Deck 4: Project Delivery Methods
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/10
Play
Full screen (f)
Deck 4: Project Delivery Methods
1
The term fast track--------
A) Is synonymous with design/manage
B) Means that construction is begun before the design is complete
C) Is synonymous with turnkey
D) Indicates that two or more companies have conbined forces for the duration of the project.
E) None of the above
A) Is synonymous with design/manage
B) Means that construction is begun before the design is complete
C) Is synonymous with turnkey
D) Indicates that two or more companies have conbined forces for the duration of the project.
E) None of the above
Means that construction is begun before the design is complete
2
An advantage of the design/build approach is that a firm's fixed price is established before construction begins.
False
3
In a pure construction management approach the construction manager usually guarantees the overall price of the project.
False
4
In a guaranteed maximum price (GMP) contract, costs above the GMP are covered by the contractor.
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
5
A unit-price contract provides an owner with price competition while still allowing for an increase or decrease in actual versus estimated quantities.
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
6
The choice of which delivery method is correct is a factor of perceived risk. Which of the following is a source of project risk?
A) Financial concerns
B) Quality of the materials or workmanship
C) When the project will be completed
D) Quality of design
E) All of the above
A) Financial concerns
B) Quality of the materials or workmanship
C) When the project will be completed
D) Quality of design
E) All of the above
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
7
Historically, a "master builder" was hired to build a project. Today, the same approach would be most like which delivery method?
A) Design/Bid/Build with a lump sum bid
B) Design/Bid/Build with a GMP
C) Construction project management
D) Design/Build
E) Unit-price contract
A) Design/Bid/Build with a lump sum bid
B) Design/Bid/Build with a GMP
C) Construction project management
D) Design/Build
E) Unit-price contract
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
8
A project is rushed into design without a total understanding of the owner's needs. As the project moves through the design, additional requirements are added, increasing the project budget. This is an example of ????
A) Project acceleration
B) Fast tracking
C) Scope creep
D) Separated functions
E) None of the above
A) Project acceleration
B) Fast tracking
C) Scope creep
D) Separated functions
E) None of the above
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
9
In which of the following project approaches is owner oversight most difficult to apply?
A) Design/Bid/Build lump sum
B) Design/Bid/Build GMP
C) Design/Build
D) Construction project management
E) Owner oversight is a function of staffing, not of the chosen delivery method or contract.
A) Design/Bid/Build lump sum
B) Design/Bid/Build GMP
C) Design/Build
D) Construction project management
E) Owner oversight is a function of staffing, not of the chosen delivery method or contract.
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
10
When assessing the risks applicable to a project, one must also look to the owner organization and the manner in which decision making occurs.
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck