Deck 9: Project Scheduling: Networks, Duration Estimation, and Critical Path

Full screen (f)
exit full mode
Question
Activities C,D,and E in the project represented by the network are to be hammocked.What is the activity length of the hammock activity?

A)20
B)16
C)13
D)11
Use Space or
up arrow
down arrow
to flip the card.
Question
These can be located by doing a backward pass through a network.

A)Critical paths
B)Merge activities
C)Successors
D)Burst activities
Question
Hammock activities allow:

A)Project managers to streamline the linkage and sequencing between activities.
B)Project workers to effectively skip nonessential activities without compromising project quality.
C)The project team to better disaggregate the overall project network into logical summaries.
D)The project manager to identify float more quickly and leverage it more successfully for the overall success of the project.
Question
Which of these statements about this network is BEST? <strong>Which of these statements about this network is BEST?  </strong> A)Activities A and B are serial activities. B)Activities B and C are serial activities. C)Activities A and C are serial activities. D)Activity D is a merge activity. <div style=padding-top: 35px>

A)Activities A and B are serial activities.
B)Activities B and C are serial activities.
C)Activities A and C are serial activities.
D)Activity D is a merge activity.
Question
Serial activities are those that:

A)Flow from one to the next in sequence.
B)Have sequential numbers.
C)Have the same numbers.
D)Should be performed simultaneously.
Question
What is the background of CPM and PERT? What are the differences between the two techniques?
Question
Concurrent activities are:

A)Activities that must be done one after the other.
B)Activities that can be performed at the same time.
C)Activities that use labor from the same group of workers.
D)Activities that use resources from the same resource pool.
Question
A sequence of activities defined by the project network logic is a(n):

A)Event.
B)Path.
C)Node.
D)Route.
Question
The overall effect of laddering activities is to:

A)Streamline the linkage and sequencing between activities and keep project resources fully employed.
B)Summarize some subsets of the activities identified in the overall project network.
C)Allow the project team to disaggregate the overall project network into logical summaries.
D)Allow the project manager to more fully deploy resources and complete the project with zero slack.
Question
<strong>  Network logic suggests that:</strong> A)Activity D can start any time. B)Activity A must be complete before Activity B can be done. C)Activities A,B and C must be complete before Activity D can be done. D)Activity C must begin before Activity B begins. <div style=padding-top: 35px> Network logic suggests that:

A)Activity D can start any time.
B)Activity A must be complete before Activity B can be done.
C)Activities A,B and C must be complete before Activity D can be done.
D)Activity C must begin before Activity B begins.
Question
Summaries for some subsets of the activities identified in the overall project network are called:

A)Ladder activities.
B)Hammock activities.
C)Negative float activities.
D)Compressed activities.
Question
Based on the activity network pictured,what is the BEST statement?

A)Before starting Activity C,Activity A and Activity B must be completed.
B)Before starting Activity D,Activity A and Activity B need to be completed.
C)Before starting Activity E,Activity A and Activity B need to be completed.
D)Before starting Activity C,Activity A and Activity D must be completed.
Question
Based on the activity network pictured,what is the BEST statement?

A)Activity C is a burst activity.
B)Activity E has one predecessor,Activity B.
C)Activity A and Activity C are merge activities.
D)There are no serial activities in this network.
Question
There's an old saying,"The job is not finished until the paperwork is done." From an activity network standpoint,this does not necessarily mean that the paperwork can't begin until the last non-paperwork activity is completed.It might be possible to work on some paperwork as early activities are completed.In order to depict this in an activity network:

A)Hammock activities could be drawn.
B)Subroutines could be added.
C)Shortcuts can be added to the network.
D)Laddering could be used to redraw the network.
Question
The term network logic means:

A)Tasks must either precede or follow other tasks in project planning and management.
B)Tasks cannot be performed unless the project manager issues a specific command to perform the work.
C)Prior project planning removes the need for any rush so that tasks can be performed in a methodical fashion.
D)Tasks are not performed unless the customer issues a specific request to perform the work.
Question
Activities C,D,and E in the project represented by the network are to be hammocked.What are the early start and late finish times of the hammock activity?

A)6,20
B)6,26
C)9,20
D)9,26
Question
A backward pass is performed when it is necessary to undo some work that has been performed in order to complete it properly.
Question
One of the defining points of a network,a junction point joined to some or all of the others by dependency lines,is called a(n):

A)Event.
B)Path.
C)Node.
D)Burst.
Question
Draw a network of any size that has at least one of each of the following features: merge activity,burst activity,hammock activity,ladder activity,critical path,serial activities,concurrent activities,and float.Mark these features on your network.
Question
An activity has an expected duration and an expected cost.Another name for an activity is a(n):

A)Work package.
B)Node.
C)Critical path.
D)Event.
Question
Preceding activities are those that must occur before others can be done.
Question
An activity has an optimistic time estimate of 25 days,a most likely estimate of 29 days,and a pessimistic estimate of 34 days.What is the expected duration of the activity?

A)Less than 31 days but greater than or equal to 29 days
B)Less than 29 days but greater than or equal to 27 days
C)Less than 27 days but greater than or equal to 25 days
D)Less than 25 days
Question
The length of time expected to complete an activity assuming that its development proceeds normally is called the:

A)Optimistic duration.
B)Pessimistic duration.
C)Most likely duration.
D)Normal duration.
Question
An activity has an optimistic time estimate of 17 days,a most likely estimate of 22 days,and a pessimistic estimate of 32 days.What is the expected duration of the activity?

A)22.83 days
B)23.67 days
C)24.33 days
D)25.17 days
Question
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project?  Activity  Length  Predecessor  A 10B18 A C14 A D20 B, C \begin{array} { | l | l | l | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 10 & -- \\\hline B & 18 & \text { A } \\\hline \mathrm { C } & 14 & \text { A } \\\hline \mathrm { D } & 20 & \text { B, C } \\\hline\end{array}

A)34
B)38
C)42
D)48
Question
At a merge point in a forward pass,the largest preceding early finish becomes the early start for that node.
Question
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project?  Activity  Length  Predecessor  A 10B18 A C14 A D20 B, C \begin{array} { | l | l | l | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 10 & -- \\\hline B & 18 & \text { A } \\\hline C & 14 & \text { A } \\\hline D & 20 & \text { B, C } \\\hline\end{array}

A)34
B)38
C)42
D)48
Question
The variance of an activity is given by:

A)[1/6(b-A)]².
B)1/6[b-a].
C)[1/36(b-a)]².
D)1/36[b-a].
Question
An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time.If the activity variance is 12,what is the expected time?

A)About 8 days
B)About 9 days
C)About 10 days
D)About 11 days
Question
Activity Z has estimates a = 5,b = 12,m = 7;activity X has estimates a = 5,b = 11,m = 6;and activity Y has estimates a = 3,b = 11,m = 8.Which of the following statements is BEST?

A)Activity X is longer than Activity Y.
B)Activity X has a higher standard deviation than Activity Z.
C)Activity Z is shorter than Activity Y.
D)Activity Y has a smaller variance than Activity Z.
Question
What does a network diagram illustrate and why are they important in project management?
Question
An activity has an optimistic time estimate of 17 days,a most likely estimate of 23 days,and a pessimistic estimate of 37 days.What is the variance of the activity?

