Deck 9: Reducing Project Duration

Full screen (f)
exit full mode
Question
Managers have several effective methods for crashing specific project activities when resources are not constrained.
Use Space or
up arrow
down arrow
to flip the card.
Question
The cost slope of an activity is calculated by dividing the run by the rise.
Question
When adding resources, there are limits as to how much speed can be gained.
Question
An activity must be crashed on each critical path in order to reduce project duration.
Question
Total cost for specific project durations is computed and then compared with the benefits of reducing project time, before the project begins or while it is in progress.
Question
Indirect costs generally represent overhead costs such as supervision, administration, consultants, and interest.
Question
When reducing project duration, there will always be an optimum cost-time point where the total cost of the project is less than it was when the project was initially planned under normal conditions.
Question
Brooks' law states that adding manpower to a software project helps keep it on schedule.
Question
Crashing can negatively impact the morale and motivation of the project team.
Question
The higher the cost slope of an activity the lower the cost to reduce its duration.
Question
Crashing frequently results in over allocation of resources.
Question
Because direct costs are assumed to be developed from "normal" methods and in a "normal" amount of time, any reduction in activity time should add to the costs of the activity.
Question
If indirect costs are a significant percentage of total project costs, reductions in project time can represent very real savings.
Question
Shortening an activity's duration is termed crashing.
Question
The total cost for each time unit of a project is the sum of labor, materials, and equipment.
Question
Crashing a more expensive activity may be wise if fewer inherent risks are involved.
Question
Direct costs are so named because they can be assigned directly to a work package and activity.
Question
When crashing an activity, you always crash to its crash point.
Question
There are more options available for reducing project time if you are not resource constrained.
Question
Incentive contracts can make the reduction of project time rewarding-usually for both the project contractor and owner.
Question
Crashing activities on a project network that is sensitive could increase the risk of the project being late.
Question
As a project is crashed and project duration is reduced, indirect costs typically

A) increase.
B) become unstable.
C) decrease.
D) become unreliable.
E) stay the same.
Question
Resources are frequently over-allocated when crashing a schedule.
Question
The direct cost for completing an activity in the shortest time it can realistically be completed in is called its __________ cost.

A) normal
B) reserve
C) crash
D) accelerated
E) expedited
Question
Before crashing, direct costs for an activity represent normal costs, which typically mean low-cost, efficient methods for completing the activity in a(n) ________ amount of time.

A) normal
B) budgeted
C) optimized
D) expected
E) targeted
Question
One of the advantages of using a project cost-duration graph is that it keeps the importance of indirect costs in the forefront of decision making.
Question
Which of the following is NOT considered a project indirect cost?

A) Supervision
B) Consultants
C) Equipment
D) Interest
E) The project manager's salary
Question
The simplest way to reduce cost on a project is to reduce the scope of a project.

A) imposed project deadlines.
B) time to market.
C) unforeseen project delays.
D) high overhead.
E) incentive contracts.
Question
As a project is crashed and project duration is reduced, direct costs typically

A) increase.
B) become unstable.
C) decrease.
D) become unreliable.
E) stay the same.
Question
Cost slope can be determined by dividing the

A) run by the rise.
B) rise by the run.
C) crash cost by the normal cost.
D) normal cost by the crash cost.
E) indirect cost by direct cost.
Question
Design flaws, equipment breakdown and adverse weather can create negative slack. These are examples of the need for reducing project duration on successive critical activities that was caused by

A) imposed project deadlines.
B) time to market.
C) unforeseen project delays.
D) high overhead.
E) incentive contracts.
Question
The accuracy of crash times and costs is frequently rough at best, when compared with normal time and cost.
Question
For most projects, the estimation of a crash time is relatively easy.
Question
An activity's crash cost includes ________ costs.

