Exam 4: Project Delivery Methods

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

An advantage of the design/build approach is that a firm's fixed price is established before construction begins.

Free
(True/False)
4.9/5
(34)
Correct Answer:
Verified

False

Historically, a "master builder" was hired to build a project. Today, the same approach would be most like which delivery method?

Free
(Multiple Choice)
4.9/5
(33)
Correct Answer:
Verified

D

A unit-price contract provides an owner with price competition while still allowing for an increase or decrease in actual versus estimated quantities.

Free
(True/False)
4.8/5
(35)
Correct Answer:
Verified

True

In a guaranteed maximum price (GMP) contract, costs above the GMP are covered by the contractor.

(True/False)
4.9/5
(33)

A project is rushed into design without a total understanding of the owner's needs. As the project moves through the design, additional requirements are added, increasing the project budget. This is an example of ????

(Multiple Choice)
4.7/5
(38)

In a pure construction management approach the construction manager usually guarantees the overall price of the project.

(True/False)
4.8/5
(36)

When assessing the risks applicable to a project, one must also look to the owner organization and the manner in which decision making occurs.

(True/False)
4.9/5
(31)

The term fast track--------

(Multiple Choice)
4.8/5
(33)

The choice of which delivery method is correct is a factor of perceived risk. Which of the following is a source of project risk?

(Multiple Choice)
4.7/5
(41)

In which of the following project approaches is owner oversight most difficult to apply?

(Multiple Choice)
4.7/5
(33)
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)