During which of the following Project Schedule Management processes does the team estimate the number of work periods that will be required to complete a schedule activity,usually expressed as workdays or workweeks? ​ 

Free
(Multiple Choice)
4.9/5
(40)
Correct Answer:
Verified

C

  Figure 7-2 Research Project -Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the slack associated with activity C - Review Reports?​  Figure 7-2 Research Project -Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the slack associated with activity C - "Review Reports"?​ 

Free
(Multiple Choice)
4.9/5
(40)
Correct Answer:
Verified

C

The most common type of logical dependency to determine the sequence of project activities is "finish-to-finish" (FF).

Free
(True/False)
4.8/5
(28)
Correct Answer:
Verified

False

  Figure 7-3 System Integration Project -Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities constitute the critical path for this project?​  Figure 7-3 System Integration Project -Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities constitute the critical path for this project?​ 

(Multiple Choice)
4.9/5
(35)

All of the following statements correctly describe an advantage or disadvantage associated with the use of Monte Carlo Analysis EXCEPT: 

(Multiple Choice)
4.9/5
(31)

Describe how you would use the members of your project team to develop and execute a project schedule.

(Essay)
4.8/5
(34)

In the enumeration method the project schedule is calculated many times (perhaps 1,000 or more),and each time,the estimate for a particular activity is generated based on the likelihood of that time as determined by the project manager.

(True/False)
4.7/5
(33)

A Gantt chart is a horizontal bar chart that shows each work activity on a separate line with the bar placed from the early start date to the early finish date for each activity on a timescale.

(True/False)
4.7/5
(42)

The amount of time a schedule activity can be delayed without delaying the early start date of immediately following schedule activities is:​ 

(Multiple Choice)
4.9/5
(35)

A mandatory dependency is a logical relationship between activities that must happen - usually due to a physical or legal demand.

(True/False)
4.9/5
(29)

The schedule activity that determines when the logical successor activity can begin or end is called the _______: 

(Multiple Choice)
5.0/5
(36)

The sequencing of activities is often based upon dependencies between the activities.The dependencies that should guide activity sequencing can be either: 

(Multiple Choice)
4.9/5
(35)

  Figure 7-5 Duration Estimates -Consider the activity duration estimates presented in Figure 7-5.Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - Package Item?​  Figure 7-5 Duration Estimates -Consider the activity duration estimates presented in Figure 7-5.Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - "Package Item"?​ 

(Multiple Choice)
4.9/5
(38)

  Figure 7-2 Research Project -Consider the Research Project depicted in Figure 7-2.Based on the information provided,which activity can you delay by one day without impacting the expected completion date for the project?​  Figure 7-2 Research Project -Consider the Research Project depicted in Figure 7-2.Based on the information provided,which activity can you delay by one day without impacting the expected completion date for the project?​ 

(Multiple Choice)
4.8/5
(38)

Which of the following statements correctly describes the critical path?​ 

(Multiple Choice)
4.8/5
(26)

  Figure 7-3 System Integration Project -Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities can be delayed one day without impacting the expected project completion date?  Figure 7-3 System Integration Project -Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities can be delayed one day without impacting the expected project completion date? 

(Multiple Choice)
4.8/5
(40)

There is often terrific pressure to complete a project as quickly as possible.To confront this pressure,a project manager should quickly promise to meet the deadlines requested by the sponsor and then assemble a team to create the corresponding schedule.

(True/False)
4.8/5
(38)

GANTT refers to the Generalized Activity Network Tracking Technique which was developed to better understand how variability in the duration of individual activities impacts the expected project duration.

(True/False)
4.9/5
(37)

All of the following strategies can help a project team to develop realistic time estimates for project activities EXCEPT:​ 

(Multiple Choice)
4.8/5
(44)

Many factors can impact the accuracy of activity duration estimates.Describe four of the problems associated with estimating activity durations accurately,and the techniques you could use as a project manager to overcome them.

(Essay)
4.8/5
(43)