A)3.33
B)6.66
C)9.99
D)11.11
Question
Prior to creating a network,it is important to:

A)Identify all loops through activities.
B)Identify the party responsible for each activity.
C)Calculate the float for each activity.
D)Understand the activity precedence.
Question
An activity has an optimistic time estimate of 12 days,a most likely estimate of 16 days,and a pessimistic estimate of 22 days.What is the expected standard deviation of the activity?

A)Between 1 and 2 days
B)Between 2 and 3 days
C)Between 3 and 4 days
D)Between 4 and 5 days
Question
What are hammock activities and when should they be used?
Question
Consider a project composed of activities X and Y having equal length and performed in that order.Both activities can be laddered such that the first half of each activity is the predecessor for its own second half,so X1 precedes X2 and Y1 precedes Y2.The first half of X1 is also the predecessor for Y1.If the laddering procedure were performed again activities X and Y would be divided in four parts each,with precedence working as it did in the first split.Derive an expression for the minimum length of the project as laddering increases.
Question
Ray's shipment of materials hit every red light and traffic jam on the way to the site.Upon arrival,half of the material was judged defective,necessitating a trip back to the supplier,and then the same arduous journey back to the site once the new materials were loaded.Traffic was a little better on the second round but the flat tire and subsequent repair caused as much if not more delay than the first trip.In the final analysis:

A)The project activity of Material Delivery was pretty close to the optimistic estimate.
B)The project activity of Material Delivery was pretty close to the most likely estimate.
C)The project activity of Material Delivery had a much higher variance than anticipated.
D)The project activity of Material Delivery was pretty close to the pessimistic estimate.
Question
Burst activities are those with two or more successor activities.
Question
A merge activity has two or more immediate predecessors.
Question
At a burst point in a backward pass,the largest succeeding late start becomes the late finish for that node.
Question
In assigning a value for the most pessimistic (b)duration,the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.
Question
What is the late start time for Activity E given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessar  A 5B7C8 AD7 AE4 BF8C,DG9E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessar } \\\hline \text { A } & 5 & - - \\\hline B & 7 & - - \\\hline \mathrm { C } & 8 & \mathrm {~A} \\\hline \mathrm { D } & 7 & \mathrm {~A} \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & \mathrm { 8 } & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & \mathrm { 9 } & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}

A)14
B)15
C)16
D)17
Question
Hammock activities break a task into greater levels of detail so that each task is represented as two or more subtasks that each have their own duration and precedence requirements.
Question
What is the early start time for Activity G given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessar  A 5B7C8 AD7 AE4 BF8C,DG9E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessar } \\\hline \text { A } & 5 & - - \\\hline B & 7 & - - \\\hline \mathrm { C } & 8 & \mathrm {~A} \\\hline \mathrm { D } & 7 & \mathrm {~A} \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & \mathrm { 8 } & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & \mathrm {9 } & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}

A)22
B)21
C)20
D)19
Question
Use the information in the table to determine the late start time for Activity E.  Early  Early  Late  Late  Task  Predecessor  Duration  Start  Firish  Start  Firish A8BA14CA238DC,B62326EC32FD,E3238\begin{array} { | l | l | l | l | l | l | l | } \hline & & & \text { Early } & \text { Early } & \text { Late } & \text { Late } \\ \text { Task } & \text { Predecessor } & \text { Duration } & \text { Start } & \text { Firish } & \text { Start } & \text { Firish } \\\hline \mathrm { A } & \mathrm { -- } & \mathbf { 8 } & & & & \\\hline \mathrm { B } & \mathrm { A } & & & & 14 & \\\hline \mathrm { C } & \mathrm { A } & & & \mathbf { 2 3 } & \mathbf { 8 } & \\\hline \mathrm { D } & \mathrm { C } , \mathrm { B } & 6 & \mathbf { 2 3 } & & \mathbf { 2 6 } & \\\hline \mathrm { E } & \mathrm { C } & & & \mathbf { 3 2 } & & \\\hline \mathrm { F } & \mathrm { D } , \mathrm { E } & & \mathbf { 3 2 } & & & \mathbf { 3 8 } \\\hline\end{array}

A)Day 23
B)Day 26
C)Day 32
D)Day 17
Question
The late start time should be calculated using a forward pass through the network.
Question
What is the early start time for Activity D given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor  A 5B6 A C4 A D5 B,C\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 5 & - - \\\hline B & 6 & \text { A } \\\hline \mathrm { C } & 4 & \text { A } \\\hline \mathrm { D } & 5 & \mathrm {~B} , \mathrm { C } \\\hline\end{array}

A)7
B)9
C)11
D)13
Question
<strong>  What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?</strong> A)Day 15 B)Day 7 C)Day 5 D)Day 3 <div style=padding-top: 35px> What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?

A)Day 15
B)Day 7
C)Day 5
D)Day 3
Question
Laddering is a technique that allows the project manager to redraw the network to more closely sequence project subtasks to make the overall network sequence more efficient.
Question
What is the late start time for Activity B given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor  A 5B6 A C4 A D5 B, C \begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 5 & -- \\\hline B & 6 & \text { A } \\\hline C & 4 & \text { A } \\\hline D & 5 & \text { B, C } \\\hline\end{array}

A)11
B)9
C)7
D)5
Question
Use the information in the table to determine the early start time for Activity B.  Early  Early  Late  Late  Task  Predecessor  Duration  Start  Firish  Start  Firish A8BA14CA238DC,B62326EC32FD,E3238\begin{array} { | l | l | l | l | l | l | l | } \hline & & & \text { Early } & \text { Early } & \text { Late } & \text { Late } \\ \text { Task } & \text { Predecessor } & \text { Duration } & \text { Start } & \text { Firish } & \text { Start } & \text { Firish } \\\hline \mathrm { A } & \mathrm { -- } & \mathbf { 8 } & & & & \\\hline \mathrm { B } & \mathrm { A } & & & & 14 & \\\hline \mathrm { C } & \mathrm { A } & & & \mathbf { 2 3 } & \mathbf { 8 } & \\\hline \mathrm { D } & \mathrm { C } , \mathrm { B } & 6 & \mathbf { 2 3 } & & \mathbf { 2 6 } & \\\hline \mathrm { E } & \mathrm { C } & & & \mathbf { 3 2 } & & \\\hline \mathrm { F } & \mathrm { D } , \mathrm { E } & & \mathbf { 3 2 } & & & \mathbf { 3 8 } \\\hline\end{array}

A)Day 10
B)Day 8
C)Day 9
D)Day 11
Question
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the expected completion time of the project?  Optimistic Most Likely  Pessimistic  Activity  time  time  time  Predecessor  Corner Posts 456 String Line 789 Dig Holes 101214 Corner Posts  Plant Posts 111417 String Line  Weld Top Bar 81114 String Line  Dig Holes, Plant  Paint 91113 Posts  Tack Wire 91216 Weld Top Bar \begin{array}{|l|l|l|l|l|}\hline&\text { Optimistic} & \text { Most Likely } & \text { Pessimistic }\\ \text { Activity } & \text { time } & \text { time } & \text { time } & \text { Predecessor }\\ \hline \text { Corner Posts } & 4 & 5 & 6 & - \\\hline \text { String Line } & 7 & 8 & 9 & -- \\\hline \text { Dig Holes } & 10 & 12 & 14 & \text { Corner Posts } \\\hline \text { Plant Posts } & 11 & 14 & 17 & \text { String Line } \\\hline \text { Weld Top Bar } & 8 & 11 & 14 & \text { String Line } \\\hline & & & & \text { Dig Holes, Plant } \\ \text { Paint } & 9 & 11 & 13 & \text { Posts } \\\hline \text { Tack Wire } & 9 &12& 16& \text { Weld Top Bar }\\\hline\end{array}

