Exam 6: Project Activity Planning

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Briefly describe the six processes for risk management identified in the PMBOK Guidelines.

Free
(Essay)
4.9/5
(37)
Correct Answer:
Verified

Risk management planning is focused on how to approach and plan the risk management activities for a project. In risk identification, the risks that can affect the project for better or for worse are identified. In qualitative risk analysis, non-numerical priorities are established for the risk events identified previously. In quantitative risk analysis, probability and impact are converted into expected monetary value. In risk response planning, contingency plans are established to capture opportunities and respond to threats. In risk monitoring and control, warning signs and triggers are used to determine when corrective actions are required to bring the project back on track.
Refer to the section: Project Risk Management.

Which of the following is not a type of quantitative risk analysis?

Free
(Multiple Choice)
4.7/5
(27)
Correct Answer:
Verified

D

A __________ must be submitted for any changes requested after the project plan has been approved.

Free
(Short Answer)
4.8/5
(35)
Correct Answer:
Verified

change order

The major tool that a project manager uses during the planning phase is called the __________.

(Short Answer)
4.7/5
(30)

In risk response planning, where the goal of the project manager is to increase the probability the opportunity will occur, the project manager must __________

(Multiple Choice)
4.8/5
(36)

The process of coordinating the work and timing of the different groups working on multidisciplinary teams is called __________.

(Multiple Choice)
4.8/5
(33)

This project plan element lists all milestone events. It identifies the estimated time for each task and is used to construct the master project schedule.

(Multiple Choice)
4.9/5
(38)

According to the authors, the task of risk identification will be horrendous if the risk management system has no memory. Discuss the important elements of a risk management system that would compensate for alack of memory by the organization.

(Essay)
4.9/5
(39)

This project plan element describes both the managerial and the technical approaches to the work. The technical discussion describes the relationship of the project to available technologies.

(Multiple Choice)
4.9/5
(40)

The __________is a list of the project activities with major activities broken down into subactivities.

(Multiple Choice)
4.8/5
(28)

This project plan element should include profit and competitive goals as well as technical goals.

(Multiple Choice)
4.9/5
(35)

Agile IT project teams are typically __________ and located at __________.

(Multiple Choice)
4.8/5
(33)

Identify two objections commonly raised by marketing organizations against the early participation by engineering and manufacturing in the selling process to external customers. Explain how you would counter these objections.

(Essay)
4.9/5
(38)

The project plan must be designed in such a way that the project outcome meets __________.

(Multiple Choice)
4.8/5
(35)

The __________ provides a description of a task that defines all the work required to accomplish it, including inputs and desired outputs.

(Short Answer)
4.8/5
(24)

The set of physical elements required to build a project is called the __________.

(Short Answer)
4.7/5
(40)

Describe the general steps recommended by the authors for designing and using the WBS.

(Essay)
4.8/5
(41)

__________ is the tendency for the project objectives to be changed with little or no discussion with other parties actively engaged in the project.

(Multiple Choice)
4.8/5
(36)

According to the authors, any project plan must contain all of the following EXCEPT __________.

(Multiple Choice)
4.7/5
(38)

The __________ is a specialized view of the action plan that focuses on who has what responsibility for each project task.

(Multiple Choice)
4.7/5
(29)
Showing 1 - 20 of 39
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)