Deck 17: Project Management

Full screen (f)
exit full mode
Question
Once a project is underway,project managers are only responsible for managing the project schedule (time)and budget (costs).
Use Space or
up arrow
down arrow
to flip the card.
Question
Risks involved in a project can be transferred by outsourcing a particular component of the project and requiring performance bonds.
Question
The path in a PERT/CPM precedence network with the fewest activities and shortest duration is referred to as the critical path.
Question
A project manager usually staffs the human resources required for a project by hiring outside specialists that only work for the company for the duration of the project.
Question
The probability of occurrence of risk events is lower near the beginning of a project and higher near the end of the project.
Question
An advantage of Gantt charts in project management is that they reveal which activities can be delayed without delaying the overall project.
Question
Careful planning of complex projects can eliminate the occurrence of risk events that have undesirable consequences.
Question
Project managers bear the ultimate responsibility for the success or failure of the project.
Question
Although PERT and CPM were originally developed for somewhat different types of projects,they are now nearly identical in terms of analysis and procedures.
Question
Projects involve routine operations that are performed repeatedly.
Question
A hierarchical listing of what must be done during a project is called a project matrix.
Question
A Gantt chart provides a visual representation of the sequence of activities in a project.
Question
Following project initiation,planning and scheduling,project execution is the last phase of a projects life cycle.
Question
The task of identifying risks should involve everyone associated with the project.
Question
Companies that are organized as pure project organizations are equivalent to matrix organizations that temporarily group specialists from different departments.
Question
Purchase planning is typically outside the scope of project planning activities.
Question
One way that project management differs from management of more traditional operations is the limited time frame of projects.
Question
PERT was originally developed for military planning in the 1940's during the Second World War (WWII).
Question
Sequential dependencies among project activities are less important than the time required to complete activities.
Question
The precedence network for a project depicts sequential relationships among activities in a project.
Question
Simulation can be used for cases in which network activity durations are dependent.
Question
A normal distribution is usually used to describe probabilistic duration estimates for activities in a project.
Question
If two consecutive activities on the same path each have two days of activity slack,this means that each of them can be delayed by two days without delaying the overall project.
Question
The latest starting time for an activity is equal to the latest finish time minus the activity time.
Question
The standard deviation of the duration of the critical path is equal to the square root of the sum of the variances of all of the activities on the critical path.
Question
The earliest finish time for an activity is equal to the latest finish time minus the activity slack.
Question
Consecutive activities on the same path have shared slack,which means if activities are delayed,the amount of slack remaining is reduced for all these activities without delaying completion of the project.
Question
The sum of activity durations of the longest path in a network indicates expected project completion time,and the activities on it are called the critical activities.
Question
Activity slack is the difference between the latest finish and earliest finish times.
Question
The path in a precedence network with the longest duration is the critical path.
Question
The probability that the project will go beyond the desired time is equal to one minus the joint probability that all paths will be completed within the desired time.
Question
The critical path has zero path slack time.
Question
For the PERT/CPM technique,completing the backward pass includes making the latest finish (LF)equal to the earliest finish (EF)for the end activity.
Question
The standard deviation of a project duration is equal to the sum of the variances of all the activities of the project.
Question
A beta distribution can be used to describe the inherent variability of an activity's duration.
Question
In order to determine the probability of timely project completion,it is sometimes necessary to take into account paths other than the critical path.
Question
Deterministic networks use three duration estimates for each activity in order to best determine the activity's estimated duration.
Question
The earliest finish time for an activity is equal to the latest finish time minus the activity time.
Question
Activities not on the critical path have a slack time equal to zero.
Question
Project managers are sometimes able to reduce indirect project costs by increasing direct costs.
Question
A relatively simple tool for planning and scheduling simple projects is the:

A) an activity-on-arrows network.
B) an activity-on-nodes network.
C) a Gantt chart.
D) critical path method.
E) program evaluation and review technique.
Question
Besides project activities,the primary information that all Gantt charts illustrate is:

A) project budget and when activities occur.
B) cost of activities and delays in the schedule.
C) planned duration of activities and when they occur in the schedule.
D) project budget and staffing levels.
E) critical path and project budget.
Question
Scope creep refers to the tendency for projects to take longer than planned.
Question
Which of the following is a part of project scheduling?

A) Identify resource requirements for activities
B) Estimate the duration of activities
C) Identify activities in the work breakdown structure
D) Identify sequential dependencies among activities
E) All of the choices are a part of project scheduling.
Question
Which of the following is not involved in project planning?

A) Risk management planning
B) Material requirements planning (MRP)
C) Quality planning
D) Communication planning
E) Purchase planning
Question
The advantage(s)the PERT/CPM technique has over a Gantt chart is (are):

A) its ability to reveal relationships among activities.
B) it illustrates multiple paths as a project network.
C) it indicates which activities are most critical.
D) it indicates the implications of delays in activities.
E) all of the choices are correct.
Question
Which of the following is not a form of risk reduction in project management?

A) Backup systems
B) Outsourcing components of the project
C) Frequent monitoring of project activities
D) Expand the project scope to reduce external dependencies
E) Improving communications
Question
Only activities on the critical path are initial candidates for crashing.
Question
A hierarchical listing of what must be done during the project is called:

A) work breakdown structure (WBS).
B) program evaluation and review technique (PERT).
C) planning matrix.
D) crashing.
E) critical path method (CPM).
Question
Which of the following are advantages of CPM/PERT?
I)Relationships among activities can be identified.
II)Slippage in project activities is no longer an issue.
III)Activities that need to be watched closely can be identified.

A) I and II
B) II and III
C) III only
D) I and III
E) I, II, and III
Question
Which of the following would probably not involve the use of project management?

A) Planning and constructing a new city hall
B) Developing a marketing campaign for the launch of a new product
C) Designing and constructing a subway system
D) Scheduling workers and purchasing raw materials for a manufacturing plant
E) Producing and staging a music festival
Question
In a precedence network the critical path is the sequence of activities which has:

A) the most activities.
B) the most nodes.
C) the most events.
D) the longest duration.
E) the greatest variance.
Question
The optimum project length in crashing occurs when the cumulative cost of crashing equals savings in the indirect costs.
Question
The life cycle of a project includes which of the following phases?
I)Initiation
II)Planning and scheduling
III)Growth and maturity
IV)Closeout

A) I and II only
B) II and III only
C) I, II, and IV only
D) II, III, and IV only
E) I, II, III, and IV
Question
The project management technique that is repeated until activities are decomposed into work packages that can be performed by a designated worker,team or subcontract is called:

A) work breakdown structure (WBS).
B) program evaluation and review technique (PERT).
C) planning matrix.
D) crashing.
E) none of the choices.
Question
The principal advantage a Gantt chart has over other project scheduling techniques is:

A) its ability to reveal relationships among activities.
B) it illustrates multiple paths as a project network.
C) it focuses on the critical path.
D) its simplicity.
E) both cost and time are included in the chart.
Question
Concerning PERT and CPM,which of the following statements is correct?

A) These are two different names for what is essentially the same technique.
B) CPM tends to focus more on the critical path.
C) PERT gives a clearer indication of activity slack, while CPM gives a better picture of path slack.
D) Because of its recent discovery, much less is known about CPM than PERT.
E) Neither provides as much detail as a Gantt chart.
Question
People working on a project are:

A) often on loan from their regular job.
B) often working only part-time on the project.
C) associated with the project for less than the full time required to complete it.
D) all of the choices.
Question
Once a project is underway,the project manager is responsible for effectively managing:
I)the people.
II)costs.
III)time.
IV)communications.

A) II only
B) I and II only
C) II and III only
D) I, II and III only
E) I, II, III, and IV
Question
The cost control technique of earned value analysis measures project progress by the budgeted cost of work scheduled.
Question
There are four activities on the critical path.Coincidentally,the standard deviations for their durations are all equal to 4.The standard deviation of the duration for the critical path is therefore equal to:

A) 2
B) 4
C) 8
D) 16
E) 64
Question
In the probabilistic approach to precedence network analysis,the duration estimate annotated "tm" for any activity is the:

A) mean duration.
B) median duration.
C) most likely duration.
D) optimistic duration.
E) pessimistic duration.
Question
Activity 4 in a network diagram has an optimistic duration estimate of 5 days,a most likely duration estimate of 7 days,and a pessimistic duration estimate of 10 days.The expected duration of Activity 4 is:

A) 5
B) 6
C) 7
D) 8
E) 9
Question
Activity C has an early start time of 8,an early finish time of 12,a latest start time of 13,and a latest finish time of 17.Its slack is:

A) 0
B) 1
C) 4
D) 5
E) 9
Question
At which point does crashing of a project cease?

