Deck 11: Project Risk Management

Full screen (f)
exit full mode
Question
Which of the following is the first step in managing risks (circle one):

A) Include in the budget funds to cover the risks.
B) Identify ways to reduce the risks.
C) Identify the risks.
D) Prepare a contingency plan for every project activity.
Use Space or
up arrow
down arrow
to flip the card.
Question
If the risk likelihood is 0.4, the risk impact is 6.0, the risk consequence is (circle one):

A) 6.6
B) 4
C) 2.4
D) None of these
Question
Suppose task B follows task A. The likelihood that a problem will occur with task A is 0.5, and the time to correct the problem would be 2 months. The likelihood that a problem will occur with task B is 0.2, and the time to correct the problem would be 3 months. The risk consequence of both activities combined is (circle one):

A) 3.5 months
B) 5.7 months
C) 1.6 months
D) cannot be determined
Question
The concept of project risk is a joint function of (circle all that apply):

A) The longest sequence of activities in the project network.
B) The likelihood that a problematical event will occur.
C) The time a contractor is allowed to respond to the RFP.
D) The impact of the problematical event, if it does occur.
Question
Which of the following are sources of internal risks in projects (circle all that apply):

A) The uniqueness of the project.
B) The experience of the project team.
C) Poorly defined customer needs.
D) The level of control exerted by customers and subcontractors over project work
E) The complexity of the end item.
Question
Which of the following are common techniques for pinpointing risks in projects (circle all that apply):

A) SOW.
B) Work breakdown structure.
C) Responsibility matrix.
D) Process flowcharts.
E) Documents from prior projects.
Question
Risk checklists (circle all that apply):

A) List the factors identified as risks based on experience and common sense.
B) Can be purchased from textbook publishers.
C) Are updated as experience grows.
D) Incorporate the judgement of experienced team members.
Question
A cause and effect diagram is ordinarily used to identify (circle all that apply):

A) Potential sources (hazards) for a given risk.
B) A potential risk that might result from a number of hazards.
C) The probability that a risk will occur.
Question
Risk likelihood is (circle all that apply):

A) The probability that a risk will occur.
B) Expressed numerically between 0 and 1.0.
C) Of all possible consequences, the percentage that are undesirable.
D) Most often based upon opinions and past experience.
Question
When applying a design margin, the target value (circle all that apply):

A) equals the requirement value +/- a safety or buffer amount.
B) is stiffer than the requirement value.
C) is set such that it will be much easier to achieve the requirement value.
D) can be "relaxed" by some amount, and still enable the requirement value to be met.
E) is the same as the requirement value.
Question
A system prototype is (circle all that apply):

A) A complete working system that has all of the functional capabilities of the project end-item system.
B) A special font used in project documents.
C) Used for testing and verifying the design of the end-item system.
D) A software package for project planning and budgeting.
E) The final, completed version of the end-item system.
Question
Risk management includes (circle all that apply):

A) Setting procedures for accurate, complete project documentation.
B) Establishing good communication so the project manager is kept informed of emerging problems.
C) Establishing reward systems so workers are well paid and motivated.
D) Establishing procedures to continuously monitor risks and updating the risk plan.
E) Setting penalties to ensure that things don't go wrong.
Question
Circle all that are true:

A) the MAXIMAX decision criterion leads to selecting the strategy that would maximize the outcome, assuming the best conditions will prevail.
B) the MAXIMIN decision criterion leads to selecting the strategy that would maximize the outcome, assuming the worst conditions prevail.
C) the MINIMAX decision criterion leads to selecting the strategy that would minimize the regret of not having selected the best strategy.
D) the MAXIMUM EXPECTED PAYOFF decision criterion leads to selecting the strategy that would maximize the outcome, assuming all conditions have equal likelihood.
Question
Suppose the impact of a risk is judged to be serious, but the likelihood of it happening is judged to be very small; (circle all that apply):

