Deck 17: Project Management
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/137
Play
Full screen (f)
Deck 17: Project Management
1
Matrix organizations transfer control of workers to project managers for the duration of the project.
False
2
The earliest finish time for an activity is equal to the latest finish time minus the activity time.
False
3
Good project management is especially important with virtual teams.
True
4
The project computing algorithm requires both a forward and backward pass.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
5
A hierarchical (vertical) listing of what must be done during a project is called matrix.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
6
An advantage of Gantt charts in project management is that they identify which activities can be delayed without delaying the overall project.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
7
Some organizations use a matrix organization to integrate the activities of specialists within a functional framework.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
8
The sum of times of the longest path in a network indicates expected project completion time, and the activities represent the critical activities.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
9
A Gantt chart is built using established precedence relationships.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
10
Once a project is approved and underway, project managers are only responsible for effectively managing time and costs which, if done well, will assure project completion on time and on budget.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
11
The higher the node number, the longer the activity will take.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
12
Although PERT and CPM were originally developed for somewhat different types of projects, they are now nearly identical in terms of analysis and procedures.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
13
The costs associated with risk events tend to be lower near the beginning of a project, and higher near the end of the project.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
14
One way that project management differs from management of more traditional activities is because of the limited lifetime of projects.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
15
The main function of dummy activities is to clarify relationships in network diagrams.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
16
Path probabilities are calculated by dividing path mean by path standard deviations.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
17
The path in a network with the average length of time to completion is called the critical path.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
18
The probability of occurrence of risk events is lower near the beginning of a project and higher near the end of the project since very few activities remain.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
19
The network diagram describes sequential relationships among major activities on a project.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
20
The latest starting time for an activity is equal to the latest finish time minus the activity time.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
21
Simulation can be used for cases in which network activity times are dependent.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
22
The earliest finish time for an activity is equal to the latest finish time minus the activity slack.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
23
Project management software eliminates conflicts when there are shared resources.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
24
If the expected length of a path is more than 2.5 standard deviations less than a desired project completion time, the path would not be a factor in assessing the probability of finishing the project on time.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
25
If two consecutive activities on the same path each have two days of activity slack, this means that each of them can be delayed by two days without delaying the project.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
26
Most likely time generally is more than optimistic time.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
27
Only activities on the critical path are initial candidates for crashing.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
28
A disadvantage of activity-on-node diagrams is the occasional need for dummy activities.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
29
In order to determine the probability of timely project completion, it is sometimes necessary to take into account paths other than the critical path.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
30
Deterministic networks use three time estimates - shortest, most likely and longest - for each activity in order to best determine the activity's estimated time.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
31
Many activities have slack time; if we add these slack times together, this represents the potential improvement in early completion for the project.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
32
The probability that the project will go beyond the desired time is equal to one minus the joint probability that all paths will be completed within the desired time.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
33
The optimum project length in crashing occurs where the cumulative cost of crashing equals savings in the indirect costs.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
34
Project managers are sometimes able to reduce indirect project costs by increasing direct costs.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
35
If two consecutive activities have shared slack, this means that each of them can use only half of the slack without delaying completion of the project.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
36
The task of identifying risks should involve everyone associated with the project.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
37
Slack time is equal to LS-ES or LF-EF.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
38
The standard deviation of the critical path is equal to the sum of the standard deviations of all of the activities on the critical path.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
39
Activities not on the critical path have a slack time equal to zero.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
40
The total cost of crashing any one activity should never exceed 20% of the total cost of the original project.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
41
Shortening activity durations is called:
A)Expediting
B)Crashing
C)Vendor management
D)Null nodes
E)Trade-off analysis
A)Expediting
B)Crashing
C)Vendor management
D)Null nodes
E)Trade-off analysis
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
42
The advantage(s) a precedence diagram has over a Gantt chart is(are):
A)its ability to reveal relationships among activities.
B)it can easily show networks.
C)(a) and (b).
D)its simplicity.
E)all of the above.
A)its ability to reveal relationships among activities.
B)it can easily show networks.
C)(a) and (b).
D)its simplicity.
E)all of the above.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
43
In PERT, the expected project duration will never exceed the expected duration of the critical path.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
44
A sequence of activities that leads from the starting node to the finishing node is called a _______.
A)Path
B)Sequel
C)Trail
D)Critical sequence
E)Time line
A)Path
B)Sequel
C)Trail
D)Critical sequence
E)Time line
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
45
Concerning PERT and CPM:
A)These are two different names for essentially the same technique.
