Deck 6: Project Activity Planning

Full screen (f)
exit full mode
Question
This project plan element describes both the managerial and the technical approaches to the work. The technical discussion describes the relationship of the project to available technologies.

A)overview
B)objectives
C)general approach
D)contractual aspects
Use Space or
up arrow
down arrow
to flip the card.
Question
Agile IT project teams are typically __________ and located at __________.

A)large, a single site
B)small, multiple sites
C)large, multiple sites
D)small, a single site
Question
The __________is a list of the project activities with major activities broken down into subactivities.

A)linear responsibility chart
B)PCMCIA
C)activity prioritization
D)WBS
Question
According to the authors, any project plan must contain all of the following EXCEPT __________.

A)evaluation methods
B)contractual aspects
C)resources
D)a 'ballpark' estimate
Question
In an agile project, teams are given several requirements but only deal with one at a time, with each iteration being referred to as a __________.

A)sprint
B)deliverable
C)WBS
D)control
Question
One of the challenges project managers face is to ensure that managers do not mix __________.

A)outcomes with the specific tasks needed to produce them
B)project milestones with their respective completion dates
C)outside interests' requirements with organizational expectations
D)control limits with specifications
Question
This project plan element should include profit and competitive goals as well as technical goals.

A)overview
B)objectives
C)general approach
D)contractual aspects
Question
The process of coordinating the work and timing of the different groups working on multidisciplinary teams is called __________.

A)procurement management
B)integration management
C)vertical management
D)matrix management
Question
The __________ of a project includes the objectives of the project as well as the time and cost required to complete the project to the customer's satisfaction.

A)scope
B)change order
C)outcome
D)purpose
Question
Which of the following is not a type of quantitative risk analysis?

A)FMEA
B)decision tree analysis
C)Monte Carlo simulation
D)expert opinion
Question
This element of the project plan contains a brief description of the procedure to be followed in monitoring, collecting, storing, and evaluating the history of the project.

A)schedule
B)resources
C)personnel
D)evaluation methods
Question
The project plan must be designed in such a way that the project outcome meets __________.

A)the objectives of the parent organization
B)unauthorized requests for change in the project outcome
C)the requirements associated with scope creep
D)only the expressed warranties identified in the contract
Question
The __________ is a specialized view of the action plan that focuses on who has what responsibility for each project task.

A)resource histogram
B)linear responsibility chart
C)project team directory
D)scope management plan
Question
RACI stands for

A)responsive, accountable, consult, inform
B)responsible, accountable, consult, inform
C)responsive, accountable, consult, integrate
D)responsible, admissible, consult, integrate
Question
Which of the following is not one of the risk management subprocesses?

A)risk identification
B)qualitative risk analysis
C)work breakdown schedule
D)risk response planning
Question
This project plan element lists all milestone events. It identifies the estimated time for each task and is used to construct the master project schedule.

A)budget
B)schedule
C)personnel plan
D)evaluation methods
Question
A type of risk response planning where the idea is to soften the danger of the threat, by reducing the likelihood it will occur, or through reducing its impact if it does occur, implies that the project manager must __________.

A)avoid
B)transfer
C)accept
D)mitigate
Question
__________ is the tendency for the project objectives to be changed with little or no discussion with other parties actively engaged in the project.

A)Scope reference
B)Scope creep
C)Effectiveness
D)Hierarchical planning
Question
In risk response planning, where the goal of the project manager is to increase the probability the opportunity will occur, the project manager must __________

A)exploit
B)share
C)enhance
D)accept
Question
The success of the project launch meeting is dependent on the existence of __________.

A)a project charter
B)the project's scope statement
C)a well-defined set of objectives for the project
D)project planning templates
Question
Identify two objections commonly raised by marketing organizations against the early participation by engineering and manufacturing in the selling process to external customers. Explain how you would counter these objections.
Question
A(n)__________ displays the organizational units responsible for each of the various work elements in the WBS.
Question
Describe the general steps recommended by the authors for designing and using the WBS.
Question
The __________ chart is a tree diagram used to represent a hierarchical plan.
Question
Why is it important for a project manager to consider risks associated with the project's external environment?
Question
The __________ is a graph showing how a statistic is changing over time compared to its average and selected control limits.
Question
Briefly describe the six processes for risk management identified in the PMBOK Guidelines.
Question
Compare the risk response planning techniques for threats and opportunities.
Question
List the seven subprocesses of project risk management.
Question
During initial project planning, activities are identified and sorted. In completing this process, each level in the hierarchy should limit the number of activities to a range between __________.
Question
A __________ must be submitted for any changes requested after the project plan has been approved.
Question
The physical items to be delivered from a project are called __________.
Question
The set of physical elements required to build a project is called the __________.
Question
Identify four important outcomes associated with the project launch meeting.
Question
__________is an approach that breaks the planning task down into the activities that must be done in each managerial level of the organization. Typically, the upper level sets the objectives for the next lower level.
Question
The major tool that a project manager uses during the planning phase is called the __________.
Question
According to the authors, the task of risk identification will be horrendous if the risk management system has no memory. Discuss the important elements of a risk management system that would compensate for alack of memory by the organization.
Question
The __________ provides a description of a task that defines all the work required to accomplish it, including inputs and desired outputs.
Question
__________ is a measure of project progress frequently related to the planned cost of tasks accomplished.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/39
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 6: Project Activity Planning
1
This project plan element describes both the managerial and the technical approaches to the work. The technical discussion describes the relationship of the project to available technologies.