A) direct
B) indirect
C) overhead
D) total
E) normal
Question
Making the decision to crash is the result of careful fiscal analysis and deep understanding of the project.
Question
In a Project Cost-Duration Graph, total project costs are a sum of

A) labor, material and equipment costs.
B) direct costs plus interest.
C) direct labor costs and the project manager's salary.
D) direct costs and the project manager's salary.
E) direct and indirect costs.
Question
The shortest possible time an activity can be completed realistically is called ___­­­_____ time.

A) expedited
B) accelerated
C) crash
D) optimistic
E) optimal
Question
Insensitive networks are a rarity; Planning for a sensitive network is more practical.
Question
Intense global competition and rapid technological advances create pressure to develop projects rapidly. This is an example of reducing project duration caused by

A) imposed project deadlines.
B) time to market.
C) unforeseen project delays.
D) high overhead.
E) incentive contracts.
Question
A construction contractor finished a bridge across a river 12 months early and received more than $5 million for the early completion. This is an example of reducing project duration caused by

A) imposed project deadlines.
B) time to market.
C) unforeseen project delays.
D) high overhead.
E) incentive contracts.
Question
When it is necessary to reduce project duration and resources are constrained, which of the following is NOT a reasonable option?

A) Establish a core project team
B) Fast-tracking
C) Reduce project scope
D) Compromise quality
E) Use critical-chain project management
Question
When reducing project duration, the duration for a project that is optimal is at the point where

A) direct costs are the lowest.
B) indirect costs are the lowest.
C) direct costs equal indirect costs.
D) total project costs are the lowest.
E) the project changes from time-constrained to resource-constrained.
Question
When determining which activity to crash, there are other factors that should be assessed beyond cost. Which of the following is NOT one of these factors?

A) The inherent risk associated with the activity
B) How crashing will impact the morale and motivation of the individuals working on that activity
C) Resource availability after crashing that activity
D) The level of difficulty involved in completing the activity
E) When during the project the activity will occur
Question
Which of the following is NOT one of the more commonly used options for cutting project costs?

A) Reduce project scope
B) Have owner take more responsibility
C) Move the completion date further out
D) Brainstorm cost savings options
E) Outsource project activities
Question
Which of the following is NOT a technique for accelerating project completion when resources are not constrained?

A) Assign additional staff and equipment
B) Establish a core team
C) Do it twice-fast and correctly
D) Reduce project scope
E) Compromise quality
Question
Which of the following correctly calculates an activity's cost slope?

A) (normal cost - crash cost) / (normal time - crash time)
B) (crash cost - normal cost) / (normal time - crash time)
C) (normal time - crash time) / (crash cost - normal cost)
D) (normal time - crash time) / (normal cost - crash cost)
E) (crash cost - normal cost) / (crash time - normal time)
Question
The relationship between the normal point and the crash point is assumed to be

A) linear.
B) curvilinear.
C) variable.
D) conversely related.
E) exponentially related.
Question
Sometimes very high __________ costs are recognized before a project begins and reducing these costs through shorter project durations becomes a high priority.

A) labor
B) direct
C) project
D) overhead
E) interest
Question
Which of the following projects would be least benefited if additional resources were added?

A) Splitting and stacking a cord of wood
B) Developing new software
C) Harvesting a crop by hand
D) Building a cabin
E) Moving to a new house
Question
When a project manager must reduce project duration but resources are constrained, creating a software program that will have less functionality than originally planned or building a house without the bonus room and the basement that the owner originally specified in the plans would both be examples of

A) fast-tracking.
B) use critical-chain project management.
C) reduce project scope.
D) compromise quality.
E) do it twice-fast and correctly.
Question
Which of the following is NOT a rational reason to reduce project duration?

A) Incentive contracts
B) High network sensitivity
C) Imposed deadlines
D) High overhead costs
E) Unforeseen delays
Question
Reducing project duration

A) involves crashing all activities to their crash point.
B) can only be done when resources are not constrained.
C) is always more expensive.
D) tends to increase network sensitivity.
E) should be considered for all projects.
Question
In selecting the best activity to crash you would first select the activity with the

A) least steep slope.
B) earliest start time.
C) longest duration.
D) most steep slope.
E) largest crash time.
Question
One way of reducing project costs is identifying tasks that _________ can do themselves.