B)CPM tends to focus more on the critical path; PERT focuses on the parallel paths.
C)PERT gives a clearer indication of activity slack, while CPM gives a better picture of path slack.
D)Because of its recent discovery, much less is known about CPM than PERT.
E)All of the above are true.
A)These are two different names for essentially the same technique.
B)CPM tends to focus more on the critical path; PERT focuses on the parallel paths.
C)PERT gives a clearer indication of activity slack, while CPM gives a better picture of path slack.
D)Because of its recent discovery, much less is known about CPM than PERT.
E)All of the above are true.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
46
To _____ an activity means to shorten the time it will take.
A)Speed
B)Fund
C)Crash
D)Aggregate
E)Matrix
A)Speed
B)Fund
C)Crash
D)Aggregate
E)Matrix
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
47
Project management differs from management of more traditional activities mainly because of:
A)its limited time frame
B)its unique, defined set of activities
C)(a) and (b)
D)the requirement for use of the appropriate resources
E)the need for planning and execution
A)its limited time frame
B)its unique, defined set of activities
C)(a) and (b)
D)the requirement for use of the appropriate resources
E)the need for planning and execution
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
48
In a project network the critical path is the sequence of activities which has the:
A)most activities
B)most nodes
C)most events
D)longest time
E)greatest variance
A)most activities
B)most nodes
C)most events
D)longest time
E)greatest variance
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
49
Which of the following would probably not involve the use of PERT?
A)planning and constructing a new city hall
B)developing an advertising campaign for a new product
C)designing and constructing a subway system
D)writing a poem
E)preparing for the visit of a foreign dignitary
A)planning and constructing a new city hall
B)developing an advertising campaign for a new product
C)designing and constructing a subway system
D)writing a poem
E)preparing for the visit of a foreign dignitary
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
50
Consider the portion of a project depicted by this graph:
What is the earliest finish time for activity 10-11 (far right hand side), if the earliest start time of 8-10 (upper left hand side) is 12, and the earliest start time of 9-10 (lower left hand side) is 13?
A)22
B)23
C)24
D)25
E)26

A)22
B)23
C)24
D)25
E)26
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
51
Which of the following is determined as a direct result of computing the earliest starting and finishing times for the activities of a project network?
A)expected project duration
B)activity slack time
C)which activities are on the critical path
D)variance in project duration
E)maximum project duration
A)expected project duration
B)activity slack time
C)which activities are on the critical path
D)variance in project duration
E)maximum project duration
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
52
Activity 7-8 is directly preceded by two activities-activity 5-7 and activity 6-7.Activity 5-7 has an expected time of five and an ES time of six.Activity 6-7 has an expected time of seven and an ES time of seven.Activity 7-8 has an expected time of 10.The ES for activity 7-8 is:
A)11
B)14
C)21
D)24
E)25
A)11
B)14
C)21
D)24
E)25
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
53
Which of the following is not true about the use of dummy activities in project networking?
A)They preserve the separate identities of activities.
B)They clarify precedence relationships among activities.
C)They have an activity time equal to zero.
D)They have an activity time variance equal to zero.
E)They are used in activities-on-nodes (AON) network diagrams.
A)They preserve the separate identities of activities.
B)They clarify precedence relationships among activities.
C)They have an activity time equal to zero.
D)They have an activity time variance equal to zero.
E)They are used in activities-on-nodes (AON) network diagrams.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
54
Which of the following is not a form of risk reduction in project management?
A)backup system
B)outsourcing
C)risk-sharing
D)scenario analysis
E)all of the above are risk reduction methods
A)backup system
B)outsourcing
C)risk-sharing
D)scenario analysis
E)all of the above are risk reduction methods
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
55
In PERT, the path with the fewest activities is referred to as the critical path.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
56
A popular tool for planning and scheduling simple projects, and for initial planning on more complex projects, is the:
A)activity-on-arrows network
B)activity-on-nodes network
C)Gantt chart
D)critical path method
E)program evaluation and review technique
A)activity-on-arrows network
B)activity-on-nodes network
C)Gantt chart
D)critical path method
E)program evaluation and review technique
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
57
Once a project is underway, the project manager usually is not responsible for effectively managing:
A)the people
B)costs
C)resources
D)time
E)project priority
A)the people
B)costs
C)resources
D)time
E)project priority
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
58
A hierarchical listing of what must be done in a project is called:
A)work breakdown structure (WBS)
B)PERT
C)planning matrix
D)crashing
E)critical path
A)work breakdown structure (WBS)
B)PERT
C)planning matrix
D)crashing
E)critical path
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
59
Which of the following is not typically treated as part of a project life cycle?
