Deck 8: Scheduling Projects

Full screen (f)
exit full mode
Question
To use the enumeration method of determining the critical path,we list or enumerate all of the paths through the network.
Use Space or
up arrow
down arrow
to flip the card.
Question
The critical path is the sequence of schedule activities determining the duration of the project,and is generally the shortest path through the project.
Question
The most common type of logical dependency to determine the sequence of project activities is "finish-to-finish" (FF).
Question
When developing a project schedule,total float refers to the amount of time a schedule activity may be delayed from its early start date without delaying the project end date.
Question
The length of time to perform an activity is often dependent upon who will do that work.
Question
The "start-to-start" logical relationship used in activity sequencing applies to the case in which a successor activity cannot start until a predecessor activity has started.
Question
A mandatory dependency is a logical relationship between activities that must happen - usually due to a physical or legal demand.
Question
There is often terrific pressure to complete a project as quickly as possible.To confront this pressure,a project manager should quickly promise to meet the deadlines requested by the sponsor and then assemble a team to create the corresponding schedule.
Question
In the enumeration method the project schedule is calculated many times (perhaps 1,000 or more),and each time,the estimate for a particular activity is generated based on the likelihood of that time as determined by the project manager.
Question
If the project manager changes an activity on the critical path to start at a later date,then the whole project will end at a later date.
Question
While the lowest level of decomposition in a WBS is the work package,work packages can still be decomposed further into work activities.
Question
A Gantt chart is a horizontal bar chart that shows each work activity on a separate line with the bar placed from the early start date to the early finish date for each activity on a timescale.
Question
In order for activities to be useful as schedule building blocks,they should have tangible output that can be verified.
Question
PERT refers to Program Evaluation and Review Technique,which was developed in the 1950s to better understand how variability in the individual activity durations impacts the entire project schedule.
Question
GANTT refers to the Generalized Activity Network Tracking Technique which was developed to better understand how variability in the duration of individual activities impacts the expected project duration.
Question
The primary advantage of PERT is that it removes uncertainty from the estimates of activity durations,thereby increasing confidence in the reliability of a project schedule.
Question
Except in rare circumstances,project teams should not attempt to decompose work packages into project activities because work packages provide sufficient detail to develop a project schedule.
Question
A successor activity is the schedule activity that follows a predecessor activity,as determined by their logical relationship.
Question
The first process in developing a project schedule is to identify all the resources available to work on the project.
Question
Even small delays on "near-critical" activities can change the critical path of a project.
Question
<strong>  Figure 7-1 Assembly Project Consider the Assembly Project depicted in Figure 7-1.Based on the information provided,what is the early start date for activity D - Attach Modules 1 & 2?​ </strong> A) Day 0  B) Day 3  C) Day 4  D) Day 5 <div style=padding-top: 35px> Figure 7-1 Assembly Project
Consider the Assembly Project depicted in Figure 7-1.Based on the information provided,what is the early start date for activity D - "Attach Modules 1 & 2"?​ 

A) Day 0 
B) Day 3 
C) Day 4 
D) Day 5
Question
Faced with significant schedule challenges,the project manager has an ethical responsibility to do all of the following EXCEPT:​ 

A) willingly accept end dates dictated by customers or sponsors 
B) persuade all stakeholders that the schedule makes sense 
C) deliver the project according to the agreed-upon schedule 
D) determine a schedule that is possible to achieve
Question
Which of the following statements correctly describes the critical path?​ 

A) The sequence of activities that represents the shortest path through the project network. 
B) It determines the latest possible end date of the project. 
C) It consists only of activities with zero float (slack). 
D) It consists only of activities with lag times
Question
Milestones are important points in a project schedule that can serve as check points for project managers and sponsors.Which of the following could be a reason to identify a milestone during project schedule planning?​ 

A) signing of  the project charter  
B) completion of a major deliverable 
C) completion of the WBS  
D) weekly team status meetings
Question
During which of the following Project Schedule Management processes does the team estimate the number of work periods that will be required to complete a schedule activity,usually expressed as workdays or workweeks? ​ 

A) Define activities 
B) Sequence activities 
C) Estimate activity durations 
D) Develop schedule
Question
The sequencing of activities is often based upon dependencies between the activities.The dependencies that should guide activity sequencing can be either: 

A) critical or non-critical 
B) opportunities or threats 
C) mandatory or discretionary 
D) interior or exterior
Question
The amount of time a schedule activity can be delayed without delaying the early start date of immediately following schedule activities is:​ 

A) reserve 
B) free float 
C) contingency 
D) lead
Question
<strong>  Figure 7-2 Research Project Consider the Research Project depicted in Figure 7-2.Based on the information provided,which activity can you delay by one day without impacting the expected completion date for the project?​ </strong> A) Activity A  B) Activity B  C) Activity C  D) Activity D <div style=padding-top: 35px> Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2.Based on the information provided,which activity can you delay by one day without impacting the expected completion date for the project?​ 

A) Activity A 
B) Activity B 
C) Activity C 
D) Activity D
Question
Which of these is NOT one of the items that can provide useful assistance to a project team to define the activities of a project?​ 

A) the major milestones from the Project Charter 
B) issue logs 
C) templates or checklists for projects of the same type 
D) schedules from similar, previous projects
Question
Which of the following remedies may reduce the likelihood of omissions when developing activity duration estimates?​ 

A) Lessons learned 
B) Resource buffers 
C) Learning curve 
D) Staggering project start dates
Question
<strong>  Figure 7-2 Research Project Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity A - Plan Research?​ </strong> A) Day 0  B) Day 2  C) Day 4  D) Day 10 <div style=padding-top: 35px> Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity A - "Plan Research"?​ 

A) Day 0 
B) Day 2 
C) Day 4 
D) Day 10
Question
Which of the following responses identifies a common type of logical dependency used to sequence project activities?​ 

A) first-in; first-out 
B) last-in; last-out 
C) finish-to-start 
D) last-in; first-out
Question
<strong>  Figure 7-2 Research Project Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the slack associated with activity C - Review Reports?​ </strong> A) 0 days  B) 1 day  C) 2 days  D) 4 days <div style=padding-top: 35px> Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the slack associated with activity C - "Review Reports"?​ 

A) 0 days 
B) 1 day 
C) 2 days 
D) 4 days
Question
Creating a realistic schedule is often an iterative process because several factors can limit how fast a project can be completed.All of the following factors can limit how fast a project can be scheduled and completed EXCEPT:​ 

A) Logical order 
B) Imposed dates 
C) Resource availability 
D) Quality metrics
Question
<strong>  Figure 7-3 System Integration Project Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,what is the expected duration of this project?​ </strong> A) 15 days  B) 16 days  C) 17 days  D) 30 days <div style=padding-top: 35px> Figure 7-3 System Integration Project
Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,what is the expected duration of this project?​ 

A) 15 days 
B) 16 days 
C) 17 days 
D) 30 days
Question
Which of these represents a typical problem that can make it difficult to estimate activity durations accurately?​ 

A) merging - multiple predecessors 
B) checklists and templates 
C) reducing sources of uncertainty in the estimate 
D) carefully authorizing the start of non-critical activities
Question
<strong>  Figure 7-2 Research Project Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity C - Review Reports?​ </strong> A) Day 0  B) Day 2  C) Day 4  D) Day 10 <div style=padding-top: 35px> Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity C - "Review Reports"?​ 

A) Day 0 
B) Day 2 
C) Day 4 
D) Day 10
Question
The schedule activity that determines when the logical successor activity can begin or end is called the _______: 

A) leader activity 
B) predecessor activity 
C) successor activity 
D) mandatory activity
Question
All of the following strategies can help a project team to develop realistic time estimates for project activities EXCEPT:​ 

A) Add a significant buffer of time to each activity 
B) Keep in mind time constraints such as learning curves, interruptions and competing priorities 
C) Estimate times of completion of work without initial reference to a calendar 
D) Verify all time estimates with the people doing the work
Question
This term is defined as the total number of work periods (not including holidays or other non-work periods)required to complete a schedule activity,usually expressed as workdays or workweeks:​ 

A) effort 
B) elapsed time 
C) duration 
D) resource days
Question
All of the following statements correctly describe an advantage or disadvantage associated with the use of Monte Carlo Analysis EXCEPT: 