A)32 days
B)33 days
C)34 days
D)35 days
Question
What are three methods of duration estimation for project activities and what are the advantages and disadvantages of each method?
Question
You must know the mean of an activity in order to determine its standard deviation.
Question
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?  <div style=padding-top: 35px>
Question
What is the underlying theory to the three time estimates approach? What data distribution should be applied in this case and what confidence should a project manager place in the calculations associated with this technique?
Question
What is the early finish time for Activity F given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor  A 5B7C8 A D7 A E4 BF8C,DG9E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 5 & -- \\\hline B & 7 & -- \\\hline \mathrm { C } & 8 & \text { A } \\\hline \mathrm { D } & 7 & \text { A } \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & 8 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & \mathrm { 9 } & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}

A)15
B)17
C)19
D)21
Question
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the standard deviation of the project's critical path?  Optimistic Most Likely  Pessimistic  Activity  time  time  time  Predecessor  Corner Posts 456 String Line 789 Dig Holes 101214 Corner Posts  Plant Posts 111417 String Line  Weld Top Bar 81114 String Line  Dig Holes, Plant  Paint 91113 Posts  Tack Wire 91216 Weld Top Bar \begin{array}{|l|l|l|l|l|}\hline&\text { Optimistic} & \text { Most Likely } & \text { Pessimistic }\\ \text { Activity } & \text { time } & \text { time } & \text { time } & \text { Predecessor }\\ \hline \text { Corner Posts } & 4 & 5 & 6 & - \\\hline \text { String Line } & 7 & 8 & 9 & -- \\\hline \text { Dig Holes } & 10 & 12 & 14 & \text { Corner Posts } \\\hline \text { Plant Posts } & 11 & 14 & 17 & \text { String Line } \\\hline \text { Weld Top Bar } & 8 & 11 & 14 & \text { String Line } \\\hline & & & & \text { Dig Holes, Plant } \\ \text { Paint } & 9 & 11 & 13 & \text { Posts } \\\hline \text { Tack Wire } & 9 &12& 16& \text { Weld Top Bar } \\\hline\end{array}


A)1.33 days
B)1.56 days
C)1.25 days
D)1.75 days
Question
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?  <div style=padding-top: 35px>
Question
What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor  A 5B7C8 A D7 A E4 BF8C,DG9E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 5 & -- \\\hline B & 7 & -- \\\hline \mathrm { C } & 8 & \text { A } \\\hline \mathrm { D } & 7 & \text { A } \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & 8 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & \mathrm { 9 } & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}

A)14
B)13
C)12
D)11
Question
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities H and I can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity?  Tirne  Predecessor A7B8 AC13 BD8CE7 AF6EG6 AH11GI12HJ14D,F,I\begin{array} { | l | l | l | } \hline & \text { Tirne } & \text { Predecessor } \\\hline \mathrm { A } & 7 & \\\hline B & 8 & \mathrm {~A} \\\hline \mathrm { C } & 13 & \mathrm {~B} \\\hline \mathrm { D } & 8 & \mathrm { C } \\\hline \mathrm { E } & 7 & \mathrm {~A} \\\hline \mathrm { F } & \mathrm { 6 } & \mathrm { E } \\\hline \mathrm { G } & 6 & \mathrm {~A} \\\hline \mathrm { H } & 11 & \mathrm { G } \\\hline \mathrm { I } & 12 & \mathrm { H } \\\hline \mathrm { J } & 14 & \mathrm { D } , \mathrm { F } , \mathrm { I } \\\hline\end{array}

A)13,36
B)13,24
C)24,36
D)7,36
Question
What is the slack time for Activity D given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor A5B7C8 A D7 AE4 BF8C,DG9E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \mathrm { A } & 5 & - - \\\hline \mathrm {B} & 7 &- - \\\hline \mathrm { C } & 8 & \text { A } \\\hline \mathrm { D } & 7 & \mathrm {~A} \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & 8 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & 9 & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}

A)2
B)1
C)0
D)3
Question
Use the network diagram and activity lengths in the nodes to determine the late start time for activity F.

A)21
B)24
C)26
D)23
Question
What is the slack time for Activity B given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor A5B7C8 A D7 AE4 BF8C,DG9E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \mathrm { A } & 5 & - - \\\hline \mathrm {B} & 7 &- - \\\hline \mathrm { C } & 8 & \text { A } \\\hline \mathrm { D } & 7 & \mathrm {~A} \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & 8 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & 9 & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}

A)10
B)9
C)8
D)7
Question
Phoebe B.Beebee is constructing a canal for the annual canoe races and has identified eleven activities that are required to complete this important project.She calculated early and late start times and early and late finish times but spilled coffee all over her printout.Use the remaining information to reconstruct the table for Phoebe B.Beebee and her new canoe canal.
 Early  Late  Activity  Predecessor  Length  Early Start  Late Start  Finish  Finish A12BBA20DB,E42EC2842FE4250GD5353HG70IG72TF4KH,I,J8191\begin{array}{|l|l|l|l|l|l|l|l|}\hline & & & & & \text { Early } & \text { Late } \\\text { Activity } & \text { Predecessor } & \text { Length } & \text { Early Start } & \text { Late Start } & \text { Finish } & \text { Finish } \\\hline\mathrm{A} &&&&&12&\\\hline \mathrm{B} & -- & & & & & & \\\hline \mathrm{B} & \mathrm{A} &20 & & & & & \\\hline \mathrm{D} & \mathrm{B}, \mathrm{E} & & & 42 & & \\\hline \mathrm{E} & \mathrm{C} & & 28 & & & 42 \\\hline \mathrm{F} & \mathrm{E} & & 42 & & 50 & \\\hline \mathrm{G} & \mathrm{D} & & 53 & 53 & & \\\hline \mathrm{H} & \mathrm{G} & & 70 & & & \\\hline \mathrm{I} & \mathrm{G} & & & 72 & & \\\hline \mathrm{T} & \mathrm{F} & 4 & & & & \\\hline \mathrm{K} & \mathrm{H}, \mathrm{I}, \mathrm{J} & & & 81 & & 91 \\\hline\end{array}
Question
Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.