A) vendors
B) suppliers
C) customers
D) company employees
E) project teams
Question
All of the following are disadvantages of scheduling overtime EXCEPT

A) overtime is associated with additional costs of coordination and communication.
B) sustained overtime work by salaried employees may incur burnout.
C) productivity is reduced the longer one is working.
D) more hours results in higher expenses if paying workers hourly.
E) continued overtime can lead to a higher turnover rate.
Question
When reducing project duration, the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known. After this, the critical path must be identified. What is the next step?

A) Find the activity with the lowest crash cost
B) Calculate the optimum cost-time point
C) Calculate the crash point
D) Calculate indirect cost per time unit
E) Find the activity with the steepest cost slope
Question
According to Brooks' Law, adding more people to a late project is most likely to have which of the following impacts?

A) Keep the project from slipping any further
B) Get the project back on schedule
C) Make the project slip further
D) Lead to burnout
E) Decrease team motivation
Question
An activity's normal time and cost are 10 and $120, respectively. Its estimated crash time and cost are 7 and $180, respectively. What is this activity's crash cost per time unit?

A) $20
B) $30
C) $40
D) $50
E) $60
Question
Helen has just learned that she needs to reduce the duration of her project to meet an imposed deadline. She has calculated the crash cost per unit and knows the maximum units each activity can be reduced. What is the next step?

A) Find the activity with the lowest crash cost
B) Calculate the optimum cost-time point
C) Calculate the crash point
D) Identify the critical path
E) Find the activity with the highest crash cost
Question
The less steep the cost slope of an activity, the

A) less it costs to shorten one time period.
B) more it costs to shorten one time period.
C) smaller the crash time is.
D) larger the crash time is.
E) cannot be determined by the information given.
Question
The direct cost for completing an activity as early as possible is called its ________ cost.

A) budgeted
B) time-limited
C) crash
D) minimal
E) early completion
Question
An activity's ________ is calculated by dividing the rise by the run.

A) run rate
B) rise rate
C) rise / run rate
D) slope
E) daily cost
Question
Costs such as labor, materials, equipment, or sub-contractors are examples of ________ project costs.

A) direct
B) budgeted
C) accumulated
D) indirect
E) time-phased
Question
The ________ project cost is the sum of the indirect and direct costs.

A) accumulated
B) total
C) budgeted
D) time-phased
E) estimated
Question
Overhead costs such as supervision, administration, consultants, and interest are examples of ________ project costs.

A) direct
B) budgeted
C) accumulated
D) indirect
E) time-phased
Question
Which of the following is not likely to result in an imposed deadline?

A) Design flaws.
B) Marketing promises the product to the customer within three months.
C) The president announces availability of the product in one year.
D) The chief technology officer says, "finish the projects in six months or start packing."
E) Intense global competition.
Question
It is going to cost $120,000 a day simply to house and feed a construction crew in the farthest reaches of northern Alaska. This would be an example of a situation requiring reducing the project duration due to

A) imposed project deadlines.
B) time to market.
C) unforeseen project delays.
D) high overhead.
E) incentive contracts.
Question
When the project team is salaried, which of the following is the preferred choice for accelerating project completion?

A) Assign additional staff and equipment
B) Subcontract work
C) Schedule overtime
D) Outsource project work
E) Establish a core project team
Question
An insensitive project network has the benefit of:

A) Not increasing risk as activities are initially crashed.
B) Having potential for real cost savings when crashed.
C) Having potential for significant time savings when crashed.
D) Having potential for flexible scheduling.
E) All of these alternatives are correct.
Question
Direct costs are assignable directly to a particular ________.

