Exam 9: Reducing Project Duration
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection101 Questions
Exam 3: Organization: Structure and Culture102 Questions
Exam 4: Defining the Project112 Questions
Exam 5: Estimating Project Times and Costs95 Questions
Exam 6: Developing a Project Schedule128 Questions
Exam 7: Managing Risk105 Questions
Exam 8: Scheduling Resources and Costs114 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager98 Questions
Exam 11: Managing Project Teams103 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations102 Questions
Exam 13: Progress and Performance Measurement and Evaluation98 Questions
Exam 14: Project Closure97 Questions
Exam 15: Agile Project Management94 Questions
Exam 16: International Projects103 Questions
Select questions type
The easiest way to add more labor to a project is not to add more people, but to schedule overtime. What are the disadvantages of scheduling overtime?
Free
(Essay)
4.7/5
(35)
Correct Answer:
First, hourly workers are typically paid at least time and a half for overtime, increasing project costs. Sustained overtime work by salaried employees may incur intangible costs such as divorce, burnout, and turnover. It is also an oversimplification to assume that, over an extended period of time, a person is as productive during his or her eleventh hour at work as during his or her third hour of work.
An activity's normal time and cost are 12 and $150, respectively. Its estimated crash time and cost are 9 and $300, respectively. This activity's crash cost per time unit is ________.
Free
(Multiple Choice)
4.9/5
(35)
Correct Answer:
A
An activity's ________ is calculated by dividing the rise by the run.
Free
(Multiple Choice)
4.8/5
(38)
Correct Answer:
D
In selecting the best activity to crash you would first select the activity with the
(Multiple Choice)
4.8/5
(38)
A project that has several near-critical or critical paths is said to be
(Multiple Choice)
4.7/5
(37)
Because direct costs are assumed to be developed from normal methods and in a normal amount of time, any reduction in activity time should ________ the direct cost of the activity.
(Multiple Choice)
4.8/5
(38)
Helen has just learned that she needs to reduce the duration of her project to meet an imposed deadline. She has calculated the crash cost per unit and knows the maximum units each activity can be reduced. What is the next step?
(Multiple Choice)
4.8/5
(40)
Sometimes very high __________ costs are recognized before a project begins and reducing these costs through shorter project durations becomes a high priority.
(Multiple Choice)
4.9/5
(42)
Consider the following table of activities that describes a project network. What is the first activity you would crash?
(Multiple Choice)
4.7/5
(36)
Insensitive networks are a rarity; Planning for a sensitive network is more practical.
(True/False)
4.7/5
(17)
Consider the following table of activities that describes a project network. Is this network sensitive? Suppose indirect costs are $550 / day. For how many days could you crash this network and still be saving money because crash costs / day are less than the indirect costs / day that would be saved?
(Multiple Choice)
4.8/5
(35)
An activity must be crashed on each critical path in order to reduce project duration.
(True/False)
4.8/5
(39)
Consider the following table of activities that describes a project network. Without causing the critical path to become noncritical or otherwise wasting money, what would be the second activity you would crash and how many days can you crash it?
(Multiple Choice)
4.9/5
(32)
Compressing activities on a project with a sensitive project network will:
(Multiple Choice)
4.8/5
(30)
Which of the following is NOT one of the more commonly used options for cutting project costs?
(Multiple Choice)
4.9/5
(30)
Consider the following table of activities that describes a project network. Without causing the critical path to become noncritical or otherwise wasting money, by how many days max could you crash this project? Assume you can crash only one activity at a time and that crashing is necessary regardless of cost. You do not want to crash the critical path(s) beyond the point where it (they) is no longer critical as this will not reduce project duration.
(Multiple Choice)
4.9/5
(37)
What does it mean to say that a project network is sensitive and why is that important to a project manager who needs to reduce the duration of his or her project?
(Essay)
4.9/5
(38)
Incentive contracts can make the reduction of project time rewarding-usually for both the project contractor and owner.
(True/False)
4.9/5
(27)
Total cost for specific project durations is computed and then compared with the benefits of reducing project time, before the project begins or while it is in progress.
(True/False)
4.9/5
(30)
Showing 1 - 20 of 106
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)