A) The flexibility of Monte Carlo Analysis allows for more realistic estimates. 
B) Monte Carlo simulation aids in the identification of near-critical paths. 
C) Monte Carlo simulations typically require the use of special software and skills. 
D) Monte Carlo simulations do not consider risks
Question
Describe free float and how you can use it to your advantage in scheduling and managing a project.
Question
<strong>  Figure 7-6 Network Scheduling Data Consider the network scheduling data presented in Figure 7-6.How many days of slack are associated with activity F? </strong> A) 0  B) 15  C) 80  D) 107 <div style=padding-top: 35px> Figure 7-6 Network Scheduling Data
Consider the network scheduling data presented in Figure 7-6.How many days of slack are associated with activity F? 

A) 0 
B) 15 
C) 80 
D) 107
Question
<strong>  Figure 7-6 Network Scheduling Data Consider the network scheduling data provided in Figure 7-6.Which activities constitute the critical path for this project network? </strong> A) A-D-F-I  B) A-C-E-H-I  C) A-B-E-H-I  D) A-B-E-G-I <div style=padding-top: 35px> Figure 7-6 Network Scheduling Data
Consider the network scheduling data provided in Figure 7-6.Which activities constitute the critical path for this project network? 

A) A-D-F-I 
B) A-C-E-H-I 
C) A-B-E-H-I 
D) A-B-E-G-I
Question
<strong>  Figure 7-4 Lab Experiment Project Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,identify the critical path(s)for this project? </strong> A) A-C-F only  B) A-B-D-F only  C) A-B-E-F only  D) Both A-B-D-F and A-B-E-F are critical paths <div style=padding-top: 35px> Figure 7-4 Lab Experiment Project
Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,identify the critical path(s)for this project? 

A) A-C-F only 
B) A-B-D-F only 
C) A-B-E-F only 
D) Both A-B-D-F and A-B-E-F are critical paths
Question
<strong>  Figure 7-4 Lab Experiment Project Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,how many days can you delay the calibration of the instrumentation (Activity B),without impacting the expected project completion date? </strong> A) 0 days  B) 1 day  C) 2 days  D) 4 days <div style=padding-top: 35px> Figure 7-4 Lab Experiment Project
Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,how many days can you delay the calibration of the instrumentation (Activity B),without impacting the expected project completion date? 

A) 0 days 
B) 1 day 
C) 2 days 
D) 4 days
Question
<strong>  Figure 7-4 Lab Experiment Project Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,what is the expected duration of this project? </strong> A) 22 days  B) 24 days  C) 26 days  D) 28 days <div style=padding-top: 35px> Figure 7-4 Lab Experiment Project
Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,what is the expected duration of this project? 

A) 22 days 
B) 24 days 
C) 26 days 
D) 28 days
Question
<strong>  Figure 7-3 System Integration Project Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities constitute the critical path for this project?​ </strong> A) A-B-E-F  B) A-C-E-F  C) A-D-E-F  D) A-D-F <div style=padding-top: 35px> Figure 7-3 System Integration Project
Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities constitute the critical path for this project?​ 

A) A-B-E-F 
B) A-C-E-F 
C) A-D-E-F 
D) A-D-F
Question
Many factors can impact the accuracy of activity duration estimates.Describe four of the problems associated with estimating activity durations accurately,and the techniques you could use as a project manager to overcome them.
Question
Describe how you would use the members of your project team to develop and execute a project schedule.
Question
<strong>  Figure 7-4 Lab Experiment Project Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,which activity can be delayed one day without impacting the expected project completion date? </strong> A) Activity B - Calibrate Instruments  B) Activity C - Review Studies  C) Activity D - Monitor Instruments  D) Activity E - Test Samples <div style=padding-top: 35px> Figure 7-4 Lab Experiment Project
Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,which activity can be delayed one day without impacting the expected project completion date? 