A) activity
B) resource
C) work package
D) task
E) milestone
Question
Consider the following table of activities that describes a project network. Which activity will you crash first?

A) A
B) B
C) C
D) D
E) E
Question
There are fewer options available for reducing project time if you are __________________ than if you can spend more than your original budget.

A) time-constrained
B) vision-limited
C) schedule-constrained
D) resource-constrained
E) physically-constrained
Question
Consider the following table of activities that describes a project network. Which activity will you crash second?

A) A
B) B
C) C
D) D
E) E
Question
In order to shorten the duration of a project the project manager should limit the choices of activities to just those that are on the __________.

A) shortest path
B) path with the greatest variability
C) critical path
D) path with the least amount of resources required
E) path with the most resources required
Question
A project that has several near-critical or critical paths is said to be

A) elastic.
B) fully consumed.
C) inherently risky.
D) sensitive.
E) insensitive.
Question
When crashing a schedule, this may set in when a least-cost method is used.

A) Increased risk
B) Fatigue and resentment
C) Increased cost
D) Decrease in available management reserve
E) Reduced quality
Question
Reducing the duration of an activity is called ________.

A) reduction
B) making smaller
C) crashing
D) re-assessment
E) acceleration
Question
Because direct costs are assumed to be developed from normal methods and in a normal amount of time, any reduction in activity time should ________ the direct cost of the activity.

A) decrease
B) increase
C) reduce
D) expand
E) approximate
Question
Compressing activities on a project with a sensitive project network will:

A) Increase risk of delaying the project.
B) Improve cost-time crashing success.
C) Reduce scheduling flexibility.
D) Increase risk of delaying the project and reduce scheduling flexibility.
E) Increase risk of delaying the project but improve cost-time crashing success.
Question
The ________ time for an activity represents low-cost, realistic, efficient methods for completing the activity under typical conditions.

A) normal
B) crash
C) estimated
D) accelerated
E) completion
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/106
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 9: Reducing Project Duration
1
Managers have several effective methods for crashing specific project activities when resources are not constrained.
True
2
The cost slope of an activity is calculated by dividing the run by the rise.
False
3
When adding resources, there are limits as to how much speed can be gained.
True
4
An activity must be crashed on each critical path in order to reduce project duration.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
5
Total cost for specific project durations is computed and then compared with the benefits of reducing project time, before the project begins or while it is in progress.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
6
Indirect costs generally represent overhead costs such as supervision, administration, consultants, and interest.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
7
When reducing project duration, there will always be an optimum cost-time point where the total cost of the project is less than it was when the project was initially planned under normal conditions.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
8
Brooks' law states that adding manpower to a software project helps keep it on schedule.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
9
Crashing can negatively impact the morale and motivation of the project team.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
10
The higher the cost slope of an activity the lower the cost to reduce its duration.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
11
Crashing frequently results in over allocation of resources.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
12
Because direct costs are assumed to be developed from "normal" methods and in a "normal" amount of time, any reduction in activity time should add to the costs of the activity.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
13
If indirect costs are a significant percentage of total project costs, reductions in project time can represent very real savings.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
14
Shortening an activity's duration is termed crashing.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
15
The total cost for each time unit of a project is the sum of labor, materials, and equipment.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
16
Crashing a more expensive activity may be wise if fewer inherent risks are involved.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
17
Direct costs are so named because they can be assigned directly to a work package and activity.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
18
When crashing an activity, you always crash to its crash point.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
19
There are more options available for reducing project time if you are not resource constrained.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
20
Incentive contracts can make the reduction of project time rewarding-usually for both the project contractor and owner.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
21
Crashing activities on a project network that is sensitive could increase the risk of the project being late.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
22
As a project is crashed and project duration is reduced, indirect costs typically

A) increase.
B) become unstable.
C) decrease.
D) become unreliable.
E) stay the same.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
23
Resources are frequently over-allocated when crashing a schedule.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
24
The direct cost for completing an activity in the shortest time it can realistically be completed in is called its __________ cost.