A) When the project is completed
B) When no additional crashing is possible
C) When the cost to crash equals or exceeds the benefit of crashing
D) All of the choices are correct
E) None of the choices are correct
Question
Activity 7 is directly preceded by two activities-activity 5 and activity 6.Activity 5 has an expected duration of five and an ES time of six.Activity 6 has an expected duration of seven and an ES time of seven.Activity 7 has an expected duration of 10.The ES for activity 7 is:

A) 11
B) 14
C) 21
D) 24
E) 25
Question
A PERT/CPM activity has an optimistic duration estimate of 3 days,a most likely duration estimate of 8 days,and a pessimistic duration estimate of 10 days.The expected duration of this activity te is:

A) 7.0
B) 7.5
C) 8.0
D) 8.5
E) 10.0
Question
The project management strategy of injecting additional resources in order to reduce the length of the project is called:

A) expediting.
B) rushing.
C) panicking.
D) crashing.
E) none of the choices are correct.
Question
In precedence network analysis,knowing the slack time allows managers to:
I)allocate scarce resources.
II)pay attention to activities that could delay the project.
III)delay critical activities.

A) I only
B) II only
C) III only
D) I and II only
E) I, II, and III
Question
In the probabilistic approach to precedence network analysis,the duration estimate that is given the highest weighting in calculating the expected duration for an activity is:

A) duration of the immediately prior activity.
B) duration of the immediately following activity.
C) most likely duration.
D) optimistic duration.
E) pessimistic duration.
Question
Given this information about activity B: ES = 10,EF = 15,LS = 16 and LF = 21,we can determine that the amount of slack associated with the activity is:

A) 0
B) 1
C) 5
D) 6
E) 11
Question
When developing probabilistic estimates of project duration,it is necessary to know which of the following?

A) The mean and variance of every activity
B) The mean and variance of activities on the critical path
C) The standard deviation of activities on the critical path
D) Each activity's probability of completion
E) The distribution of activity durations
Question
Which of the following is not an advantage of using project management software?

A) It automatically generates and formats a variety of reports.
B) It reduces project costs.
C) It can enhance communication among team members.
D) It can generate various charts.
E) It provides a logical planning structure.
Question
An activity,A,has two succeeding activities,B and C.Given the following information,determine the latest starting time for activity A. EF B = 15,EF C = 17,LF B = 24,LF C = 27; activity times are A = 4,B = 6,C = 8.

A)14
B)15
C)16
D)17
E)18
Question
Uncontrolled growth in the number of activities that end up being included as a part of a project is called:

A) the critical path.
B) project slack.
C) scope creep.
D) indirect costs.
E) time-cost trade-offs.
Question
<strong>  Given the portion of the network shown above,based on the activity durations shown what is the latest start time of activity 7 if the latest finish of activity 8 is 26,and the latest finish of activity 9 is 23?</strong> A) 18 B) 17 C) 13 D) 12 E) 10 <div style=padding-top: 35px> Given the portion of the network shown above,based on the activity durations shown what is the latest start time of activity 7 if the latest finish of activity 8 is 26,and the latest finish of activity 9 is 23?

A) 18
B) 17
C) 13
D) 12
E) 10
Question
Which of the following is used to compute the earliest finish times once the earliest start times are calculated for an activity on a precedence network?

A) Expected activity duration
B) Activity slack time
C) Activities that are on the critical path
D) Variance in project duration
E) Maximum project duration
Question
<strong>  Given the portion of the network shown above,based on the activity durations shown what is the earliest finish time for activity D,if the earliest start time of B is 12,and the earliest start time of C is 13?</strong> A) 19 B) 20 C) 21 D) 22 E) 23 <div style=padding-top: 35px> Given the portion of the network shown above,based on the activity durations shown what is the earliest finish time for activity D,if the earliest start time of B is 12,and the earliest start time of C is 13?

