Deck 5: Scheduling the Project

Full screen (f)
exit full mode
Question
Another name for total slack is free slack.
Use Space or
up arrow
down arrow
to flip the card.
Question
Critical path tasks always have zero slack.
Question
AON and AOA networks can both be used to depict any project network.
Question
Networks are usually drawn with a "Start" node to the right and a "Finish" node to the left.
Question
The difference between EST and LFT is called slack.
Question
The difference between LFT and EFT is called slack.
Question
An event is a series of connected activities.
Question
A big advantage of AON networks is that they are easier to draw.
Question
There is more than one way to compute slack.
Question
When it was originally developed, PERT used certain (deterministic) methods to estimate activity duration.
Question
The difference between LST and LFT is called slack.
Question
The shortest time to complete a network is equal to the duration of the longest path through the network.
Question
A diagram of nodes connected by directional arcs that defines the project and illustrates the technical of all activities is referred to as a network.
Question
The difference between LFT and EFT is called free slack.
Question
Milestones are not depended upon the predecessor activities in the project plan.
Question
The difference between the LST and EST is called free slack.
Question
The difference between the LST and EST is called slack.
Question
Critical path tasks always have zero free slack.
Question
Standard Pert/CPM networks can be used to resolve probabilistic concerns.
Question
To manage a project successfully, the project manager need only pay close attention to tasks on the critical path.
Question
Float refers to the amount of time a noncritical task can be delayed without causing a delay in the entire project.
Question
All project-related statistical calculations are performed using the normal distribution.
Question
If task duration estimates are carefully made, the project manager needs to only examine the critical path when conducting a risk analysis.
Question
Milestones in a project consume no resources or time.
Question
The formula for the expected time of an activity in a network assumes that the optimistic, pessimistic, and most likely time estimates have a normal distribution.
Question
The amount of time an activity can be delayed without affecting the start time of any successor activity is known as free slack.
Question
A situation where two or more activities have the same starting and finishing nodes or where a single activity connects to two or more nodes is called a dummy task.
Question
Any activity in a project not on the critical path can be delayed without delaying the project.
Question
When calculating the variance of an activity, the formula is σ2=b-a26 is the correct formula no matter what probability is used to estimate b and
a.
Question
An activity using slack does not impact any other activity.
Question
"Merger" is a term used to describe the situation in which two or more paths in a network join together.
Question
When conducting risk analysis on a project, we always know which path will be the critical path.
Question
The tasks of project planning, project budgeting, and project scheduling are largely separable from one another.
Question
A project schedule is a project action plan converted into a timetable.
Question
The formula for the expected time of an activity in a network assumes that the optimistic, pessimistic, and most likely time estimates have a beta distribution.
Question
Events in a project consume no resources or time.
Question
A situation where two or more activities have the same starting and finishing nodes or where a single activity connects to two or more nodes is called a milestone.
Question
The movement from left to right through the network beginning with the start node that calculates the LS and LF for each activity is known as "forward pass".
Question
A disadvantage of using beta distribution to approximate activity times is that it is generally less flexible than the normal distribution.
Question
Activities on a project always meet the assumption of statistical independence.
Question
The start-to-finish linkage is used in situations where is it desirable for two or more activities to finish at the same time.
Question
Anyone interested in the project can read a Gantt chart with little or no training and with little or no technical knowledge of the project.
Question
Milestones cannot be identified on a Gantt chart.
Question
The simulation approach is generally preferred over the statistical method.
Question
The critical path always has the largest variance.
Question
It is easiest to see lead and lag time in a project task on a PERT/CPM networks.
Question
Scum takes a more just-in-time (JIT) approach to project planning whereby planning is done as late as possible and when the most is known about the project.
Question
The cost to complete an activity is always known in advance.
Question
Technical dependencies are generally easier to see on a Gantt chart than on PERT/CPM networks.
Question
The actual project duration will be known with certainty after the project is completed.
Question
The cost to complete a project is driven in large part by the time required to complete the project.
Question
When two or more paths through a network join, even at the end of the network, paths that have little slack and/or high variance may become critical simply by chance.
Question
A Gantt chart cannot depict a critical path, only a PERT/CPM chart can.
Question
A disadvantage of Gantt charts is that they are hard to draw.
Question
Gantt charts were developed in the early twentieth century.
Question
Technical dependencies are often harder to see on a Gantt chart than on a PERT/CPM network.
Question
A start-to-finish linkage is the most common way of linking to successive task.
Question
Gantt charts are not adequate replacements for networks.
Question
Henry Gantt developed the Gantt chart.
Question
The actual project duration will be known with certainty after the project is fully planned.
Question
Ben is part of a new project in his company. He is asked to complete a task within two days, but he is only able to finish it in three days. Since the task assigned to him is noncritical in nature, the extra day taken by Ben does not cause a delay in the project. In this scenario, the additional day taken by Ben is known as _____.

