Deck 4: Linear Programming and Project Management
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/18
Play
Full screen (f)
Deck 4: Linear Programming and Project Management
1
The solution space of a LP problem is unbounded due to
A) An incorrect formulation of the LP model
B) Objective function is unbounded
C) Neither (a) nor (b)
D) Both (a) and (b)
A) An incorrect formulation of the LP model
B) Objective function is unbounded
C) Neither (a) nor (b)
D) Both (a) and (b)
Neither (a) nor (b)
2
While solving LP problem graphically, the area bounded by the constraints is called
A) Feasible region
B) Infeasible region
C) Unbounded solution
D) None of the above
A) Feasible region
B) Infeasible region
C) Unbounded solution
D) None of the above
Feasible region
3
Which of the following may not be in a linear programming formulation?
A) <=.
B) >.
C) =.
D) All the above
A) <=.
B) >.
C) =.
D) All the above
>.
4
While solving an LP problem infeasibility may be removed by
A) Adding another constraint
B) Adding another variable
C) Removing a constraint
D) Removing a variable
A) Adding another constraint
B) Adding another variable
C) Removing a constraint
D) Removing a variable
Unlock Deck
Unlock for access to all 18 flashcards in this deck.
Unlock Deck
k this deck
5
Straight lines shown in a linear programming graph indicates
A) Objective function
B) Constraints
C) Points
D) All the above
A) Objective function
B) Constraints
C) Points
D) All the above
Unlock Deck
Unlock for access to all 18 flashcards in this deck.
Unlock Deck
k this deck
6
In linear programming problem if all constraints are less than or equal to, then the feasible region is
A) Above lines
B) Below the lines
C) Unbounded
D) None of the above
A) Above lines
B) Below the lines
C) Unbounded
D) None of the above
Unlock Deck
Unlock for access to all 18 flashcards in this deck.
Unlock Deck
k this deck
7
……. is a series of related activities which result in some product or services.
A) Network
B) transportation model
C) assignment
D) none of these
A) Network
B) transportation model
C) assignment
D) none of these
Unlock Deck
Unlock for access to all 18 flashcards in this deck.
Unlock Deck
k this deck
8
Any activity which does not consume either any resource or time is called ………. . activity.
A) Predecessor
B) Successor
C) Dummy
D) End
A) Predecessor
B) Successor
C) Dummy
D) End
Unlock Deck
Unlock for access to all 18 flashcards in this deck.
Unlock Deck
k this deck
9
All negative constraints must be written as
A) Equality
B) Non equality
C) Greater than or equal to
D) Less than or equal to
A) Equality
B) Non equality
C) Greater than or equal to
D) Less than or equal to
Unlock Deck
Unlock for access to all 18 flashcards in this deck.
Unlock Deck
k this deck
10
Activities that cannot be started until one or more of the other activities are completed, but immediately succeed them are called ……activities
A) Predecessor
B) Successor
C) Dummy
D) End
A) Predecessor
B) Successor
C) Dummy
D) End
Unlock Deck
Unlock for access to all 18 flashcards in this deck.
Unlock Deck
k this deck
11
An event which represents the beginning of more than one activity is known as ………. . event.
A) Merge
B) Net
C) Burst
D) None of the above
A) Merge
B) Net
C) Burst
D) None of the above
Unlock Deck
Unlock for access to all 18 flashcards in this deck.
Unlock Deck
k this deck
12
If two constraints do not intersect in the positive quadrant of the graph, then
A) The problem is infeasible
B) The solution is unbounded
C) One of the constraints is redundant
D) None of the above
A) The problem is infeasible
B) The solution is unbounded
C) One of the constraints is redundant
D) None of the above
Unlock Deck
Unlock for access to all 18 flashcards in this deck.
Unlock Deck
k this deck
13
An activity which must be completed before one or more other activities start is known as ………. activity.
A) Predecessor
B) Successor
C) Dummy
D) End
A) Predecessor
B) Successor
C) Dummy
D) End
Unlock Deck
Unlock for access to all 18 flashcards in this deck.
Unlock Deck
k this deck
14
While solving an LP problem, infeasibility may be removed by
A) Adding another constraint
B) Adding another variable
C) Removing a constraint
D) Removing a variable
A) Adding another constraint
B) Adding another variable
C) Removing a constraint
D) Removing a variable
Unlock Deck
Unlock for access to all 18 flashcards in this deck.
Unlock Deck
k this deck
15
…. ……. . is that sequence of activities which determines the total project time.
A) Net work
B) Critical path
C) Critical activities
D) None of the above
A) Net work
B) Critical path
C) Critical activities
D) None of the above
Unlock Deck
Unlock for access to all 18 flashcards in this deck.
Unlock Deck
k this deck
16
Activities lying on the critical path are called………….
A) Net work
B) Critical path
C) Critical activities
D) None of the above
A) Net work
B) Critical path
C) Critical activities
D) None of the above
Unlock Deck
Unlock for access to all 18 flashcards in this deck.
Unlock Deck
k this deck
17
………. . models in which the input and output variables follow a probability distribution.
A) Iconic
B) mathematical
C) analogue
D) Deterministic model
A) Iconic
B) mathematical
C) analogue
D) Deterministic model
Unlock Deck
Unlock for access to all 18 flashcards in this deck.
Unlock Deck
k this deck
18
………. Example of probabilistic model
A) Game theory
B) Charts
C) Graphs
D) All the above
A) Game theory
B) Charts
C) Graphs
D) All the above
Unlock Deck
Unlock for access to all 18 flashcards in this deck.
Unlock Deck
k this deck