A)12
B)13
C)14
D)15
Question
Use the information in the table to determine the late finish time for Activity B.  Early  Early  Late  Late  Task  Predecessor  Duration  Start  Firish  Start  Firish A8BA14CA238DC,B62326EC32FD,E3238\begin{array} { | l | l | l | l | l | l | l | } \hline & & & \text { Early } & \text { Early } & \text { Late } & \text { Late } \\ \text { Task } & \text { Predecessor } & \text { Duration } & \text { Start } & \text { Firish } & \text { Start } & \text { Firish } \\\hline \mathrm { A } & \mathrm { -- } & \mathbf { 8 } & & & & \\\hline \mathrm { B } & \mathrm { A } & & & & 14 & \\\hline \mathrm { C } & \mathrm { A } & & & \mathbf { 2 3 } & \mathbf { 8 } & \\\hline \mathrm { D } & \mathrm { C } , \mathrm { B } & 6 & \mathbf { 2 3 } & & \mathbf { 2 6 } & \\\hline \mathrm { E } & \mathrm { C } & & & \mathbf { 3 2 } & & \\\hline \mathrm { F } & \mathrm { D } , \mathrm { E } & & \mathbf { 3 2 } & & & \mathbf { 3 8 } \\\hline\end{array}

A)Day 17
B)Day 20
C)Day 23
D)Day 26
Question
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the late finish for the Plant Posts activity?  Optimistic Most Likely  Pessimistic  Activity  time  time  time  Predecessor  Corner Posts 456 String Line 789 Dig Holes 101214 Corner Posts  Plant Posts 111417 String Line  Weld Top Bar 81114 String Line  Dig Holes, Plant  Paint 91113 Posts  Tack Wire 91216 Weld Top Bar \begin{array}{|l|l|l|l|l|}\hline&\text { Optimistic} & \text { Most Likely } & \text { Pessimistic }\\ \text { Activity } & \text { time } & \text { time } & \text { time } & \text { Predecessor }\\ \hline \text { Corner Posts } & 4 & 5 & 6 & - \\\hline \text { String Line } & 7 & 8 & 9 & -- \\\hline \text { Dig Holes } & 10 & 12 & 14 & \text { Corner Posts } \\\hline \text { Plant Posts } & 11 & 14 & 17 & \text { String Line } \\\hline \text { Weld Top Bar } & 8 & 11 & 14 & \text { String Line } \\\hline & & & & \text { Dig Holes, Plant } \\ \text { Paint } & 9 & 11 & 13 & \text { Posts } \\\hline \text { Tack Wire } & 9 &12& 16& \text { Weld Top Bar } \\\hline\end{array}



A)13.3 days
B)8 days
C)20.83 days
D)22 days
Question
Compute early and late start and finish times for the network shown.
Compute early and late start and finish times for the network shown.  <div style=padding-top: 35px>
Question
The amount of time an activity may be delayed from its early start without delaying the finish of the project is the:

A)Delay.
B)Float.
C)Late start.
D)Late finish.
Question
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration,so activity C in the original project becomes two activities,C1 and C2,each of which lasts 7 days.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the difference in the late start time for activity C in the original project and activity C1 in the laddered project?  Activity  Length  Predecessor  A 10B18 A C14 A D20 B, C \begin{array} { | l | l | l | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 10 & -- \\\hline B & 18 & \text { A } \\\hline \mathrm { C } & 14 & \text { A } \\\hline \mathrm { D } & 20 & \text { B, C } \\\hline\end{array}

A)3
B)5
C)7
D)9
Question
Construct a network using the information in the table and identify the critical path.
 Activity  Time  Predecessor  A 4B6 A C9 A D11 BE16 B,CF4DG8E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 4 & \\\hline B & 6 & \text { A } \\\hline \mathrm { C } & 9 & \text { A } \\\hline \mathrm { D } & 11 & \mathrm {~B} \\\hline \mathrm { E } & 16 & \mathrm {~B} , \mathrm { C } \\\hline \mathrm { F } & 4 & \mathrm { D } \\\hline \mathrm { G } & \mathrm { 8 } & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & \mathrm { 7 } & \mathrm { G } \\\hline\end{array}
Question
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities B,C,and D can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity?  Tirne  Predecessor A7B8 AC13 BD8CE7 AF6EG6 AH11GI12HJ14D,F,I\begin{array} { | l | l | l | } \hline & \text { Tirne } & \text { Predecessor } \\\hline \mathrm { A } & 7 & \\\hline B & 8 & \mathrm {~A} \\\hline \mathrm { C } & 13 & \mathrm {~B} \\\hline \mathrm { D } & 8 & \mathrm { C } \\\hline \mathrm { E } & 7 & \mathrm {~A} \\\hline \mathrm { F } & \mathrm { 6 } & \mathrm { E } \\\hline \mathrm { G } & 6 & \mathrm {~A} \\\hline \mathrm { H } & 11 & \mathrm { G } \\\hline \mathrm { I } & 12 & \mathrm { H } \\\hline \mathrm { J } & 14 & \mathrm { D } , \mathrm { F } , \mathrm { I } \\\hline\end{array}

A)11,30
B)7,24
C)11,24
D)7,36
Question
Use the information in the table to sketch the network and compute early and late start times.
 Activity  Time  Predecessor A8B4 A C5 B, FD12 AE8DF4DG9E,F\begin{array} { | l | l | l |} \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \mathrm { A } & 8 & \\\hline\mathrm { B} & 4 & \text { A } \\\hline \mathrm { C } & 5 & \mathrm {~B} , \mathrm {~F} \\\hline \mathrm { D } & 12 & \mathrm {~A} \\\hline \mathrm { E } & 8 & \mathrm { D } \\\hline \mathrm { F } & 4 & \mathrm { D } \\\hline \mathrm { G } & 9 & \mathrm { E } , \mathrm { F } \\\hline\end{array}
Question
The least amount of float is found:

A)In a resource-limited schedule.
B)After a burst activity.
C)On the critical path.
D)After a merge activity.
Question
Use the information in the table to determine the early finish time for Activity D.  Early  Early  Late  Late  Task  Predecessor  Duration  Start  Firish  Start  Firish A8BA14CA238DC,B62326EC32FD,E3238\begin{array} { | l | l | l | l | l | l | l | } \hline & & & \text { Early } & \text { Early } & \text { Late } & \text { Late } \\ \text { Task } & \text { Predecessor } & \text { Duration } & \text { Start } & \text { Firish } & \text { Start } & \text { Firish } \\\hline \mathrm { A } & \mathrm { -- } & \mathbf { 8 } & & & & \\\hline \mathrm { B } & \mathrm { A } & & & & 14 & \\\hline \mathrm { C } & \mathrm { A } & & & \mathbf { 2 3 } & \mathbf { 8 } & \\\hline \mathrm { D } & \mathrm { C } , \mathrm { B } & 6 & \mathbf { 2 3 } & & \mathbf { 2 6 } & \\\hline \mathrm { E } & \mathrm { C } & & & \mathbf { 3 2 } & & \\\hline \mathrm { F } & \mathrm { D } , \mathrm { E } & & \mathbf { 3 2 } & & & \mathbf { 3 8 } \\\hline\end{array}

A)Day 23
B)Day 26
C)Day 29
D)Day 32
Question
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.

A)8
B)13
C)14
D)21
Question
Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G.

A)26
B)25
C)24
D)23
Question
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.

A)8
B)13
C)14
D)21
Question
Use the information in the table to sketch the network and compute early and late start times.
 Activity  Time  Predecessor  A 8B4AC5B, FD12 AE8DF4DG9E, FH12GI6C,GJ5IK9HF12 J, K\begin{array} { | l | l | l |} \hline\text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 8 & \\\hline \mathrm{B }& 4 & \mathrm{A} \\\hline \mathrm { C } & 5 & \mathrm { B }, \mathrm {~F} \\\hline \mathrm { D } & 12 & \mathrm {~A} \\\hline \mathrm { E } & 8 & \mathrm { D } \\\hline \mathrm { F } & 4 & \mathrm { D } \\\hline \mathrm { G } & 9 & \mathrm { E } , \mathrm {~F} \\\hline \mathrm { H } & 12 & \mathrm { G } \\\hline \mathrm { I } & 6 & \mathrm { C } , \mathrm { G } \\\hline \mathrm { J } & 5 & \mathrm { I } \\\hline \mathrm { K } & 9 & \mathrm { H } \\\hline \mathrm { F } & 12 & \mathrm {~J} , \mathrm {~K} \\\hline\end{array}
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/105
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
1
Activities C,D,and E in the project represented by the network are to be hammocked.What is the activity length of the hammock activity?