A) flow time
B) throughput
C) slack
D) critical time
E) flowgrind
Question
High velocity is a goal of Agile scheduling.
Question
Paul, the marketing manager of a food company, created a diagram of nodes to represent the marketing process for a new product of the company. Each node represented an activity in the marketing process, and an arc joined each node. He used this diagram to demonstrate the objectives of the marketing process. In the context of the language of the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM), the diagram used by Paul is known as a _____.

A) network
B) flowchart
C) Gantt chart
D) Smith chart
E) control chart
Question
With scum, a prerequisite to being able to realistically determine the amount of work that can be completed in a sprint is having accurate estimates for the amount of effort required to complete each requirement.
Question
Consider a project network that begins with activity A and is followed by activity B. Activity A takes 6 days to finish. If the earliest start time for activity B is 6 days and the latest start time for it is 10 days, activity B has a slack of _____.

A) 16 days
B) 4 days
C) 10 days
D) 2 days
E) 12 days
Question
Organ Bennett Inc., a public relations firm, is working on a project to improve the brand image of Sizil, a client firm, over a period of a year. The project requires Organ Bennett to organize a press conference to announce the launch of Sizil's new product. The project members need to invite reporters for the same. In the context of the language of the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM), inviting reporters is most likely a(n) _____.

A) event
B) activity
C) network
D) milestone
E) float
Question
Miros Inc., a recording studio, displays its recording process by using a network of nodes and arrows. The nodes are used to depict the activities involved in recording a song, such as setting up the instruments, and the arrows are used to depict the order of precedence of the activities. Which of the following project networks is Miros using in the given scenario?

A) A time-on-node network
B) An activity-on-arrow network
C) A time-on-arrow network
D) An activity-on-node network
E) An event-on-node network
Question
PERT was originally used for what type of project?

A) construction
B) R & D
C) military
D) computer software development
E) advertising
Question
Slack is calculated as?

A) LFT - EST
B) LFT - LST
C) LST - LFT
D) LFT - EFT
E) EFT - EST
Question
Which of the following terms is most closely associated with a task required by the project?

A) activity
B) event
C) milestone
D) network
E) path
Question
An Agile team's velocity is only valid as long as the sprint duration remains constant.
Question
The amount of time a noncritical task can be delayed without delaying the project is called?

A) surplus
B) flop
C) slack
D) critical time
E) safety
Question
An identifiable state resulting from the completion of one or more activities is called?

A) an event
B) an activity
C) a milestone
D) a path
E) the critical path
Question
The scum master develops estimates for the effort required to complete each product requirement listed in the product backlog.
Question
Agile velocity is not impacted by the team size.
Question
Nessage Mique, a niche fashion boutique, displays its production process by using a network of nodes and arrows. The nodes are used to depict the state of completion of various activities and the arrows are used to depict their order of precedence. Which of the following project networks is Nessage Mique using in the given scenario?

A) An event-on-arrow network
B) A time-on-arrow network
C) An activity-on-node network
D) A time-on-node network
E) An activity-on-arrow network
Question
A Term not used in the discussion of PERT/CPM analysis is

A) Activity
B) Events
C) Critical Path
D) Sensitivity path
E) network s
Question
Verita Nist, an automobile company, sought to improve the production time and quality of its products within a year. In the first month, the company installed five new assembling machines. This reduced the production time by 15 percent. In the context of the language of the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM), this decrease in the production time of Verita Nist's products is an example of a(n) _____.

A) task
B) activity
C) critical path
D) event
E) throughput
Question
Consider a project network that begins with activity X and is followed by activity Y. The earliest start time for activity X is 5 days and it will take 3 days to be completed. The earliest start time for activity Y is 12 days. Given this information, activity X has _____ of free slack.

A) 20 days
B) 4 days
C) 12 days
D) 9 days
E) 15 days
Question
Minkset Blu, a textile company, wants to improve its sales over a span of four years. In the first year, the company installs new looming machines that improve the production cost. However, it takes two years for the company to establish a liaison with online retailers to improve the accessibility of its products. This delays the company's goal of improving sales by a year. In the context of the language of the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM), the set of activities that cause the delay are part of _____.