A) If the computed expected value consequence is small, the risk can be ignored.
B) The risk should be taken seriously.
C) If the computed expected value consequence is lower than others in the project, it should be addressed only if time and funds allow.
D) A different opinion should be sought that would yield a reduced or not severe impact.
Question
Statement: A project is considered risky only if the likelihood of a very serious event occurring is high.
Question
Statement: An "acceptable level of risk" in a project is a matter of judgement.
Question
Statement: The analogy technique for identifying risks works best when there is a documented history of previous, similar projects to review.
Question
Statement: A risk symptom is a visible, physical sign that a risk is starting to materialize.
Question
Statement: A risk in which the expected value consequence is small should be ignored.
Question
Statement: The principle of risk transfer uses contractual incentives or penalties to shift the risk from one party to another.
Question
Statement: In virtually all projects, both the contractor and the customer are exposed to some form or level of risk, regardless of planning or contractual agreements.
Question
Statement: In development projects, attempts to avoid risk will tend to increase the opportunities and payoff.
Question
Statement: Projects in which activities are intricately interconnected are inherently less risky than projects wherein activities are independent.
Question
Statement: To develop a contingency plan, it is best to wait until a problem develops, then create the plan that best addresses it.
Question
Statement: Not every project requires a comprehensive risk analysis and risk management plan.
Question
Statement: In general, a larger variance in the estimated duration time or cost for an activity represents greater risk for that activity.
Question
Transferring of risk is one of five ways to deal with risk in projects. List THREE others:
Question
Match each of the following definition with the correct terms:

-____ A buffer resource for dealing with a risk if it occurs.

A) risk profile
B) risk officer
C) risk reserve
D) risk management plan
Question
Match each of the following definition with the correct terms:

-____ Specifies ways to identify and deal with project risks.

A) risk profile
B) risk officer
C) risk reserve
D) risk management plan
Question
Match each of the following definition with the correct terms:

-____ Specifies the likelihood, impact, and consequence of each risk.

A) risk profile
B) risk officer
C) risk reserve
D) risk management plan
Question
Match each of the following definition with the correct terms:

-____ Oversees identification, assessment, and tracking of all reasons why something might go wrong.

A) risk profile
B) risk officer
C) risk reserve
D) risk management plan
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/31
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 11: Project Risk Management
1
Which of the following is the first step in managing risks (circle one):

A) Include in the budget funds to cover the risks.
B) Identify ways to reduce the risks.
C) Identify the risks.
D) Prepare a contingency plan for every project activity.
Identify the risks.
2
If the risk likelihood is 0.4, the risk impact is 6.0, the risk consequence is (circle one):

A) 6.6
B) 4
C) 2.4
D) None of these
2.4
3
Suppose task B follows task A. The likelihood that a problem will occur with task A is 0.5, and the time to correct the problem would be 2 months. The likelihood that a problem will occur with task B is 0.2, and the time to correct the problem would be 3 months. The risk consequence of both activities combined is (circle one):

A) 3.5 months
B) 5.7 months
C) 1.6 months
D) cannot be determined
1.6 months
4
The concept of project risk is a joint function of (circle all that apply):

A) The longest sequence of activities in the project network.
B) The likelihood that a problematical event will occur.
C) The time a contractor is allowed to respond to the RFP.
D) The impact of the problematical event, if it does occur.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
5
Which of the following are sources of internal risks in projects (circle all that apply):

A) The uniqueness of the project.
B) The experience of the project team.
C) Poorly defined customer needs.
D) The level of control exerted by customers and subcontractors over project work
E) The complexity of the end item.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
6
Which of the following are common techniques for pinpointing risks in projects (circle all that apply):

A) SOW.
B) Work breakdown structure.
C) Responsibility matrix.
D) Process flowcharts.
E) Documents from prior projects.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
7
Risk checklists (circle all that apply):

A) List the factors identified as risks based on experience and common sense.
B) Can be purchased from textbook publishers.
C) Are updated as experience grows.
D) Incorporate the judgement of experienced team members.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
8
A cause and effect diagram is ordinarily used to identify (circle all that apply):

A) Potential sources (hazards) for a given risk.
B) A potential risk that might result from a number of hazards.
C) The probability that a risk will occur.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
9
Risk likelihood is (circle all that apply):

