manager notices that $5,560 worth of work that was scheduled to be completed at this time has not been accomplished. She knows this by looking at the

A) EV.
B) TCPI.
C) SV.
D) PCIB.
E) EAC.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
58
A reason that the duration on a task may differ from an original duration on a tracking Gantt chart could be

A) an expected delay.
B) new information on the task.
C) the task has been cancelled.
D) a new budget cycle.
E) an unexpected delay.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
59
Which of the following is NOT true regarding scope creep?

A) It commonly occurs late in projects.
B) It is frequently unnoticed until time delays or cost overruns are observed.
C) It wears down team motivation and cohesiveness.
D) Project suppliers resent frequent changes.
E) Scope changes can represent significant opportunity.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
60
Which of the following are required to assess the current status of a project using the earned-value cost / schedule system?

A) BAC, EAC, and ETC
B) VAC, EAC, and BAC
C) CV, SV, and BAC
D) PV, EV, and AC
E) TCPI, EV, and PV
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
61
________ is simply the percent complete times the original budget.

A) Actual cost
B) Earned value
C) Cost Performance Index
D) Schedule Performance Index
E) Budget at Completion
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
62
Causes for scope creep can include

A) newly identified features.
B) incorrect design assumptions.
C) new technology.
D) users want more functionality.
E) All of these alternatives are correct.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
63
Because of their easy-to-understand visual format, ________ charts are the most favored, used, and understandable tool used to report project schedule status.

A) Network
B) Work breakdown structure
C) Gantt
D) Burndown
E) Cost / schedule
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
64
The indicator that tells you the planned time-phased value of the work that is scheduled is the _______________.

A) planned value (PV)
B) earned value (EV)
C) schedule variance (SV)
D) cost variance (CV)
E) None of these alternatives is correct.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
65
The ________ rule assumes credit is earned for having performed the work once it is completed. This rule is usually used for work packages having very short durations.

A) one-to-ten
B) one-to-one
C) 50 / 100
D) 0 / 100
E) 50 / 50
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
66
When reviewing the cost variance on a project, you compare Earned Value with

A) actual cost.
B) realized risks.
C) planned value.
D) Both actual cost and planned value.
E) All of these alternatives are correct.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
67
The ________ variance is the difference between the earned value to date and the baseline schedule.

A) schedule
B) cost
C) budget
D) time
E) performance
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
68
Baseline project budgets are derived from time-phasing the work ________.

A) products
B) milestones
C) packages
D) modules
E) resources
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
69
A project can have a negative schedule variance and still be ahead of schedule when

A) all budget targets have been achieved.
B) earned value exceeds planned value.
C) progress on the critical path is faster than non-critical path tasks.
D) actual cost exceeds earned value.
E) None of these alternatives is correct.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
70
A Cost / Schedule graph can be interpreted using ___________ for its vertical axis and _______ for its horizontal axis.

A) Earned Value; Schedule.
B) Dates; Actual Cost.
C) Baseline; Deadline.
D) Dollar Amounts; Time.
E) None of these alternatives is correct.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
71
Conditions or scope can change during execution, which, in turn, will require a change to the __________ plan to recognize the new information.

A) project
B) budget
C) schedule
D) overall
E) baseline
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
72
A negative CV indicates the project is currently ________ budget.

A) over
B) under
C) on track with
D) ahead of
E) behind
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
73
When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the ____________ rule.

A) estimated completion
B) estimated cost
C) percent complete
D) estimation
E) estimation method
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
74
The value that tells you how much work has been completed in dollars of value is ___________.

A) earned value
B) planned value
C) actual cost
D) budgeted cost of work scheduled
E) baseline plan
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
75
Which of the following is not one of the four steps for measuring and evaluating project performance?

A) Setting a baseline plan.
B) Setting a baseline budget.
C) Taking action.
D) Measuring progress and performance.
E) Comparing plan against actual.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
76
The ________ variance is the difference between the earned value and the actual costs for the work completed to date.

A) schedule
B) cost
C) budget
D) time
E) performance
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
77
Taking action in the four steps for measuring and evaluating project performance can only happen after _________.

A) setting a baseline plan.
B) setting a baseline budget.
C) measuring progress and performance.
D) comparing plan against actual.
E) writing a progress and performance report.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
78
The project network schedule is derived from the _______ and it serves as the baseline to compare against actual performance.

A) Risk Breakdown Structure
B) Work Breakdown Structure
C) Gantt Chart
D) Organization Breakdown Structure
E) Risk Register
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
79
A negative cost variance combined with a negative schedule variance is an indicator of

A) actual cost exceeding earned value.
B) planned value exceeding earned value.
C) budget over-runs.
D) behind schedule.
E) All of these alternatives are correct.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
80
The start of a task may be moved on a tracking Gantt due to

A) increase in earned value.
B) lack of an updated control chart.
C) a predecessor task starting late.
D) Both an increase in earned value and a lack of an updated control chart.
E) All of these alternatives are correct.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 98 flashcards in this deck.