The latest starting time for an activity is equal to the latest finish time minus the activity time.

Free
(True/False)
4.9/5
(29)
Correct Answer:
Verified

True

In the probabilistic approach to precedence network analysis,the duration estimate annotated "tm" for any activity is the:

Free
(Multiple Choice)
4.9/5
(32)
Correct Answer:
Verified

C

  -What are the estimated expected (mean)durations (in weeks)for activities A-H? -What are the estimated expected (mean)durations (in weeks)for activities A-H?

Free
(Short Answer)
4.8/5
(26)
Correct Answer:
Verified

15; 20; 10; 35; 25; 30; 20; 5

What is the probability that this project will be completed within 205 days?

(Multiple Choice)
4.9/5
(33)

In "crashing",a project manager will generally focus on activities which:

(Multiple Choice)
4.8/5
(25)

Purchase planning is typically outside the scope of project planning activities.

(True/False)
4.9/5
(31)

Determine the amount of slack in each of a project's activities (see the list below),and identify those which are on the critical path. Determine the amount of slack in each of a project's activities (see the list below),and identify those which are on the critical path.

(Essay)
4.9/5
(29)

Which of the following is not a form of risk reduction in project management?

(Multiple Choice)
4.7/5
(35)

A hierarchical listing of what must be done during the project is called:

(Multiple Choice)
4.8/5
(28)

The standard deviation of the duration of the critical path is equal to the square root of the sum of the variances of all of the activities on the critical path.

(True/False)
4.9/5
(25)

A PERT/CPM activity has an optimistic duration estimate of 3 days,a most likely duration estimate of 8 days,and a pessimistic duration estimate of 10 days.The expected duration of this activity te is:

(Multiple Choice)
4.7/5
(35)

What is the estimated slack time for the path A-D-F?

(Multiple Choice)
4.9/5
(35)

What is the estimated slack time for the path B-D-F?

(Multiple Choice)
4.9/5
(40)

  -What is the critical path for this project network? -What is the critical path for this project network?

(Short Answer)
4.8/5
(32)

The project management strategy of injecting additional resources in order to reduce the length of the project is called:

(Multiple Choice)
4.8/5
(35)

The life cycle of a project includes which of the following phases? I.Initiation II.Planning and scheduling III.Growth and maturity IV.Closeout

(Multiple Choice)
5.0/5
(35)

The principal advantage a Gantt chart has over other project scheduling techniques is:

(Multiple Choice)
4.8/5
(35)

Consecutive activities on the same path have shared slack,which means if activities are delayed,the amount of slack remaining is reduced for all these activities without delaying completion of the project.

(True/False)
4.8/5
(37)

The standard deviation of a project duration is equal to the sum of the variances of all the activities of the project.

(True/False)
4.9/5
(34)

What is the estimated standard deviation of the duration for activity E?

(Multiple Choice)
4.9/5
(45)