A) 19
B) 20
C) 21
D) 22
E) 23
Question
There are four activities on the critical path,and the standard deviations for their durations are 1,2,4,and 2 days.The standard deviation of the duration of the critical path is:

A) 3
B) 5
C) 9
D) 16
E) 25
Question
In "crashing",a project manager will generally focus on activities which:

A) are not on the critical path.
B) are the least costly to crash.
C) are costly to crash and are on the critical path.
D) are on the critical path and are the least costly to crash.
E) none of the choices are correct.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/127
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 17: Project Management
1
Once a project is underway,project managers are only responsible for managing the project schedule (time)and budget (costs).
False
2
Risks involved in a project can be transferred by outsourcing a particular component of the project and requiring performance bonds.
True
3
The path in a PERT/CPM precedence network with the fewest activities and shortest duration is referred to as the critical path.
False
4
A project manager usually staffs the human resources required for a project by hiring outside specialists that only work for the company for the duration of the project.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
5
The probability of occurrence of risk events is lower near the beginning of a project and higher near the end of the project.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
6
An advantage of Gantt charts in project management is that they reveal which activities can be delayed without delaying the overall project.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
7
Careful planning of complex projects can eliminate the occurrence of risk events that have undesirable consequences.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
8
Project managers bear the ultimate responsibility for the success or failure of the project.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
9
Although PERT and CPM were originally developed for somewhat different types of projects,they are now nearly identical in terms of analysis and procedures.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
10
Projects involve routine operations that are performed repeatedly.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
11
A hierarchical listing of what must be done during a project is called a project matrix.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
12
A Gantt chart provides a visual representation of the sequence of activities in a project.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
13
Following project initiation,planning and scheduling,project execution is the last phase of a projects life cycle.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
14
The task of identifying risks should involve everyone associated with the project.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
15
Companies that are organized as pure project organizations are equivalent to matrix organizations that temporarily group specialists from different departments.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
16
Purchase planning is typically outside the scope of project planning activities.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
17
One way that project management differs from management of more traditional operations is the limited time frame of projects.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
18
PERT was originally developed for military planning in the 1940's during the Second World War (WWII).
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
19
Sequential dependencies among project activities are less important than the time required to complete activities.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
20
The precedence network for a project depicts sequential relationships among activities in a project.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
21
Simulation can be used for cases in which network activity durations are dependent.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
22
A normal distribution is usually used to describe probabilistic duration estimates for activities in a project.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
23
If two consecutive activities on the same path each have two days of activity slack,this means that each of them can be delayed by two days without delaying the overall project.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
24
The latest starting time for an activity is equal to the latest finish time minus the activity time.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
25
The standard deviation of the duration of the critical path is equal to the square root of the sum of the variances of all of the activities on the critical path.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
26
The earliest finish time for an activity is equal to the latest finish time minus the activity slack.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
27
Consecutive activities on the same path have shared slack,which means if activities are delayed,the amount of slack remaining is reduced for all these activities without delaying completion of the project.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
28
The sum of activity durations of the longest path in a network indicates expected project completion time,and the activities on it are called the critical activities.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
29
Activity slack is the difference between the latest finish and earliest finish times.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
30
The path in a precedence network with the longest duration is the critical path.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
31
The probability that the project will go beyond the desired time is equal to one minus the joint probability that all paths will be completed within the desired time.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
32
The critical path has zero path slack time.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
33
For the PERT/CPM technique,completing the backward pass includes making the latest finish (LF)equal to the earliest finish (EF)for the end activity.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
34
The standard deviation of a project duration is equal to the sum of the variances of all the activities of the project.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
35
A beta distribution can be used to describe the inherent variability of an activity's duration.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
36
In order to determine the probability of timely project completion,it is sometimes necessary to take into account paths other than the critical path.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
37
Deterministic networks use three duration estimates for each activity in order to best determine the activity's estimated duration.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
38
The earliest finish time for an activity is equal to the latest finish time minus the activity time.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
39
Activities not on the critical path have a slack time equal to zero.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
40
Project managers are sometimes able to reduce indirect project costs by increasing direct costs.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
41
A relatively simple tool for planning and scheduling simple projects is the:

A) an activity-on-arrows network.
B) an activity-on-nodes network.
C) a Gantt chart.
D) critical path method.
E) program evaluation and review technique.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
42
Besides project activities,the primary information that all Gantt charts illustrate is:

A) project budget and when activities occur.
B) cost of activities and delays in the schedule.
C) planned duration of activities and when they occur in the schedule.
D) project budget and staffing levels.
E) critical path and project budget.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
43
Scope creep refers to the tendency for projects to take longer than planned.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
44
Which of the following is a part of project scheduling?

A) Identify resource requirements for activities
B) Estimate the duration of activities
C) Identify activities in the work breakdown structure
D) Identify sequential dependencies among activities
E) All of the choices are a part of project scheduling.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
45
Which of the following is not involved in project planning?