A) the Smith chart
B) the Portolan chart
C) the critical path
D) the throughput process
E) the control chart
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/109
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 5: Scheduling the Project
1
Another name for total slack is free slack.
False
2
Critical path tasks always have zero slack.
True
3
AON and AOA networks can both be used to depict any project network.
True
4
Networks are usually drawn with a "Start" node to the right and a "Finish" node to the left.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
5
The difference between EST and LFT is called slack.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
6
The difference between LFT and EFT is called slack.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
7
An event is a series of connected activities.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
8
A big advantage of AON networks is that they are easier to draw.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
9
There is more than one way to compute slack.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
10
When it was originally developed, PERT used certain (deterministic) methods to estimate activity duration.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
11
The difference between LST and LFT is called slack.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
12
The shortest time to complete a network is equal to the duration of the longest path through the network.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
13
A diagram of nodes connected by directional arcs that defines the project and illustrates the technical of all activities is referred to as a network.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
14
The difference between LFT and EFT is called free slack.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
15
Milestones are not depended upon the predecessor activities in the project plan.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
16
The difference between the LST and EST is called free slack.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
17
The difference between the LST and EST is called slack.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
18
Critical path tasks always have zero free slack.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
19
Standard Pert/CPM networks can be used to resolve probabilistic concerns.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
20
To manage a project successfully, the project manager need only pay close attention to tasks on the critical path.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
21
Float refers to the amount of time a noncritical task can be delayed without causing a delay in the entire project.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
22
All project-related statistical calculations are performed using the normal distribution.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
23
If task duration estimates are carefully made, the project manager needs to only examine the critical path when conducting a risk analysis.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
24
Milestones in a project consume no resources or time.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
25
The formula for the expected time of an activity in a network assumes that the optimistic, pessimistic, and most likely time estimates have a normal distribution.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
26
The amount of time an activity can be delayed without affecting the start time of any successor activity is known as free slack.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
27
A situation where two or more activities have the same starting and finishing nodes or where a single activity connects to two or more nodes is called a dummy task.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
28
Any activity in a project not on the critical path can be delayed without delaying the project.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
29
When calculating the variance of an activity, the formula is σ2=b-a26 is the correct formula no matter what probability is used to estimate b and
a.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
30
An activity using slack does not impact any other activity.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
31
"Merger" is a term used to describe the situation in which two or more paths in a network join together.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
32
When conducting risk analysis on a project, we always know which path will be the critical path.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
33
The tasks of project planning, project budgeting, and project scheduling are largely separable from one another.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
34
A project schedule is a project action plan converted into a timetable.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
35
The formula for the expected time of an activity in a network assumes that the optimistic, pessimistic, and most likely time estimates have a beta distribution.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
36
Events in a project consume no resources or time.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
37
A situation where two or more activities have the same starting and finishing nodes or where a single activity connects to two or more nodes is called a milestone.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
38
The movement from left to right through the network beginning with the start node that calculates the LS and LF for each activity is known as "forward pass".
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
39
A disadvantage of using beta distribution to approximate activity times is that it is generally less flexible than the normal distribution.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
40
Activities on a project always meet the assumption of statistical independence.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
41
The start-to-finish linkage is used in situations where is it desirable for two or more activities to finish at the same time.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
42
Anyone interested in the project can read a Gantt chart with little or no training and with little or no technical knowledge of the project.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
43
Milestones cannot be identified on a Gantt chart.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
44
The simulation approach is generally preferred over the statistical method.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
45
The critical path always has the largest variance.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
46
It is easiest to see lead and lag time in a project task on a PERT/CPM networks.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
47
Scum takes a more just-in-time (JIT) approach to project planning whereby planning is done as late as possible and when the most is known about the project.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
48
The cost to complete an activity is always known in advance.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
49
Technical dependencies are generally easier to see on a Gantt chart than on PERT/CPM networks.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
50
The actual project duration will be known with certainty after the project is completed.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
51
The cost to complete a project is driven in large part by the time required to complete the project.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
52
When two or more paths through a network join, even at the end of the network, paths that have little slack and/or high variance may become critical simply by chance.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
53
A Gantt chart cannot depict a critical path, only a PERT/CPM chart can.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
54
A disadvantage of Gantt charts is that they are hard to draw.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
55
Gantt charts were developed in the early twentieth century.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
56
Technical dependencies are often harder to see on a Gantt chart than on a PERT/CPM network.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
57
A start-to-finish linkage is the most common way of linking to successive task.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
58
Gantt charts are not adequate replacements for networks.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
59
Henry Gantt developed the Gantt chart.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
60
The actual project duration will be known with certainty after the project is fully planned.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
61
Ben is part of a new project in his company. He is asked to complete a task within two days, but he is only able to finish it in three days. Since the task assigned to him is noncritical in nature, the extra day taken by Ben does not cause a delay in the project. In this scenario, the additional day taken by Ben is known as _____.

