Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture105 Questions
Exam 3: Project Selection and Portfolio Management103 Questions
Exam 4: Leadership and the Project Manager112 Questions
Exam 5: Scope Management111 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting105 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain105 Questions
Exam 12: Resource Management98 Questions
Exam 13: Project Evaluation and Control107 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
-Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.

Free
(Multiple Choice)
4.8/5
(38)
Correct Answer:
C
Use the information in the table to determine the early finish time for Activity D. Early Early Late Late Task Predecessor Duration Start Firish Start Firish 14 , 6 ,
Free
(Multiple Choice)
4.8/5
(45)
Correct Answer:
C
The amount of time an activity may be delayed from its early start without delaying the finish of the project is the:
Free
(Multiple Choice)
4.8/5
(35)
Correct Answer:
B
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?
Activity Predecessor Optirnistic Likely Pessimistic A -- 5 7 10 B A 4 6 9 A 10 13 18 3 11 15 , 2 5
(Essay)
4.9/5
(36)
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the probability that the project is completed in 31 days? Activity Optimistic time Most Likely time Pessimistic time Predecessor Corner Posts 4 5 6 - String Line 7 8 9 - Dig Holes 10 12 14 Corner Posts Plant Posts 11 14 17 String Line Weld Top Bar 8 11 14 String Line Dig Holes, Plant Paint 9 11 13 Posts Tack Wire 9 12 16 Weld Top Bar
(Multiple Choice)
4.8/5
(42)
Use the information in the table to sketch the network and compute early and late start times.
Activity Time Predecessor 8 4 A 5 , 12 8 4 9 ,
(Essay)
4.8/5
(26)
Based on the activity network pictured,what is the BEST statement?
(Multiple Choice)
4.8/5
(41)
An activity has an optimistic time estimate of 17 days,a most likely estimate of 22 days,and a pessimistic estimate of 32 days.What is the expected duration of the activity?
(Multiple Choice)
4.8/5
(40)
The PERT technique assumes that durations are more deterministic.
(True/False)
4.8/5
(23)
What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?

(Multiple Choice)
4.8/5
(33)
What is the slack time for Activity D given the activity times and precedence requirements shown in the table? Activity Time Predecessor 5 -- 7 -- 8 A 7 4 8 , 9 , 7
(Multiple Choice)
4.9/5
(34)
The late start time should be calculated using a forward pass through the network.
(True/False)
4.8/5
(31)
What is the slack time for Activity B given the activity times and precedence requirements shown in the table? Activity Time Predecessor 5 -- 7 -- 8 A 7 4 8 , 9 , 7
(Multiple Choice)
4.7/5
(38)
Use the information in the table to determine the late finish time for Activity B. Early Early Late Late Task Predecessor Duration Start Firish Start Firish 14 , 6 ,
(Multiple Choice)
4.8/5
(31)
Activities C,D,and E in the project represented by the network are to be hammocked.What are the late start and early finish times of the hammock activity?

(Multiple Choice)
4.8/5
(38)
An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time.If the activity variance is 12,what is the expected time?
(Multiple Choice)
4.7/5
(29)
Showing 1 - 20 of 105
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)