A)20
B)16
C)13
D)11
A
2
These can be located by doing a backward pass through a network.

A)Critical paths
B)Merge activities
C)Successors
D)Burst activities
D
3
Hammock activities allow:

A)Project managers to streamline the linkage and sequencing between activities.
B)Project workers to effectively skip nonessential activities without compromising project quality.
C)The project team to better disaggregate the overall project network into logical summaries.
D)The project manager to identify float more quickly and leverage it more successfully for the overall success of the project.
C
4
Which of these statements about this network is BEST? <strong>Which of these statements about this network is BEST?  </strong> A)Activities A and B are serial activities. B)Activities B and C are serial activities. C)Activities A and C are serial activities. D)Activity D is a merge activity.

A)Activities A and B are serial activities.
B)Activities B and C are serial activities.
C)Activities A and C are serial activities.
D)Activity D is a merge activity.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
5
Serial activities are those that:

A)Flow from one to the next in sequence.
B)Have sequential numbers.
C)Have the same numbers.
D)Should be performed simultaneously.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
6
What is the background of CPM and PERT? What are the differences between the two techniques?
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
7
Concurrent activities are:

A)Activities that must be done one after the other.
B)Activities that can be performed at the same time.
C)Activities that use labor from the same group of workers.
D)Activities that use resources from the same resource pool.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
8
A sequence of activities defined by the project network logic is a(n):

A)Event.
B)Path.
C)Node.
D)Route.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
9
The overall effect of laddering activities is to:

A)Streamline the linkage and sequencing between activities and keep project resources fully employed.
B)Summarize some subsets of the activities identified in the overall project network.
C)Allow the project team to disaggregate the overall project network into logical summaries.
D)Allow the project manager to more fully deploy resources and complete the project with zero slack.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
10
<strong>  Network logic suggests that:</strong> A)Activity D can start any time. B)Activity A must be complete before Activity B can be done. C)Activities A,B and C must be complete before Activity D can be done. D)Activity C must begin before Activity B begins. Network logic suggests that:

A)Activity D can start any time.
B)Activity A must be complete before Activity B can be done.
C)Activities A,B and C must be complete before Activity D can be done.
D)Activity C must begin before Activity B begins.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
11
Summaries for some subsets of the activities identified in the overall project network are called:

A)Ladder activities.
B)Hammock activities.
C)Negative float activities.
D)Compressed activities.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
12
Based on the activity network pictured,what is the BEST statement?

A)Before starting Activity C,Activity A and Activity B must be completed.
B)Before starting Activity D,Activity A and Activity B need to be completed.
C)Before starting Activity E,Activity A and Activity B need to be completed.
D)Before starting Activity C,Activity A and Activity D must be completed.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
13
Based on the activity network pictured,what is the BEST statement?

A)Activity C is a burst activity.
B)Activity E has one predecessor,Activity B.
C)Activity A and Activity C are merge activities.
D)There are no serial activities in this network.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
14
There's an old saying,"The job is not finished until the paperwork is done." From an activity network standpoint,this does not necessarily mean that the paperwork can't begin until the last non-paperwork activity is completed.It might be possible to work on some paperwork as early activities are completed.In order to depict this in an activity network:

A)Hammock activities could be drawn.
B)Subroutines could be added.
C)Shortcuts can be added to the network.
D)Laddering could be used to redraw the network.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
15
The term network logic means:

A)Tasks must either precede or follow other tasks in project planning and management.
B)Tasks cannot be performed unless the project manager issues a specific command to perform the work.
C)Prior project planning removes the need for any rush so that tasks can be performed in a methodical fashion.
D)Tasks are not performed unless the customer issues a specific request to perform the work.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
16
Activities C,D,and E in the project represented by the network are to be hammocked.What are the early start and late finish times of the hammock activity?

A)6,20
B)6,26
C)9,20
D)9,26
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
17
A backward pass is performed when it is necessary to undo some work that has been performed in order to complete it properly.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
18
One of the defining points of a network,a junction point joined to some or all of the others by dependency lines,is called a(n):

A)Event.
B)Path.
C)Node.
D)Burst.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
19
Draw a network of any size that has at least one of each of the following features: merge activity,burst activity,hammock activity,ladder activity,critical path,serial activities,concurrent activities,and float.Mark these features on your network.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
20
An activity has an expected duration and an expected cost.Another name for an activity is a(n):

A)Work package.
B)Node.
C)Critical path.
D)Event.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
21
Preceding activities are those that must occur before others can be done.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
22
An activity has an optimistic time estimate of 25 days,a most likely estimate of 29 days,and a pessimistic estimate of 34 days.What is the expected duration of the activity?

A)Less than 31 days but greater than or equal to 29 days
B)Less than 29 days but greater than or equal to 27 days
C)Less than 27 days but greater than or equal to 25 days
D)Less than 25 days
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
23
The length of time expected to complete an activity assuming that its development proceeds normally is called the:

A)Optimistic duration.
B)Pessimistic duration.
C)Most likely duration.
D)Normal duration.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
24
An activity has an optimistic time estimate of 17 days,a most likely estimate of 22 days,and a pessimistic estimate of 32 days.What is the expected duration of the activity?

A)22.83 days
B)23.67 days
C)24.33 days
D)25.17 days
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
25
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project?  Activity  Length  Predecessor  A 10B18 A C14 A D20 B, C \begin{array} { | l | l | l | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 10 & -- \\\hline B & 18 & \text { A } \\\hline \mathrm { C } & 14 & \text { A } \\\hline \mathrm { D } & 20 & \text { B, C } \\\hline\end{array}

A)34
B)38
C)42
D)48
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
26
At a merge point in a forward pass,the largest preceding early finish becomes the early start for that node.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
27
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project?  Activity  Length  Predecessor  A 10B18 A C14 A D20 B, C \begin{array} { | l | l | l | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 10 & -- \\\hline B & 18 & \text { A } \\\hline C & 14 & \text { A } \\\hline D & 20 & \text { B, C } \\\hline\end{array}

A)34
B)38
C)42
D)48
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
28
The variance of an activity is given by:

A)[1/6(b-A)]².
B)1/6[b-a].
C)[1/36(b-a)]².
D)1/36[b-a].
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
29
An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time.If the activity variance is 12,what is the expected time?

A)About 8 days
B)About 9 days
C)About 10 days
D)About 11 days
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
30
Activity Z has estimates a = 5,b = 12,m = 7;activity X has estimates a = 5,b = 11,m = 6;and activity Y has estimates a = 3,b = 11,m = 8.Which of the following statements is BEST?

A)Activity X is longer than Activity Y.
B)Activity X has a higher standard deviation than Activity Z.
C)Activity Z is shorter than Activity Y.
D)Activity Y has a smaller variance than Activity Z.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
31
What does a network diagram illustrate and why are they important in project management?
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
32
An activity has an optimistic time estimate of 17 days,a most likely estimate of 23 days,and a pessimistic estimate of 37 days.What is the variance of the activity?

A)3.33
B)6.66
C)9.99
D)11.11
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
33
Prior to creating a network,it is important to:

A)Identify all loops through activities.
B)Identify the party responsible for each activity.
C)Calculate the float for each activity.
D)Understand the activity precedence.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
34
An activity has an optimistic time estimate of 12 days,a most likely estimate of 16 days,and a pessimistic estimate of 22 days.What is the expected standard deviation of the activity?