A) normal
B) reserve
C) crash
D) accelerated
E) expedited
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
25
Before crashing, direct costs for an activity represent normal costs, which typically mean low-cost, efficient methods for completing the activity in a(n) ________ amount of time.

A) normal
B) budgeted
C) optimized
D) expected
E) targeted
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
26
One of the advantages of using a project cost-duration graph is that it keeps the importance of indirect costs in the forefront of decision making.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
27
Which of the following is NOT considered a project indirect cost?

A) Supervision
B) Consultants
C) Equipment
D) Interest
E) The project manager's salary
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
28
The simplest way to reduce cost on a project is to reduce the scope of a project.

A) imposed project deadlines.
B) time to market.
C) unforeseen project delays.
D) high overhead.
E) incentive contracts.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
29
As a project is crashed and project duration is reduced, direct costs typically

A) increase.
B) become unstable.
C) decrease.
D) become unreliable.
E) stay the same.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
30
Cost slope can be determined by dividing the

A) run by the rise.
B) rise by the run.
C) crash cost by the normal cost.
D) normal cost by the crash cost.
E) indirect cost by direct cost.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
31
Design flaws, equipment breakdown and adverse weather can create negative slack. These are examples of the need for reducing project duration on successive critical activities that was caused by

A) imposed project deadlines.
B) time to market.
C) unforeseen project delays.
D) high overhead.
E) incentive contracts.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
32
The accuracy of crash times and costs is frequently rough at best, when compared with normal time and cost.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
33
For most projects, the estimation of a crash time is relatively easy.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
34
An activity's crash cost includes ________ costs.

A) direct
B) indirect
C) overhead
D) total
E) normal
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
35
Making the decision to crash is the result of careful fiscal analysis and deep understanding of the project.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
36
In a Project Cost-Duration Graph, total project costs are a sum of

A) labor, material and equipment costs.
B) direct costs plus interest.
C) direct labor costs and the project manager's salary.
D) direct costs and the project manager's salary.
E) direct and indirect costs.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
37
The shortest possible time an activity can be completed realistically is called ___­­­_____ time.

A) expedited
B) accelerated
C) crash
D) optimistic
E) optimal
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
38
Insensitive networks are a rarity; Planning for a sensitive network is more practical.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
39
Intense global competition and rapid technological advances create pressure to develop projects rapidly. This is an example of reducing project duration caused by

A) imposed project deadlines.
B) time to market.
C) unforeseen project delays.
D) high overhead.
E) incentive contracts.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
40
A construction contractor finished a bridge across a river 12 months early and received more than $5 million for the early completion. This is an example of reducing project duration caused by

A) imposed project deadlines.
B) time to market.
C) unforeseen project delays.
D) high overhead.
E) incentive contracts.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
41
When it is necessary to reduce project duration and resources are constrained, which of the following is NOT a reasonable option?

A) Establish a core project team
B) Fast-tracking
C) Reduce project scope
D) Compromise quality
E) Use critical-chain project management
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
42
When reducing project duration, the duration for a project that is optimal is at the point where

A) direct costs are the lowest.
B) indirect costs are the lowest.
C) direct costs equal indirect costs.
D) total project costs are the lowest.
E) the project changes from time-constrained to resource-constrained.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
43
When determining which activity to crash, there are other factors that should be assessed beyond cost. Which of the following is NOT one of these factors?

A) The inherent risk associated with the activity
B) How crashing will impact the morale and motivation of the individuals working on that activity
C) Resource availability after crashing that activity
D) The level of difficulty involved in completing the activity
E) When during the project the activity will occur
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
44
Which of the following is NOT one of the more commonly used options for cutting project costs?

A) Reduce project scope
B) Have owner take more responsibility
C) Move the completion date further out
D) Brainstorm cost savings options
E) Outsource project activities
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
45
Which of the following is NOT a technique for accelerating project completion when resources are not constrained?

