Exam 11: Project Risk Management
Exam 1: What Is Project Management12 Questions
Exam 2: Systems Approach28 Questions
Exam 3: Project Life Cycle and Project Conception32 Questions
Exam 4: Project Definition and System Definition42 Questions
Exam 5: Project Execution and Closeout32 Questions
Exam 6: Basic Project Planning Techniques32 Questions
Exam 7: Project Schedule Planning and Networks26 Questions
Exam 8: Advanced Project Network Analysis and Scheduling29 Questions
Exam 9: Cost Estimating and Budgeting29 Questions
Exam 10: Project Quality Management11 Questions
Exam 11: Project Risk Management31 Questions
Exam 12: Project Procurement Management and Contracting36 Questions
Exam 13: Project Monitoring and Control41 Questions
Exam 14: Agile Project Management and Lean27 Questions
Exam 15: Project Organizational Structure and Integration22 Questions
Exam 16: Project Roles and Stakeholders22 Questions
Exam 17: Leadership, Teamwork, and Conflict30 Questions
Exam 18: Meta-Management of Projects and Program Management38 Questions
Exam 19: Project Selection and Portfolio Management40 Questions
Exam 20: International Project Management45 Questions
Select questions type
Statement: The principle of risk transfer uses contractual incentives or penalties to shift the risk from one party to another.
Free
(True/False)
4.9/5
(35)
Correct Answer:
True
Statement: Not every project requires a comprehensive risk analysis and risk management plan.
Free
(True/False)
4.7/5
(29)
Correct Answer:
True
Statement: In general, a larger variance in the estimated duration time or cost for an activity represents greater risk for that activity.
(True/False)
4.8/5
(30)
Match each of the following definition with the correct terms:
-____ A buffer resource for dealing with a risk if it occurs.
(Multiple Choice)
4.8/5
(35)
If the risk likelihood is 0.4, the risk impact is 6.0, the risk consequence is (circle one):
(Multiple Choice)
4.9/5
(31)
Statement: In development projects, attempts to avoid risk will tend to increase the opportunities and payoff.
(True/False)
4.8/5
(41)
Transferring of risk is one of five ways to deal with risk in projects. List THREE others:
(Short Answer)
4.9/5
(36)
Suppose task B follows task A. The likelihood that a problem will occur with task A is 0.5, and the time to correct the problem would be 2 months. The likelihood that a problem will occur with task B is 0.2, and the time to correct the problem would be 3 months. The risk consequence of both activities combined is (circle one):
(Multiple Choice)
4.7/5
(36)
Statement: An "acceptable level of risk" in a project is a matter of judgement.
(True/False)
4.9/5
(31)
Match each of the following definition with the correct terms:
-____ Specifies ways to identify and deal with project risks.
(Multiple Choice)
5.0/5
(28)
Statement: To develop a contingency plan, it is best to wait until a problem develops, then create the plan that best addresses it.
(True/False)
4.8/5
(32)
Match each of the following definition with the correct terms:
-____ Specifies the likelihood, impact, and consequence of each risk.
(Multiple Choice)
5.0/5
(32)
Which of the following are common techniques for pinpointing risks in projects (circle all that apply):
(Multiple Choice)
4.8/5
(21)
A cause and effect diagram is ordinarily used to identify (circle all that apply):
(Multiple Choice)
4.9/5
(38)
Statement: The analogy technique for identifying risks works best when there is a documented history of previous, similar projects to review.
(True/False)
4.9/5
(34)
Which of the following is the first step in managing risks (circle one):
(Multiple Choice)
4.9/5
(34)
Statement: Projects in which activities are intricately interconnected are inherently less risky than projects wherein activities are independent.
(True/False)
4.9/5
(34)
Showing 1 - 20 of 31
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)