A)Between 1 and 2 days
B)Between 2 and 3 days
C)Between 3 and 4 days
D)Between 4 and 5 days
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
35
What are hammock activities and when should they be used?
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
36
Consider a project composed of activities X and Y having equal length and performed in that order.Both activities can be laddered such that the first half of each activity is the predecessor for its own second half,so X1 precedes X2 and Y1 precedes Y2.The first half of X1 is also the predecessor for Y1.If the laddering procedure were performed again activities X and Y would be divided in four parts each,with precedence working as it did in the first split.Derive an expression for the minimum length of the project as laddering increases.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
37
Ray's shipment of materials hit every red light and traffic jam on the way to the site.Upon arrival,half of the material was judged defective,necessitating a trip back to the supplier,and then the same arduous journey back to the site once the new materials were loaded.Traffic was a little better on the second round but the flat tire and subsequent repair caused as much if not more delay than the first trip.In the final analysis:

A)The project activity of Material Delivery was pretty close to the optimistic estimate.
B)The project activity of Material Delivery was pretty close to the most likely estimate.
C)The project activity of Material Delivery had a much higher variance than anticipated.
D)The project activity of Material Delivery was pretty close to the pessimistic estimate.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
38
Burst activities are those with two or more successor activities.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
39
A merge activity has two or more immediate predecessors.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
40
At a burst point in a backward pass,the largest succeeding late start becomes the late finish for that node.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
41
In assigning a value for the most pessimistic (b)duration,the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
42
What is the late start time for Activity E given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessar  A 5B7C8 AD7 AE4 BF8C,DG9E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessar } \\\hline \text { A } & 5 & - - \\\hline B & 7 & - - \\\hline \mathrm { C } & 8 & \mathrm {~A} \\\hline \mathrm { D } & 7 & \mathrm {~A} \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & \mathrm { 8 } & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & \mathrm { 9 } & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}

A)14
B)15
C)16
D)17
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
43
Hammock activities break a task into greater levels of detail so that each task is represented as two or more subtasks that each have their own duration and precedence requirements.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
44
What is the early start time for Activity G given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessar  A 5B7C8 AD7 AE4 BF8C,DG9E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessar } \\\hline \text { A } & 5 & - - \\\hline B & 7 & - - \\\hline \mathrm { C } & 8 & \mathrm {~A} \\\hline \mathrm { D } & 7 & \mathrm {~A} \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & \mathrm { 8 } & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & \mathrm {9 } & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}

A)22
B)21
C)20
D)19
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
45
Use the information in the table to determine the late start time for Activity E.  Early  Early  Late  Late  Task  Predecessor  Duration  Start  Firish  Start  Firish A8BA14CA238DC,B62326EC32FD,E3238\begin{array} { | l | l | l | l | l | l | l | } \hline & & & \text { Early } & \text { Early } & \text { Late } & \text { Late } \\ \text { Task } & \text { Predecessor } & \text { Duration } & \text { Start } & \text { Firish } & \text { Start } & \text { Firish } \\\hline \mathrm { A } & \mathrm { -- } & \mathbf { 8 } & & & & \\\hline \mathrm { B } & \mathrm { A } & & & & 14 & \\\hline \mathrm { C } & \mathrm { A } & & & \mathbf { 2 3 } & \mathbf { 8 } & \\\hline \mathrm { D } & \mathrm { C } , \mathrm { B } & 6 & \mathbf { 2 3 } & & \mathbf { 2 6 } & \\\hline \mathrm { E } & \mathrm { C } & & & \mathbf { 3 2 } & & \\\hline \mathrm { F } & \mathrm { D } , \mathrm { E } & & \mathbf { 3 2 } & & & \mathbf { 3 8 } \\\hline\end{array}

A)Day 23
B)Day 26
C)Day 32
D)Day 17
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
46
The late start time should be calculated using a forward pass through the network.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
47
What is the early start time for Activity D given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor  A 5B6 A C4 A D5 B,C\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 5 & - - \\\hline B & 6 & \text { A } \\\hline \mathrm { C } & 4 & \text { A } \\\hline \mathrm { D } & 5 & \mathrm {~B} , \mathrm { C } \\\hline\end{array}

A)7
B)9
C)11
D)13
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
48
<strong>  What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?</strong> A)Day 15 B)Day 7 C)Day 5 D)Day 3 What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?

A)Day 15
B)Day 7
C)Day 5
D)Day 3
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
49
Laddering is a technique that allows the project manager to redraw the network to more closely sequence project subtasks to make the overall network sequence more efficient.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
50
What is the late start time for Activity B given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor  A 5B6 A C4 A D5 B, C \begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 5 & -- \\\hline B & 6 & \text { A } \\\hline C & 4 & \text { A } \\\hline D & 5 & \text { B, C } \\\hline\end{array}

A)11
B)9
C)7
D)5
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
51
Use the information in the table to determine the early start time for Activity B.  Early  Early  Late  Late  Task  Predecessor  Duration  Start  Firish  Start  Firish A8BA14CA238DC,B62326EC32FD,E3238\begin{array} { | l | l | l | l | l | l | l | } \hline & & & \text { Early } & \text { Early } & \text { Late } & \text { Late } \\ \text { Task } & \text { Predecessor } & \text { Duration } & \text { Start } & \text { Firish } & \text { Start } & \text { Firish } \\\hline \mathrm { A } & \mathrm { -- } & \mathbf { 8 } & & & & \\\hline \mathrm { B } & \mathrm { A } & & & & 14 & \\\hline \mathrm { C } & \mathrm { A } & & & \mathbf { 2 3 } & \mathbf { 8 } & \\\hline \mathrm { D } & \mathrm { C } , \mathrm { B } & 6 & \mathbf { 2 3 } & & \mathbf { 2 6 } & \\\hline \mathrm { E } & \mathrm { C } & & & \mathbf { 3 2 } & & \\\hline \mathrm { F } & \mathrm { D } , \mathrm { E } & & \mathbf { 3 2 } & & & \mathbf { 3 8 } \\\hline\end{array}

A)Day 10
B)Day 8
C)Day 9
D)Day 11
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
52
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the expected completion time of the project?  Optimistic Most Likely  Pessimistic  Activity  time  time  time  Predecessor  Corner Posts 456 String Line 789 Dig Holes 101214 Corner Posts  Plant Posts 111417 String Line  Weld Top Bar 81114 String Line  Dig Holes, Plant  Paint 91113 Posts  Tack Wire 91216 Weld Top Bar \begin{array}{|l|l|l|l|l|}\hline&\text { Optimistic} & \text { Most Likely } & \text { Pessimistic }\\ \text { Activity } & \text { time } & \text { time } & \text { time } & \text { Predecessor }\\ \hline \text { Corner Posts } & 4 & 5 & 6 & - \\\hline \text { String Line } & 7 & 8 & 9 & -- \\\hline \text { Dig Holes } & 10 & 12 & 14 & \text { Corner Posts } \\\hline \text { Plant Posts } & 11 & 14 & 17 & \text { String Line } \\\hline \text { Weld Top Bar } & 8 & 11 & 14 & \text { String Line } \\\hline & & & & \text { Dig Holes, Plant } \\ \text { Paint } & 9 & 11 & 13 & \text { Posts } \\\hline \text { Tack Wire } & 9 &12& 16& \text { Weld Top Bar }\\\hline\end{array}

