Exam 4: Project Delivery Methods
Exam 1: The Construction Industry10 Questions
Exam 2: Project Participants10 Questions
Exam 3: Organizing and Leading the Construction Project9 Questions
Exam 4: Project Delivery Methods10 Questions
Exam 5: Project Chronology10 Questions
Exam 6: Construction Services During Design10 Questions
Exam 7: Bidding and Procurement10 Questions
Exam 8: Construction and Closeout10 Questions
Exam 9: Estimating Project Costs10 Questions
Exam 10: Project Planning and Scheduling10 Questions
Exam 11: Controlling Project Cost, Time, and Quality10 Questions
Exam 12: Job Site Administration10 Questions
Exam 13: Construction Law10 Questions
Exam 14: Construction Safety and Health10 Questions
Exam 15: Key Concepts in Construction Management and Delivery Methods135 Questions
Select questions type
An advantage of the design/build approach is that a firm's fixed price is established before construction begins.
Free
(True/False)
4.9/5
(34)
Correct Answer:
False
Historically, a "master builder" was hired to build a project. Today, the same approach would be most like which delivery method?
Free
(Multiple Choice)
4.9/5
(33)
Correct Answer:
D
A unit-price contract provides an owner with price competition while still allowing for an increase or decrease in actual versus estimated quantities.
Free
(True/False)
4.8/5
(35)
Correct Answer:
True
In a guaranteed maximum price (GMP) contract, costs above the GMP are covered by the contractor.
(True/False)
4.9/5
(33)
A project is rushed into design without a total understanding of the owner's needs. As the project moves through the design, additional requirements are added, increasing the project budget. This is an example of ????
(Multiple Choice)
4.7/5
(38)
In a pure construction management approach the construction manager usually guarantees the overall price of the project.
(True/False)
4.8/5
(36)
When assessing the risks applicable to a project, one must also look to the owner organization and the manner in which decision making occurs.
(True/False)
4.9/5
(31)
The choice of which delivery method is correct is a factor of perceived risk. Which of the following is a source of project risk?
(Multiple Choice)
4.7/5
(41)
In which of the following project approaches is owner oversight most difficult to apply?
(Multiple Choice)
4.7/5
(33)