A) Risk management planning
B) Material requirements planning (MRP)
C) Quality planning
D) Communication planning
E) Purchase planning
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
46
The advantage(s)the PERT/CPM technique has over a Gantt chart is (are):

A) its ability to reveal relationships among activities.
B) it illustrates multiple paths as a project network.
C) it indicates which activities are most critical.
D) it indicates the implications of delays in activities.
E) all of the choices are correct.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
47
Which of the following is not a form of risk reduction in project management?

A) Backup systems
B) Outsourcing components of the project
C) Frequent monitoring of project activities
D) Expand the project scope to reduce external dependencies
E) Improving communications
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
48
Only activities on the critical path are initial candidates for crashing.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
49
A hierarchical listing of what must be done during the project is called:

A) work breakdown structure (WBS).
B) program evaluation and review technique (PERT).
C) planning matrix.
D) crashing.
E) critical path method (CPM).
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
50
Which of the following are advantages of CPM/PERT?
I)Relationships among activities can be identified.
II)Slippage in project activities is no longer an issue.
III)Activities that need to be watched closely can be identified.

A) I and II
B) II and III
C) III only
D) I and III
E) I, II, and III
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
51
Which of the following would probably not involve the use of project management?

A) Planning and constructing a new city hall
B) Developing a marketing campaign for the launch of a new product
C) Designing and constructing a subway system
D) Scheduling workers and purchasing raw materials for a manufacturing plant
E) Producing and staging a music festival
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
52
In a precedence network the critical path is the sequence of activities which has:

A) the most activities.
B) the most nodes.
C) the most events.
D) the longest duration.
E) the greatest variance.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
53
The optimum project length in crashing occurs when the cumulative cost of crashing equals savings in the indirect costs.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
54
The life cycle of a project includes which of the following phases?
I)Initiation
II)Planning and scheduling
III)Growth and maturity
IV)Closeout

A) I and II only
B) II and III only
C) I, II, and IV only
D) II, III, and IV only
E) I, II, III, and IV
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
55
The project management technique that is repeated until activities are decomposed into work packages that can be performed by a designated worker,team or subcontract is called:

A) work breakdown structure (WBS).
B) program evaluation and review technique (PERT).
C) planning matrix.
D) crashing.
E) none of the choices.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
56
The principal advantage a Gantt chart has over other project scheduling techniques is:

A) its ability to reveal relationships among activities.
B) it illustrates multiple paths as a project network.
C) it focuses on the critical path.
D) its simplicity.
E) both cost and time are included in the chart.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
57
Concerning PERT and CPM,which of the following statements is correct?

A) These are two different names for what is essentially the same technique.
B) CPM tends to focus more on the critical path.
C) PERT gives a clearer indication of activity slack, while CPM gives a better picture of path slack.
D) Because of its recent discovery, much less is known about CPM than PERT.
E) Neither provides as much detail as a Gantt chart.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
58
People working on a project are:

A) often on loan from their regular job.
B) often working only part-time on the project.
C) associated with the project for less than the full time required to complete it.
D) all of the choices.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
59
Once a project is underway,the project manager is responsible for effectively managing:
I)the people.
II)costs.
III)time.
IV)communications.

A) II only
B) I and II only
C) II and III only
D) I, II and III only
E) I, II, III, and IV
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
60
The cost control technique of earned value analysis measures project progress by the budgeted cost of work scheduled.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
61
There are four activities on the critical path.Coincidentally,the standard deviations for their durations are all equal to 4.The standard deviation of the duration for the critical path is therefore equal to:

A) 2
B) 4
C) 8
D) 16
E) 64
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
62
In the probabilistic approach to precedence network analysis,the duration estimate annotated "tm" for any activity is the:

A) mean duration.
B) median duration.
C) most likely duration.
D) optimistic duration.
E) pessimistic duration.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
63
Activity 4 in a network diagram has an optimistic duration estimate of 5 days,a most likely duration estimate of 7 days,and a pessimistic duration estimate of 10 days.The expected duration of Activity 4 is:

A) 5
B) 6
C) 7
D) 8
E) 9
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
64
Activity C has an early start time of 8,an early finish time of 12,a latest start time of 13,and a latest finish time of 17.Its slack is:

A) 0
B) 1
C) 4
D) 5
E) 9
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
65
At which point does crashing of a project cease?