A) Assign additional staff and equipment
B) Establish a core team
C) Do it twice-fast and correctly
D) Reduce project scope
E) Compromise quality
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
46
Which of the following correctly calculates an activity's cost slope?

A) (normal cost - crash cost) / (normal time - crash time)
B) (crash cost - normal cost) / (normal time - crash time)
C) (normal time - crash time) / (crash cost - normal cost)
D) (normal time - crash time) / (normal cost - crash cost)
E) (crash cost - normal cost) / (crash time - normal time)
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
47
The relationship between the normal point and the crash point is assumed to be

A) linear.
B) curvilinear.
C) variable.
D) conversely related.
E) exponentially related.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
48
Sometimes very high __________ costs are recognized before a project begins and reducing these costs through shorter project durations becomes a high priority.

A) labor
B) direct
C) project
D) overhead
E) interest
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
49
Which of the following projects would be least benefited if additional resources were added?

A) Splitting and stacking a cord of wood
B) Developing new software
C) Harvesting a crop by hand
D) Building a cabin
E) Moving to a new house
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
50
When a project manager must reduce project duration but resources are constrained, creating a software program that will have less functionality than originally planned or building a house without the bonus room and the basement that the owner originally specified in the plans would both be examples of

A) fast-tracking.
B) use critical-chain project management.
C) reduce project scope.
D) compromise quality.
E) do it twice-fast and correctly.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
51
Which of the following is NOT a rational reason to reduce project duration?

A) Incentive contracts
B) High network sensitivity
C) Imposed deadlines
D) High overhead costs
E) Unforeseen delays
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
52
Reducing project duration

A) involves crashing all activities to their crash point.
B) can only be done when resources are not constrained.
C) is always more expensive.
D) tends to increase network sensitivity.
E) should be considered for all projects.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
53
In selecting the best activity to crash you would first select the activity with the

A) least steep slope.
B) earliest start time.
C) longest duration.
D) most steep slope.
E) largest crash time.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
54
One way of reducing project costs is identifying tasks that _________ can do themselves.

A) vendors
B) suppliers
C) customers
D) company employees
E) project teams
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
55
All of the following are disadvantages of scheduling overtime EXCEPT

A) overtime is associated with additional costs of coordination and communication.
B) sustained overtime work by salaried employees may incur burnout.
C) productivity is reduced the longer one is working.
D) more hours results in higher expenses if paying workers hourly.
E) continued overtime can lead to a higher turnover rate.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
56
When reducing project duration, the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known. After this, the critical path must be identified. What is the next step?

A) Find the activity with the lowest crash cost
B) Calculate the optimum cost-time point
C) Calculate the crash point
D) Calculate indirect cost per time unit
E) Find the activity with the steepest cost slope
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
57
According to Brooks' Law, adding more people to a late project is most likely to have which of the following impacts?

A) Keep the project from slipping any further
B) Get the project back on schedule
C) Make the project slip further
D) Lead to burnout
E) Decrease team motivation
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
58
An activity's normal time and cost are 10 and $120, respectively. Its estimated crash time and cost are 7 and $180, respectively. What is this activity's crash cost per time unit?

A) $20
B) $30
C) $40
D) $50
E) $60
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
59
Helen has just learned that she needs to reduce the duration of her project to meet an imposed deadline. She has calculated the crash cost per unit and knows the maximum units each activity can be reduced. What is the next step?

A) Find the activity with the lowest crash cost
B) Calculate the optimum cost-time point
C) Calculate the crash point
D) Identify the critical path
E) Find the activity with the highest crash cost
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
60
The less steep the cost slope of an activity, the

A) less it costs to shorten one time period.
B) more it costs to shorten one time period.
C) smaller the crash time is.
D) larger the crash time is.
E) cannot be determined by the information given.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
61
The direct cost for completing an activity as early as possible is called its ________ cost.