A) Activity B - Calibrate Instruments 
B) Activity C - Review Studies 
C) Activity D - Monitor Instruments 
D) Activity E - Test Samples
Question
<strong>  Figure 7-5 Duration Estimates Consider the activity duration estimates presented in Figure 7-5.Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - Package Item?​ </strong> A) 9 days  B) 9.5 days  C) 10 days  D) 12 days <div style=padding-top: 35px> Figure 7-5 Duration Estimates
Consider the activity duration estimates presented in Figure 7-5.Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - "Package Item"?​ 

A) 9 days 
B) 9.5 days 
C) 10 days 
D) 12 days
Question
Despite the insights that PERT provides,there are still practical limitations that impact its usefulness.All of the following difficulties are associated with the use of PERT EXCEPT: 

A) It often requires more effort to generate three estimates than one. 
B) It highlights uncertainty in project duration 
C) It does not accurately address the case when two activities both need to be accomplished before a third can begin. 
D) There is no assurance that three estimates are any more accurate than one
Question
<strong>  Figure 7-3 System Integration Project Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,how many days can you delay the purchase of software (Activity C),without impacting the expected project completion date? </strong> A) 0 days  B) 1 day  C) 2 days  D) 4 days <div style=padding-top: 35px> Figure 7-3 System Integration Project
Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,how many days can you delay the purchase of software (Activity C),without impacting the expected project completion date? 

A) 0 days 
B) 1 day 
C) 2 days 
D) 4 days
Question
<strong>  Figure 7-6 Network Scheduling Data Consider the network scheduling data provided in Figure 7-6.What is the expected duration of this project? </strong> A) 97 days  B) 102 days  C) 107 days  D) 112 days <div style=padding-top: 35px> Figure 7-6 Network Scheduling Data
Consider the network scheduling data provided in Figure 7-6.What is the expected duration of this project? 

A) 97 days 
B) 102 days 
C) 107 days 
D) 112 days
Question
<strong>  Figure 7-3 System Integration Project Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities can be delayed one day without impacting the expected project completion date? </strong> A) Activity E - Install Software and Activity F - Test System  B) Activity C - Purchase Software and Activity E - Install Software  C) Activity C - Purchase Software and Activity D - Prepare Test Plan  D) none of these <div style=padding-top: 35px> Figure 7-3 System Integration Project
Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities can be delayed one day without impacting the expected project completion date? 

A) Activity E - Install Software and Activity F - Test System 
B) Activity C - Purchase Software and Activity E - Install Software 
C) Activity C - Purchase Software and Activity D - Prepare Test Plan 
D) none of these
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/56
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 8: Scheduling Projects
1
To use the enumeration method of determining the critical path,we list or enumerate all of the paths through the network.
True
2
The critical path is the sequence of schedule activities determining the duration of the project,and is generally the shortest path through the project.
False
3
The most common type of logical dependency to determine the sequence of project activities is "finish-to-finish" (FF).
False
4
When developing a project schedule,total float refers to the amount of time a schedule activity may be delayed from its early start date without delaying the project end date.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
5
The length of time to perform an activity is often dependent upon who will do that work.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
6
The "start-to-start" logical relationship used in activity sequencing applies to the case in which a successor activity cannot start until a predecessor activity has started.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
7
A mandatory dependency is a logical relationship between activities that must happen - usually due to a physical or legal demand.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
8
There is often terrific pressure to complete a project as quickly as possible.To confront this pressure,a project manager should quickly promise to meet the deadlines requested by the sponsor and then assemble a team to create the corresponding schedule.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
9
In the enumeration method the project schedule is calculated many times (perhaps 1,000 or more),and each time,the estimate for a particular activity is generated based on the likelihood of that time as determined by the project manager.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
10
If the project manager changes an activity on the critical path to start at a later date,then the whole project will end at a later date.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
11
While the lowest level of decomposition in a WBS is the work package,work packages can still be decomposed further into work activities.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
12
A Gantt chart is a horizontal bar chart that shows each work activity on a separate line with the bar placed from the early start date to the early finish date for each activity on a timescale.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
13
In order for activities to be useful as schedule building blocks,they should have tangible output that can be verified.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
14
PERT refers to Program Evaluation and Review Technique,which was developed in the 1950s to better understand how variability in the individual activity durations impacts the entire project schedule.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
15
GANTT refers to the Generalized Activity Network Tracking Technique which was developed to better understand how variability in the duration of individual activities impacts the expected project duration.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
16
The primary advantage of PERT is that it removes uncertainty from the estimates of activity durations,thereby increasing confidence in the reliability of a project schedule.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
17
Except in rare circumstances,project teams should not attempt to decompose work packages into project activities because work packages provide sufficient detail to develop a project schedule.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
18
A successor activity is the schedule activity that follows a predecessor activity,as determined by their logical relationship.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
19
The first process in developing a project schedule is to identify all the resources available to work on the project.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
20
Even small delays on "near-critical" activities can change the critical path of a project.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
21
<strong>  Figure 7-1 Assembly Project Consider the Assembly Project depicted in Figure 7-1.Based on the information provided,what is the early start date for activity D - Attach Modules 1 & 2?​ </strong> A) Day 0  B) Day 3  C) Day 4  D) Day 5 Figure 7-1 Assembly Project
Consider the Assembly Project depicted in Figure 7-1.Based on the information provided,what is the early start date for activity D - "Attach Modules 1 & 2"?​ 