A) When the project is completed
B) When no additional crashing is possible
C) When the cost to crash equals or exceeds the benefit of crashing
D) All of the choices are correct
E) None of the choices are correct
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
66
Activity 7 is directly preceded by two activities-activity 5 and activity 6.Activity 5 has an expected duration of five and an ES time of six.Activity 6 has an expected duration of seven and an ES time of seven.Activity 7 has an expected duration of 10.The ES for activity 7 is:

A) 11
B) 14
C) 21
D) 24
E) 25
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
67
A PERT/CPM activity has an optimistic duration estimate of 3 days,a most likely duration estimate of 8 days,and a pessimistic duration estimate of 10 days.The expected duration of this activity te is:

A) 7.0
B) 7.5
C) 8.0
D) 8.5
E) 10.0
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
68
The project management strategy of injecting additional resources in order to reduce the length of the project is called:

A) expediting.
B) rushing.
C) panicking.
D) crashing.
E) none of the choices are correct.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
69
In precedence network analysis,knowing the slack time allows managers to:
I)allocate scarce resources.
II)pay attention to activities that could delay the project.
III)delay critical activities.

A) I only
B) II only
C) III only
D) I and II only
E) I, II, and III
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
70
In the probabilistic approach to precedence network analysis,the duration estimate that is given the highest weighting in calculating the expected duration for an activity is:

A) duration of the immediately prior activity.
B) duration of the immediately following activity.
C) most likely duration.
D) optimistic duration.
E) pessimistic duration.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
71
Given this information about activity B: ES = 10,EF = 15,LS = 16 and LF = 21,we can determine that the amount of slack associated with the activity is:

A) 0
B) 1
C) 5
D) 6
E) 11
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
72
When developing probabilistic estimates of project duration,it is necessary to know which of the following?

A) The mean and variance of every activity
B) The mean and variance of activities on the critical path
C) The standard deviation of activities on the critical path
D) Each activity's probability of completion
E) The distribution of activity durations
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
73
Which of the following is not an advantage of using project management software?

A) It automatically generates and formats a variety of reports.
B) It reduces project costs.
C) It can enhance communication among team members.
D) It can generate various charts.
E) It provides a logical planning structure.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
74
An activity,A,has two succeeding activities,B and C.Given the following information,determine the latest starting time for activity A. EF B = 15,EF C = 17,LF B = 24,LF C = 27; activity times are A = 4,B = 6,C = 8.

A)14
B)15
C)16
D)17
E)18
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
75
Uncontrolled growth in the number of activities that end up being included as a part of a project is called:

A) the critical path.
B) project slack.
C) scope creep.
D) indirect costs.
E) time-cost trade-offs.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
76
<strong>  Given the portion of the network shown above,based on the activity durations shown what is the latest start time of activity 7 if the latest finish of activity 8 is 26,and the latest finish of activity 9 is 23?</strong> A) 18 B) 17 C) 13 D) 12 E) 10 Given the portion of the network shown above,based on the activity durations shown what is the latest start time of activity 7 if the latest finish of activity 8 is 26,and the latest finish of activity 9 is 23?

A) 18
B) 17
C) 13
D) 12
E) 10
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
77
Which of the following is used to compute the earliest finish times once the earliest start times are calculated for an activity on a precedence network?

A) Expected activity duration
B) Activity slack time
C) Activities that are on the critical path
D) Variance in project duration
E) Maximum project duration
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
78
<strong>  Given the portion of the network shown above,based on the activity durations shown what is the earliest finish time for activity D,if the earliest start time of B is 12,and the earliest start time of C is 13?</strong> A) 19 B) 20 C) 21 D) 22 E) 23 Given the portion of the network shown above,based on the activity durations shown what is the earliest finish time for activity D,if the earliest start time of B is 12,and the earliest start time of C is 13?

A) 19
B) 20
C) 21
D) 22
E) 23
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
79
There are four activities on the critical path,and the standard deviations for their durations are 1,2,4,and 2 days.The standard deviation of the duration of the critical path is:

A) 3
B) 5
C) 9
D) 16
E) 25
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
80
In "crashing",a project manager will generally focus on activities which:

A) are not on the critical path.
B) are the least costly to crash.
C) are costly to crash and are on the critical path.
D) are on the critical path and are the least costly to crash.
E) none of the choices are correct.
Unlock Deck
Unlock for access to all 127 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 127 flashcards in this deck.