A)overview
B)objectives
C)general approach
D)contractual aspects
A
2
Agile IT project teams are typically __________ and located at __________.

A)large, a single site
B)small, multiple sites
C)large, multiple sites
D)small, a single site
D
3
The __________is a list of the project activities with major activities broken down into subactivities.

A)linear responsibility chart
B)PCMCIA
C)activity prioritization
D)WBS
D
4
According to the authors, any project plan must contain all of the following EXCEPT __________.

A)evaluation methods
B)contractual aspects
C)resources
D)a 'ballpark' estimate
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
5
In an agile project, teams are given several requirements but only deal with one at a time, with each iteration being referred to as a __________.

A)sprint
B)deliverable
C)WBS
D)control
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
6
One of the challenges project managers face is to ensure that managers do not mix __________.

A)outcomes with the specific tasks needed to produce them
B)project milestones with their respective completion dates
C)outside interests' requirements with organizational expectations
D)control limits with specifications
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
7
This project plan element should include profit and competitive goals as well as technical goals.

A)overview
B)objectives
C)general approach
D)contractual aspects
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
8
The process of coordinating the work and timing of the different groups working on multidisciplinary teams is called __________.

A)procurement management
B)integration management
C)vertical management
D)matrix management
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
9
The __________ of a project includes the objectives of the project as well as the time and cost required to complete the project to the customer's satisfaction.

A)scope
B)change order
C)outcome
D)purpose
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
10
Which of the following is not a type of quantitative risk analysis?

A)FMEA
B)decision tree analysis
C)Monte Carlo simulation
D)expert opinion
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
11
This element of the project plan contains a brief description of the procedure to be followed in monitoring, collecting, storing, and evaluating the history of the project.

A)schedule
B)resources
C)personnel
D)evaluation methods
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
12
The project plan must be designed in such a way that the project outcome meets __________.

A)the objectives of the parent organization
B)unauthorized requests for change in the project outcome
C)the requirements associated with scope creep
D)only the expressed warranties identified in the contract
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
13
The __________ is a specialized view of the action plan that focuses on who has what responsibility for each project task.

A)resource histogram
B)linear responsibility chart
C)project team directory
D)scope management plan
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
14
RACI stands for

A)responsive, accountable, consult, inform
B)responsible, accountable, consult, inform
C)responsive, accountable, consult, integrate
D)responsible, admissible, consult, integrate
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
15
Which of the following is not one of the risk management subprocesses?

A)risk identification
B)qualitative risk analysis
C)work breakdown schedule
D)risk response planning
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
16
This project plan element lists all milestone events. It identifies the estimated time for each task and is used to construct the master project schedule.

A)budget
B)schedule
C)personnel plan
D)evaluation methods
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
17
A type of risk response planning where the idea is to soften the danger of the threat, by reducing the likelihood it will occur, or through reducing its impact if it does occur, implies that the project manager must __________.

A)avoid
B)transfer
C)accept
D)mitigate
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
18
__________ is the tendency for the project objectives to be changed with little or no discussion with other parties actively engaged in the project.

A)Scope reference
B)Scope creep
C)Effectiveness
D)Hierarchical planning
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
19
In risk response planning, where the goal of the project manager is to increase the probability the opportunity will occur, the project manager must __________

A)exploit
B)share
C)enhance
D)accept
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
20
The success of the project launch meeting is dependent on the existence of __________.

A)a project charter
B)the project's scope statement
C)a well-defined set of objectives for the project
D)project planning templates
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
21
Identify two objections commonly raised by marketing organizations against the early participation by engineering and manufacturing in the selling process to external customers. Explain how you would counter these objections.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
22
A(n)__________ displays the organizational units responsible for each of the various work elements in the WBS.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
23
Describe the general steps recommended by the authors for designing and using the WBS.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
24
The __________ chart is a tree diagram used to represent a hierarchical plan.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
25
Why is it important for a project manager to consider risks associated with the project's external environment?
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
26
The __________ is a graph showing how a statistic is changing over time compared to its average and selected control limits.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
27
Briefly describe the six processes for risk management identified in the PMBOK Guidelines.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
28
Compare the risk response planning techniques for threats and opportunities.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
29
List the seven subprocesses of project risk management.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
30
During initial project planning, activities are identified and sorted. In completing this process, each level in the hierarchy should limit the number of activities to a range between __________.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
31
A __________ must be submitted for any changes requested after the project plan has been approved.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
32
The physical items to be delivered from a project are called __________.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
33
The set of physical elements required to build a project is called the __________.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
34
Identify four important outcomes associated with the project launch meeting.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
35
__________is an approach that breaks the planning task down into the activities that must be done in each managerial level of the organization. Typically, the upper level sets the objectives for the next lower level.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
36
The major tool that a project manager uses during the planning phase is called the __________.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
37
According to the authors, the task of risk identification will be horrendous if the risk management system has no memory. Discuss the important elements of a risk management system that would compensate for alack of memory by the organization.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
38
The __________ provides a description of a task that defines all the work required to accomplish it, including inputs and desired outputs.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
39
__________ is a measure of project progress frequently related to the planned cost of tasks accomplished.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 39 flashcards in this deck.