A) Day 0 
B) Day 3 
C) Day 4 
D) Day 5
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
22
Faced with significant schedule challenges,the project manager has an ethical responsibility to do all of the following EXCEPT:​ 

A) willingly accept end dates dictated by customers or sponsors 
B) persuade all stakeholders that the schedule makes sense 
C) deliver the project according to the agreed-upon schedule 
D) determine a schedule that is possible to achieve
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
23
Which of the following statements correctly describes the critical path?​ 

A) The sequence of activities that represents the shortest path through the project network. 
B) It determines the latest possible end date of the project. 
C) It consists only of activities with zero float (slack). 
D) It consists only of activities with lag times
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
24
Milestones are important points in a project schedule that can serve as check points for project managers and sponsors.Which of the following could be a reason to identify a milestone during project schedule planning?​ 

A) signing of  the project charter  
B) completion of a major deliverable 
C) completion of the WBS  
D) weekly team status meetings
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
25
During which of the following Project Schedule Management processes does the team estimate the number of work periods that will be required to complete a schedule activity,usually expressed as workdays or workweeks? ​ 

A) Define activities 
B) Sequence activities 
C) Estimate activity durations 
D) Develop schedule
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
26
The sequencing of activities is often based upon dependencies between the activities.The dependencies that should guide activity sequencing can be either: 

A) critical or non-critical 
B) opportunities or threats 
C) mandatory or discretionary 
D) interior or exterior
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
27
The amount of time a schedule activity can be delayed without delaying the early start date of immediately following schedule activities is:​ 

A) reserve 
B) free float 
C) contingency 
D) lead
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
28
<strong>  Figure 7-2 Research Project Consider the Research Project depicted in Figure 7-2.Based on the information provided,which activity can you delay by one day without impacting the expected completion date for the project?​ </strong> A) Activity A  B) Activity B  C) Activity C  D) Activity D Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2.Based on the information provided,which activity can you delay by one day without impacting the expected completion date for the project?​ 

A) Activity A 
B) Activity B 
C) Activity C 
D) Activity D
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
29
Which of these is NOT one of the items that can provide useful assistance to a project team to define the activities of a project?​ 

A) the major milestones from the Project Charter 
B) issue logs 
C) templates or checklists for projects of the same type 
D) schedules from similar, previous projects
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
30
Which of the following remedies may reduce the likelihood of omissions when developing activity duration estimates?​ 

A) Lessons learned 
B) Resource buffers 
C) Learning curve 
D) Staggering project start dates
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
31
<strong>  Figure 7-2 Research Project Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity A - Plan Research?​ </strong> A) Day 0  B) Day 2  C) Day 4  D) Day 10 Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity A - "Plan Research"?​ 

A) Day 0 
B) Day 2 
C) Day 4 
D) Day 10
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
32
Which of the following responses identifies a common type of logical dependency used to sequence project activities?​ 

A) first-in; first-out 
B) last-in; last-out 
C) finish-to-start 
D) last-in; first-out
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
33
<strong>  Figure 7-2 Research Project Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the slack associated with activity C - Review Reports?​ </strong> A) 0 days  B) 1 day  C) 2 days  D) 4 days Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the slack associated with activity C - "Review Reports"?​ 