A) The probability that a risk will occur.
B) Expressed numerically between 0 and 1.0.
C) Of all possible consequences, the percentage that are undesirable.
D) Most often based upon opinions and past experience.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
10
When applying a design margin, the target value (circle all that apply):

A) equals the requirement value +/- a safety or buffer amount.
B) is stiffer than the requirement value.
C) is set such that it will be much easier to achieve the requirement value.
D) can be "relaxed" by some amount, and still enable the requirement value to be met.
E) is the same as the requirement value.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
11
A system prototype is (circle all that apply):

A) A complete working system that has all of the functional capabilities of the project end-item system.
B) A special font used in project documents.
C) Used for testing and verifying the design of the end-item system.
D) A software package for project planning and budgeting.
E) The final, completed version of the end-item system.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
12
Risk management includes (circle all that apply):

A) Setting procedures for accurate, complete project documentation.
B) Establishing good communication so the project manager is kept informed of emerging problems.
C) Establishing reward systems so workers are well paid and motivated.
D) Establishing procedures to continuously monitor risks and updating the risk plan.
E) Setting penalties to ensure that things don't go wrong.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
13
Circle all that are true:

A) the MAXIMAX decision criterion leads to selecting the strategy that would maximize the outcome, assuming the best conditions will prevail.
B) the MAXIMIN decision criterion leads to selecting the strategy that would maximize the outcome, assuming the worst conditions prevail.
C) the MINIMAX decision criterion leads to selecting the strategy that would minimize the regret of not having selected the best strategy.
D) the MAXIMUM EXPECTED PAYOFF decision criterion leads to selecting the strategy that would maximize the outcome, assuming all conditions have equal likelihood.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
14
Suppose the impact of a risk is judged to be serious, but the likelihood of it happening is judged to be very small; (circle all that apply):

A) If the computed expected value consequence is small, the risk can be ignored.
B) The risk should be taken seriously.
C) If the computed expected value consequence is lower than others in the project, it should be addressed only if time and funds allow.
D) A different opinion should be sought that would yield a reduced or not severe impact.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
15
Statement: A project is considered risky only if the likelihood of a very serious event occurring is high.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
16
Statement: An "acceptable level of risk" in a project is a matter of judgement.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
17
Statement: The analogy technique for identifying risks works best when there is a documented history of previous, similar projects to review.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
18
Statement: A risk symptom is a visible, physical sign that a risk is starting to materialize.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
19
Statement: A risk in which the expected value consequence is small should be ignored.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
20
Statement: The principle of risk transfer uses contractual incentives or penalties to shift the risk from one party to another.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
21
Statement: In virtually all projects, both the contractor and the customer are exposed to some form or level of risk, regardless of planning or contractual agreements.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
22
Statement: In development projects, attempts to avoid risk will tend to increase the opportunities and payoff.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
23
Statement: Projects in which activities are intricately interconnected are inherently less risky than projects wherein activities are independent.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
24
Statement: To develop a contingency plan, it is best to wait until a problem develops, then create the plan that best addresses it.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
25
Statement: Not every project requires a comprehensive risk analysis and risk management plan.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
26
Statement: In general, a larger variance in the estimated duration time or cost for an activity represents greater risk for that activity.
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
27
Transferring of risk is one of five ways to deal with risk in projects. List THREE others:
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
28
Match each of the following definition with the correct terms:

-____ A buffer resource for dealing with a risk if it occurs.

A) risk profile
B) risk officer
C) risk reserve
D) risk management plan
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
29
Match each of the following definition with the correct terms:

-____ Specifies ways to identify and deal with project risks.

A) risk profile
B) risk officer
C) risk reserve
D) risk management plan
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
30
Match each of the following definition with the correct terms:

-____ Specifies the likelihood, impact, and consequence of each risk.

A) risk profile
B) risk officer
C) risk reserve
D) risk management plan
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
31
Match each of the following definition with the correct terms:

-____ Oversees identification, assessment, and tracking of all reasons why something might go wrong.

A) risk profile
B) risk officer
C) risk reserve
D) risk management plan
Unlock Deck
Unlock for access to all 31 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 31 flashcards in this deck.