A) flow time
B) throughput
C) slack
D) critical time
E) flowgrind
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
62
High velocity is a goal of Agile scheduling.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
63
Paul, the marketing manager of a food company, created a diagram of nodes to represent the marketing process for a new product of the company. Each node represented an activity in the marketing process, and an arc joined each node. He used this diagram to demonstrate the objectives of the marketing process. In the context of the language of the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM), the diagram used by Paul is known as a _____.

A) network
B) flowchart
C) Gantt chart
D) Smith chart
E) control chart
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
64
With scum, a prerequisite to being able to realistically determine the amount of work that can be completed in a sprint is having accurate estimates for the amount of effort required to complete each requirement.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
65
Consider a project network that begins with activity A and is followed by activity B. Activity A takes 6 days to finish. If the earliest start time for activity B is 6 days and the latest start time for it is 10 days, activity B has a slack of _____.

A) 16 days
B) 4 days
C) 10 days
D) 2 days
E) 12 days
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
66
Organ Bennett Inc., a public relations firm, is working on a project to improve the brand image of Sizil, a client firm, over a period of a year. The project requires Organ Bennett to organize a press conference to announce the launch of Sizil's new product. The project members need to invite reporters for the same. In the context of the language of the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM), inviting reporters is most likely a(n) _____.

A) event
B) activity
C) network
D) milestone
E) float
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
67
Miros Inc., a recording studio, displays its recording process by using a network of nodes and arrows. The nodes are used to depict the activities involved in recording a song, such as setting up the instruments, and the arrows are used to depict the order of precedence of the activities. Which of the following project networks is Miros using in the given scenario?

A) A time-on-node network
B) An activity-on-arrow network
C) A time-on-arrow network
D) An activity-on-node network
E) An event-on-node network
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
68
PERT was originally used for what type of project?

A) construction
B) R & D
C) military
D) computer software development
E) advertising
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
69
Slack is calculated as?

A) LFT - EST
B) LFT - LST
C) LST - LFT
D) LFT - EFT
E) EFT - EST
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
70
Which of the following terms is most closely associated with a task required by the project?

A) activity
B) event
C) milestone
D) network
E) path
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
71
An Agile team's velocity is only valid as long as the sprint duration remains constant.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
72
The amount of time a noncritical task can be delayed without delaying the project is called?

A) surplus
B) flop
C) slack
D) critical time
E) safety
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
73
An identifiable state resulting from the completion of one or more activities is called?

A) an event
B) an activity
C) a milestone
D) a path
E) the critical path
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
74
The scum master develops estimates for the effort required to complete each product requirement listed in the product backlog.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
75
Agile velocity is not impacted by the team size.
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
76
Nessage Mique, a niche fashion boutique, displays its production process by using a network of nodes and arrows. The nodes are used to depict the state of completion of various activities and the arrows are used to depict their order of precedence. Which of the following project networks is Nessage Mique using in the given scenario?

A) An event-on-arrow network
B) A time-on-arrow network
C) An activity-on-node network
D) A time-on-node network
E) An activity-on-arrow network
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
77
A Term not used in the discussion of PERT/CPM analysis is

A) Activity
B) Events
C) Critical Path
D) Sensitivity path
E) network s
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
78
Verita Nist, an automobile company, sought to improve the production time and quality of its products within a year. In the first month, the company installed five new assembling machines. This reduced the production time by 15 percent. In the context of the language of the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM), this decrease in the production time of Verita Nist's products is an example of a(n) _____.

A) task
B) activity
C) critical path
D) event
E) throughput
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
79
Consider a project network that begins with activity X and is followed by activity Y. The earliest start time for activity X is 5 days and it will take 3 days to be completed. The earliest start time for activity Y is 12 days. Given this information, activity X has _____ of free slack.

A) 20 days
B) 4 days
C) 12 days
D) 9 days
E) 15 days
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
80
Minkset Blu, a textile company, wants to improve its sales over a span of four years. In the first year, the company installs new looming machines that improve the production cost. However, it takes two years for the company to establish a liaison with online retailers to improve the accessibility of its products. This delays the company's goal of improving sales by a year. In the context of the language of the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM), the set of activities that cause the delay are part of _____.

A) the Smith chart
B) the Portolan chart
C) the critical path
D) the throughput process
E) the control chart
Unlock Deck
Unlock for access to all 109 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 109 flashcards in this deck.