A) 0 days 
B) 1 day 
C) 2 days 
D) 4 days
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
34
Creating a realistic schedule is often an iterative process because several factors can limit how fast a project can be completed.All of the following factors can limit how fast a project can be scheduled and completed EXCEPT:​ 

A) Logical order 
B) Imposed dates 
C) Resource availability 
D) Quality metrics
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
35
<strong>  Figure 7-3 System Integration Project Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,what is the expected duration of this project?​ </strong> A) 15 days  B) 16 days  C) 17 days  D) 30 days Figure 7-3 System Integration Project
Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,what is the expected duration of this project?​ 

A) 15 days 
B) 16 days 
C) 17 days 
D) 30 days
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
36
Which of these represents a typical problem that can make it difficult to estimate activity durations accurately?​ 

A) merging - multiple predecessors 
B) checklists and templates 
C) reducing sources of uncertainty in the estimate 
D) carefully authorizing the start of non-critical activities
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
37
<strong>  Figure 7-2 Research Project Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity C - Review Reports?​ </strong> A) Day 0  B) Day 2  C) Day 4  D) Day 10 Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity C - "Review Reports"?​ 

A) Day 0 
B) Day 2 
C) Day 4 
D) Day 10
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
38
The schedule activity that determines when the logical successor activity can begin or end is called the _______: 

A) leader activity 
B) predecessor activity 
C) successor activity 
D) mandatory activity
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
39
All of the following strategies can help a project team to develop realistic time estimates for project activities EXCEPT:​ 

A) Add a significant buffer of time to each activity 
B) Keep in mind time constraints such as learning curves, interruptions and competing priorities 
C) Estimate times of completion of work without initial reference to a calendar 
D) Verify all time estimates with the people doing the work
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
40
This term is defined as the total number of work periods (not including holidays or other non-work periods)required to complete a schedule activity,usually expressed as workdays or workweeks:​ 

A) effort 
B) elapsed time 
C) duration 
D) resource days
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
41
All of the following statements correctly describe an advantage or disadvantage associated with the use of Monte Carlo Analysis EXCEPT: 

A) The flexibility of Monte Carlo Analysis allows for more realistic estimates. 
B) Monte Carlo simulation aids in the identification of near-critical paths. 
C) Monte Carlo simulations typically require the use of special software and skills. 
D) Monte Carlo simulations do not consider risks
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
42
Describe free float and how you can use it to your advantage in scheduling and managing a project.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
43
<strong>  Figure 7-6 Network Scheduling Data Consider the network scheduling data presented in Figure 7-6.How many days of slack are associated with activity F? </strong> A) 0  B) 15  C) 80  D) 107 Figure 7-6 Network Scheduling Data
Consider the network scheduling data presented in Figure 7-6.How many days of slack are associated with activity F? 

A) 0 
B) 15 
C) 80 
D) 107
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
44
<strong>  Figure 7-6 Network Scheduling Data Consider the network scheduling data provided in Figure 7-6.Which activities constitute the critical path for this project network? </strong> A) A-D-F-I  B) A-C-E-H-I  C) A-B-E-H-I  D) A-B-E-G-I Figure 7-6 Network Scheduling Data
Consider the network scheduling data provided in Figure 7-6.Which activities constitute the critical path for this project network? 

A) A-D-F-I 
B) A-C-E-H-I 
C) A-B-E-H-I 
D) A-B-E-G-I
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
45
<strong>  Figure 7-4 Lab Experiment Project Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,identify the critical path(s)for this project? </strong> A) A-C-F only  B) A-B-D-F only  C) A-B-E-F only  D) Both A-B-D-F and A-B-E-F are critical paths Figure 7-4 Lab Experiment Project
Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,identify the critical path(s)for this project? 

A) A-C-F only 
B) A-B-D-F only 
C) A-B-E-F only 
D) Both A-B-D-F and A-B-E-F are critical paths
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
46
<strong>  Figure 7-4 Lab Experiment Project Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,how many days can you delay the calibration of the instrumentation (Activity B),without impacting the expected project completion date? </strong> A) 0 days  B) 1 day  C) 2 days  D) 4 days Figure 7-4 Lab Experiment Project
Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,how many days can you delay the calibration of the instrumentation (Activity B),without impacting the expected project completion date? 