A)32 days
B)33 days
C)34 days
D)35 days
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
53
What are three methods of duration estimation for project activities and what are the advantages and disadvantages of each method?
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
54
You must know the mean of an activity in order to determine its standard deviation.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
55
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
56
What is the underlying theory to the three time estimates approach? What data distribution should be applied in this case and what confidence should a project manager place in the calculations associated with this technique?
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
57
What is the early finish time for Activity F given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor  A 5B7C8 A D7 A E4 BF8C,DG9E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 5 & -- \\\hline B & 7 & -- \\\hline \mathrm { C } & 8 & \text { A } \\\hline \mathrm { D } & 7 & \text { A } \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & 8 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & \mathrm { 9 } & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}

A)15
B)17
C)19
D)21
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
58
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the standard deviation of the project's critical path?  Optimistic Most Likely  Pessimistic  Activity  time  time  time  Predecessor  Corner Posts 456 String Line 789 Dig Holes 101214 Corner Posts  Plant Posts 111417 String Line  Weld Top Bar 81114 String Line  Dig Holes, Plant  Paint 91113 Posts  Tack Wire 91216 Weld Top Bar \begin{array}{|l|l|l|l|l|}\hline&\text { Optimistic} & \text { Most Likely } & \text { Pessimistic }\\ \text { Activity } & \text { time } & \text { time } & \text { time } & \text { Predecessor }\\ \hline \text { Corner Posts } & 4 & 5 & 6 & - \\\hline \text { String Line } & 7 & 8 & 9 & -- \\\hline \text { Dig Holes } & 10 & 12 & 14 & \text { Corner Posts } \\\hline \text { Plant Posts } & 11 & 14 & 17 & \text { String Line } \\\hline \text { Weld Top Bar } & 8 & 11 & 14 & \text { String Line } \\\hline & & & & \text { Dig Holes, Plant } \\ \text { Paint } & 9 & 11 & 13 & \text { Posts } \\\hline \text { Tack Wire } & 9 &12& 16& \text { Weld Top Bar } \\\hline\end{array}


A)1.33 days
B)1.56 days
C)1.25 days
D)1.75 days
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
59
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
60
What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor  A 5B7C8 A D7 A E4 BF8C,DG9E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 5 & -- \\\hline B & 7 & -- \\\hline \mathrm { C } & 8 & \text { A } \\\hline \mathrm { D } & 7 & \text { A } \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & 8 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & \mathrm { 9 } & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}

A)14
B)13
C)12
D)11
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
61
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities H and I can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity?  Tirne  Predecessor A7B8 AC13 BD8CE7 AF6EG6 AH11GI12HJ14D,F,I\begin{array} { | l | l | l | } \hline & \text { Tirne } & \text { Predecessor } \\\hline \mathrm { A } & 7 & \\\hline B & 8 & \mathrm {~A} \\\hline \mathrm { C } & 13 & \mathrm {~B} \\\hline \mathrm { D } & 8 & \mathrm { C } \\\hline \mathrm { E } & 7 & \mathrm {~A} \\\hline \mathrm { F } & \mathrm { 6 } & \mathrm { E } \\\hline \mathrm { G } & 6 & \mathrm {~A} \\\hline \mathrm { H } & 11 & \mathrm { G } \\\hline \mathrm { I } & 12 & \mathrm { H } \\\hline \mathrm { J } & 14 & \mathrm { D } , \mathrm { F } , \mathrm { I } \\\hline\end{array}

A)13,36
B)13,24
C)24,36
D)7,36
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
62
What is the slack time for Activity D given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor A5B7C8 A D7 AE4 BF8C,DG9E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \mathrm { A } & 5 & - - \\\hline \mathrm {B} & 7 &- - \\\hline \mathrm { C } & 8 & \text { A } \\\hline \mathrm { D } & 7 & \mathrm {~A} \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & 8 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & 9 & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}

A)2
B)1
C)0
D)3
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
63
Use the network diagram and activity lengths in the nodes to determine the late start time for activity F.

A)21
B)24
C)26
D)23
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
64
What is the slack time for Activity B given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor A5B7C8 A D7 AE4 BF8C,DG9E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \mathrm { A } & 5 & - - \\\hline \mathrm {B} & 7 &- - \\\hline \mathrm { C } & 8 & \text { A } \\\hline \mathrm { D } & 7 & \mathrm {~A} \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & 8 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & 9 & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}

A)10
B)9
C)8
D)7
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
65
Phoebe B.Beebee is constructing a canal for the annual canoe races and has identified eleven activities that are required to complete this important project.She calculated early and late start times and early and late finish times but spilled coffee all over her printout.Use the remaining information to reconstruct the table for Phoebe B.Beebee and her new canoe canal.
 Early  Late  Activity  Predecessor  Length  Early Start  Late Start  Finish  Finish A12BBA20DB,E42EC2842FE4250GD5353HG70IG72TF4KH,I,J8191\begin{array}{|l|l|l|l|l|l|l|l|}\hline & & & & & \text { Early } & \text { Late } \\\text { Activity } & \text { Predecessor } & \text { Length } & \text { Early Start } & \text { Late Start } & \text { Finish } & \text { Finish } \\\hline\mathrm{A} &&&&&12&\\\hline \mathrm{B} & -- & & & & & & \\\hline \mathrm{B} & \mathrm{A} &20 & & & & & \\\hline \mathrm{D} & \mathrm{B}, \mathrm{E} & & & 42 & & \\\hline \mathrm{E} & \mathrm{C} & & 28 & & & 42 \\\hline \mathrm{F} & \mathrm{E} & & 42 & & 50 & \\\hline \mathrm{G} & \mathrm{D} & & 53 & 53 & & \\\hline \mathrm{H} & \mathrm{G} & & 70 & & & \\\hline \mathrm{I} & \mathrm{G} & & & 72 & & \\\hline \mathrm{T} & \mathrm{F} & 4 & & & & \\\hline \mathrm{K} & \mathrm{H}, \mathrm{I}, \mathrm{J} & & & 81 & & 91 \\\hline\end{array}
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
66
Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.

A)12
B)13
C)14
D)15
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
67
Use the information in the table to determine the late finish time for Activity B.  Early  Early  Late  Late  Task  Predecessor  Duration  Start  Firish  Start  Firish A8BA14CA238DC,B62326EC32FD,E3238\begin{array} { | l | l | l | l | l | l | l | } \hline & & & \text { Early } & \text { Early } & \text { Late } & \text { Late } \\ \text { Task } & \text { Predecessor } & \text { Duration } & \text { Start } & \text { Firish } & \text { Start } & \text { Firish } \\\hline \mathrm { A } & \mathrm { -- } & \mathbf { 8 } & & & & \\\hline \mathrm { B } & \mathrm { A } & & & & 14 & \\\hline \mathrm { C } & \mathrm { A } & & & \mathbf { 2 3 } & \mathbf { 8 } & \\\hline \mathrm { D } & \mathrm { C } , \mathrm { B } & 6 & \mathbf { 2 3 } & & \mathbf { 2 6 } & \\\hline \mathrm { E } & \mathrm { C } & & & \mathbf { 3 2 } & & \\\hline \mathrm { F } & \mathrm { D } , \mathrm { E } & & \mathbf { 3 2 } & & & \mathbf { 3 8 } \\\hline\end{array}