A) budgeted
B) time-limited
C) crash
D) minimal
E) early completion
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
62
An activity's ________ is calculated by dividing the rise by the run.

A) run rate
B) rise rate
C) rise / run rate
D) slope
E) daily cost
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
63
Costs such as labor, materials, equipment, or sub-contractors are examples of ________ project costs.

A) direct
B) budgeted
C) accumulated
D) indirect
E) time-phased
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
64
The ________ project cost is the sum of the indirect and direct costs.

A) accumulated
B) total
C) budgeted
D) time-phased
E) estimated
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
65
Overhead costs such as supervision, administration, consultants, and interest are examples of ________ project costs.

A) direct
B) budgeted
C) accumulated
D) indirect
E) time-phased
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
66
Which of the following is not likely to result in an imposed deadline?

A) Design flaws.
B) Marketing promises the product to the customer within three months.
C) The president announces availability of the product in one year.
D) The chief technology officer says, "finish the projects in six months or start packing."
E) Intense global competition.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
67
It is going to cost $120,000 a day simply to house and feed a construction crew in the farthest reaches of northern Alaska. This would be an example of a situation requiring reducing the project duration due to

A) imposed project deadlines.
B) time to market.
C) unforeseen project delays.
D) high overhead.
E) incentive contracts.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
68
When the project team is salaried, which of the following is the preferred choice for accelerating project completion?

A) Assign additional staff and equipment
B) Subcontract work
C) Schedule overtime
D) Outsource project work
E) Establish a core project team
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
69
An insensitive project network has the benefit of:

A) Not increasing risk as activities are initially crashed.
B) Having potential for real cost savings when crashed.
C) Having potential for significant time savings when crashed.
D) Having potential for flexible scheduling.
E) All of these alternatives are correct.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
70
Direct costs are assignable directly to a particular ________.

A) activity
B) resource
C) work package
D) task
E) milestone
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
71
Consider the following table of activities that describes a project network. Which activity will you crash first?

A) A
B) B
C) C
D) D
E) E
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
72
There are fewer options available for reducing project time if you are __________________ than if you can spend more than your original budget.

A) time-constrained
B) vision-limited
C) schedule-constrained
D) resource-constrained
E) physically-constrained
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
73
Consider the following table of activities that describes a project network. Which activity will you crash second?

A) A
B) B
C) C
D) D
E) E
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
74
In order to shorten the duration of a project the project manager should limit the choices of activities to just those that are on the __________.

A) shortest path
B) path with the greatest variability
C) critical path
D) path with the least amount of resources required
E) path with the most resources required
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
75
A project that has several near-critical or critical paths is said to be

A) elastic.
B) fully consumed.
C) inherently risky.
D) sensitive.
E) insensitive.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
76
When crashing a schedule, this may set in when a least-cost method is used.

A) Increased risk
B) Fatigue and resentment
C) Increased cost
D) Decrease in available management reserve
E) Reduced quality
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
77
Reducing the duration of an activity is called ________.

A) reduction
B) making smaller
C) crashing
D) re-assessment
E) acceleration
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
78
Because direct costs are assumed to be developed from normal methods and in a normal amount of time, any reduction in activity time should ________ the direct cost of the activity.

A) decrease
B) increase
C) reduce
D) expand
E) approximate
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
79
Compressing activities on a project with a sensitive project network will:

A) Increase risk of delaying the project.
B) Improve cost-time crashing success.
C) Reduce scheduling flexibility.
D) Increase risk of delaying the project and reduce scheduling flexibility.
E) Increase risk of delaying the project but improve cost-time crashing success.
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
80
The ________ time for an activity represents low-cost, realistic, efficient methods for completing the activity under typical conditions.

A) normal
B) crash
C) estimated
D) accelerated
E) completion
Unlock Deck
Unlock for access to all 106 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 106 flashcards in this deck.