A) 0 days 
B) 1 day 
C) 2 days 
D) 4 days
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
47
<strong>  Figure 7-4 Lab Experiment Project Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,what is the expected duration of this project? </strong> A) 22 days  B) 24 days  C) 26 days  D) 28 days Figure 7-4 Lab Experiment Project
Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,what is the expected duration of this project? 

A) 22 days 
B) 24 days 
C) 26 days 
D) 28 days
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
48
<strong>  Figure 7-3 System Integration Project Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities constitute the critical path for this project?​ </strong> A) A-B-E-F  B) A-C-E-F  C) A-D-E-F  D) A-D-F Figure 7-3 System Integration Project
Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities constitute the critical path for this project?​ 

A) A-B-E-F 
B) A-C-E-F 
C) A-D-E-F 
D) A-D-F
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
49
Many factors can impact the accuracy of activity duration estimates.Describe four of the problems associated with estimating activity durations accurately,and the techniques you could use as a project manager to overcome them.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
50
Describe how you would use the members of your project team to develop and execute a project schedule.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
51
<strong>  Figure 7-4 Lab Experiment Project Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,which activity can be delayed one day without impacting the expected project completion date? </strong> A) Activity B - Calibrate Instruments  B) Activity C - Review Studies  C) Activity D - Monitor Instruments  D) Activity E - Test Samples Figure 7-4 Lab Experiment Project
Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,which activity can be delayed one day without impacting the expected project completion date? 

A) Activity B - Calibrate Instruments 
B) Activity C - Review Studies 
C) Activity D - Monitor Instruments 
D) Activity E - Test Samples
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
52
<strong>  Figure 7-5 Duration Estimates Consider the activity duration estimates presented in Figure 7-5.Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - Package Item?​ </strong> A) 9 days  B) 9.5 days  C) 10 days  D) 12 days Figure 7-5 Duration Estimates
Consider the activity duration estimates presented in Figure 7-5.Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - "Package Item"?​ 

A) 9 days 
B) 9.5 days 
C) 10 days 
D) 12 days
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
53
Despite the insights that PERT provides,there are still practical limitations that impact its usefulness.All of the following difficulties are associated with the use of PERT EXCEPT: 

A) It often requires more effort to generate three estimates than one. 
B) It highlights uncertainty in project duration 
C) It does not accurately address the case when two activities both need to be accomplished before a third can begin. 
D) There is no assurance that three estimates are any more accurate than one
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
54
<strong>  Figure 7-3 System Integration Project Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,how many days can you delay the purchase of software (Activity C),without impacting the expected project completion date? </strong> A) 0 days  B) 1 day  C) 2 days  D) 4 days Figure 7-3 System Integration Project
Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,how many days can you delay the purchase of software (Activity C),without impacting the expected project completion date? 

A) 0 days 
B) 1 day 
C) 2 days 
D) 4 days
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
55
<strong>  Figure 7-6 Network Scheduling Data Consider the network scheduling data provided in Figure 7-6.What is the expected duration of this project? </strong> A) 97 days  B) 102 days  C) 107 days  D) 112 days Figure 7-6 Network Scheduling Data
Consider the network scheduling data provided in Figure 7-6.What is the expected duration of this project? 

A) 97 days 
B) 102 days 
C) 107 days 
D) 112 days
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
56
<strong>  Figure 7-3 System Integration Project Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities can be delayed one day without impacting the expected project completion date? </strong> A) Activity E - Install Software and Activity F - Test System  B) Activity C - Purchase Software and Activity E - Install Software  C) Activity C - Purchase Software and Activity D - Prepare Test Plan  D) none of these Figure 7-3 System Integration Project
Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities can be delayed one day without impacting the expected project completion date? 

A) Activity E - Install Software and Activity F - Test System 
B) Activity C - Purchase Software and Activity E - Install Software 
C) Activity C - Purchase Software and Activity D - Prepare Test Plan 
D) none of these
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 56 flashcards in this deck.