A)Day 17
B)Day 20
C)Day 23
D)Day 26
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
68
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the late finish for the Plant Posts activity?  Optimistic Most Likely  Pessimistic  Activity  time  time  time  Predecessor  Corner Posts 456 String Line 789 Dig Holes 101214 Corner Posts  Plant Posts 111417 String Line  Weld Top Bar 81114 String Line  Dig Holes, Plant  Paint 91113 Posts  Tack Wire 91216 Weld Top Bar \begin{array}{|l|l|l|l|l|}\hline&\text { Optimistic} & \text { Most Likely } & \text { Pessimistic }\\ \text { Activity } & \text { time } & \text { time } & \text { time } & \text { Predecessor }\\ \hline \text { Corner Posts } & 4 & 5 & 6 & - \\\hline \text { String Line } & 7 & 8 & 9 & -- \\\hline \text { Dig Holes } & 10 & 12 & 14 & \text { Corner Posts } \\\hline \text { Plant Posts } & 11 & 14 & 17 & \text { String Line } \\\hline \text { Weld Top Bar } & 8 & 11 & 14 & \text { String Line } \\\hline & & & & \text { Dig Holes, Plant } \\ \text { Paint } & 9 & 11 & 13 & \text { Posts } \\\hline \text { Tack Wire } & 9 &12& 16& \text { Weld Top Bar } \\\hline\end{array}



A)13.3 days
B)8 days
C)20.83 days
D)22 days
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
69
Compute early and late start and finish times for the network shown.
Compute early and late start and finish times for the network shown.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
70
The amount of time an activity may be delayed from its early start without delaying the finish of the project is the:

A)Delay.
B)Float.
C)Late start.
D)Late finish.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
71
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration,so activity C in the original project becomes two activities,C1 and C2,each of which lasts 7 days.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the difference in the late start time for activity C in the original project and activity C1 in the laddered project?  Activity  Length  Predecessor  A 10B18 A C14 A D20 B, C \begin{array} { | l | l | l | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 10 & -- \\\hline B & 18 & \text { A } \\\hline \mathrm { C } & 14 & \text { A } \\\hline \mathrm { D } & 20 & \text { B, C } \\\hline\end{array}

A)3
B)5
C)7
D)9
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
72
Construct a network using the information in the table and identify the critical path.
 Activity  Time  Predecessor  A 4B6 A C9 A D11 BE16 B,CF4DG8E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 4 & \\\hline B & 6 & \text { A } \\\hline \mathrm { C } & 9 & \text { A } \\\hline \mathrm { D } & 11 & \mathrm {~B} \\\hline \mathrm { E } & 16 & \mathrm {~B} , \mathrm { C } \\\hline \mathrm { F } & 4 & \mathrm { D } \\\hline \mathrm { G } & \mathrm { 8 } & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & \mathrm { 7 } & \mathrm { G } \\\hline\end{array}
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
73
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities B,C,and D can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity?  Tirne  Predecessor A7B8 AC13 BD8CE7 AF6EG6 AH11GI12HJ14D,F,I\begin{array} { | l | l | l | } \hline & \text { Tirne } & \text { Predecessor } \\\hline \mathrm { A } & 7 & \\\hline B & 8 & \mathrm {~A} \\\hline \mathrm { C } & 13 & \mathrm {~B} \\\hline \mathrm { D } & 8 & \mathrm { C } \\\hline \mathrm { E } & 7 & \mathrm {~A} \\\hline \mathrm { F } & \mathrm { 6 } & \mathrm { E } \\\hline \mathrm { G } & 6 & \mathrm {~A} \\\hline \mathrm { H } & 11 & \mathrm { G } \\\hline \mathrm { I } & 12 & \mathrm { H } \\\hline \mathrm { J } & 14 & \mathrm { D } , \mathrm { F } , \mathrm { I } \\\hline\end{array}

A)11,30
B)7,24
C)11,24
D)7,36
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
74
Use the information in the table to sketch the network and compute early and late start times.
 Activity  Time  Predecessor A8B4 A C5 B, FD12 AE8DF4DG9E,F\begin{array} { | l | l | l |} \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \mathrm { A } & 8 & \\\hline\mathrm { B} & 4 & \text { A } \\\hline \mathrm { C } & 5 & \mathrm {~B} , \mathrm {~F} \\\hline \mathrm { D } & 12 & \mathrm {~A} \\\hline \mathrm { E } & 8 & \mathrm { D } \\\hline \mathrm { F } & 4 & \mathrm { D } \\\hline \mathrm { G } & 9 & \mathrm { E } , \mathrm { F } \\\hline\end{array}
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
75
The least amount of float is found:

A)In a resource-limited schedule.
B)After a burst activity.
C)On the critical path.
D)After a merge activity.
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
76
Use the information in the table to determine the early finish time for Activity D.  Early  Early  Late  Late  Task  Predecessor  Duration  Start  Firish  Start  Firish A8BA14CA238DC,B62326EC32FD,E3238\begin{array} { | l | l | l | l | l | l | l | } \hline & & & \text { Early } & \text { Early } & \text { Late } & \text { Late } \\ \text { Task } & \text { Predecessor } & \text { Duration } & \text { Start } & \text { Firish } & \text { Start } & \text { Firish } \\\hline \mathrm { A } & \mathrm { -- } & \mathbf { 8 } & & & & \\\hline \mathrm { B } & \mathrm { A } & & & & 14 & \\\hline \mathrm { C } & \mathrm { A } & & & \mathbf { 2 3 } & \mathbf { 8 } & \\\hline \mathrm { D } & \mathrm { C } , \mathrm { B } & 6 & \mathbf { 2 3 } & & \mathbf { 2 6 } & \\\hline \mathrm { E } & \mathrm { C } & & & \mathbf { 3 2 } & & \\\hline \mathrm { F } & \mathrm { D } , \mathrm { E } & & \mathbf { 3 2 } & & & \mathbf { 3 8 } \\\hline\end{array}

A)Day 23
B)Day 26
C)Day 29
D)Day 32
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
77
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.

A)8
B)13
C)14
D)21
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
78
Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G.

A)26
B)25
C)24
D)23
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
79
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.

A)8
B)13
C)14
D)21
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
80
Use the information in the table to sketch the network and compute early and late start times.
 Activity  Time  Predecessor  A 8B4AC5B, FD12 AE8DF4DG9E, FH12GI6C,GJ5IK9HF12 J, K\begin{array} { | l | l | l |} \hline\text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 8 & \\\hline \mathrm{B }& 4 & \mathrm{A} \\\hline \mathrm { C } & 5 & \mathrm { B }, \mathrm {~F} \\\hline \mathrm { D } & 12 & \mathrm {~A} \\\hline \mathrm { E } & 8 & \mathrm { D } \\\hline \mathrm { F } & 4 & \mathrm { D } \\\hline \mathrm { G } & 9 & \mathrm { E } , \mathrm {~F} \\\hline \mathrm { H } & 12 & \mathrm { G } \\\hline \mathrm { I } & 6 & \mathrm { C } , \mathrm { G } \\\hline \mathrm { J } & 5 & \mathrm { I } \\\hline \mathrm { K } & 9 & \mathrm { H } \\\hline \mathrm { F } & 12 & \mathrm {~J} , \mathrm {~K} \\\hline\end{array}
Unlock Deck
Unlock for access to all 105 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 105 flashcards in this deck.