A)feasibility analysis
B)planning
C)maturity
D)incubation
E)alternative generation
A)feasibility analysis
B)planning
C)maturity
D)incubation
E)alternative generation
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
60
A method used for establishing a logical framework for identifying the required activities for the project is called:
A)Work breakdown structure
B)PERT
C)planning matrix
D)crashing
E)critical path analysis
A)Work breakdown structure
B)PERT
C)planning matrix
D)crashing
E)critical path analysis
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
61
Consider the portion of a project depicted by this graph:
What is the latest start time of activity 6-7 if the latest finish of activity 7-8 is 26, and the latest finish of activity 7-9 is 23?
A)18
B)17
C)13
D)12
E)10

A)18
B)17
C)13
D)12
E)10
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
62
In "crashing" a project, a manager will generally focus on activities which:
A)are not on the critical path
B)are the least costly to crash
C)are costly to crash and are on the critical path
D)are on the critical path and are the least costly to crash
E)are the easiest to crash
A)are not on the critical path
B)are the least costly to crash
C)are costly to crash and are on the critical path
D)are on the critical path and are the least costly to crash
E)are the easiest to crash
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
63
Consider the project depicted by the following A-O-A diagram:
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
64
There are four activities on the critical path.Coincidentally, their standard deviations are all equal to 4.The standard deviation of the critical path is therefore equal to:
A)2
B)4
C)8
D)16
E)64
A)2
B)4
C)8
D)16
E)64
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
65
The basis for use of the beta distribution in PERT is:
A)essentially theoretical.
B)its adaptability.
C)its symmetry.
D)It is bimodal.
E)It can easily be converted to a normal distribution.
A)essentially theoretical.
B)its adaptability.
C)its symmetry.
D)It is bimodal.
E)It can easily be converted to a normal distribution.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
66
Given this information about activity 3-4: ES = 10, EF = 15, LS = 16, and LF = 21, we can determine that the amount of slack associated with the activity is:
A)0
B)1
C)5
D)6
E)11
A)0
B)1
C)5
D)6
E)11
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
67
In the probabilistic approach to project network analysis, the time estimate annotated "tm" for any activity is the:
A)mean time
B)median time
C)most likely time
D)mode time
E)marginal time
A)mean time
B)median time
C)most likely time
D)mode time
E)marginal time
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
68
A PERT/CPM activity has an optimistic time estimate of three days, a most likely time estimate of eight days, and a pessimistic time estimate of 10 days.The expected time (in days) of this activity is:
A)7.0
B)7.5
C)8.0
D)8.5
E)10.0
A)7.0
B)7.5
C)8.0
D)8.5
E)10.0
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
69
A node has one entering activity, a, and two leaving activities, b and c.Given the following information, determine the latest starting time for activity a: EFb = 15, EFc = 17, LFb = 24, LFc = 27; activity times are a = 4, b = 6, c = 8.
A)14
B)15
C)16
D)17
E)18
A)14
B)15
C)16
D)17
E)18
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
70
Which of the following are limitations of PERT? (I) Time estimates may include a fudge factor.
(II) Important activities may be overlooked.
(III) It is an after-the-fact analysis.
A)I and II
B)I, II, and III
C)I and III
D)II and III
E)I only
(II) Important activities may be overlooked.
(III) It is an after-the-fact analysis.
A)I and II
B)I, II, and III
C)I and III
D)II and III
E)I only
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
71
At which point does crashing of a project cease?
A)when the project is completed
B)when no additional crashing is possible
C)when the cost to crash equals or exceeds the benefit of crashing
D)when the project is one-half completed
E)none of the above
A)when the project is completed
B)when no additional crashing is possible
C)when the cost to crash equals or exceeds the benefit of crashing
D)when the project is one-half completed
E)none of the above
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
72
There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2 days.The standard deviation of the critical path is:
A)3
B)5
C)9
D)16
E)25
A)3
B)5
C)9
D)16
E)25
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
73
Which of the following is not a limitation of PERT and similar project-scheduling techniques?
A)They force the manager to organize and quantify information.
B)One or more important activities may be omitted from the network.
C)Precedence relationships may not all be correct as shown.
D)Time estimates may contain a "fudge factor."
E)The use of a computer is essential for large projects.
A)They force the manager to organize and quantify information.
B)One or more important activities may be omitted from the network.
C)Precedence relationships may not all be correct as shown.
D)Time estimates may contain a "fudge factor."
E)The use of a computer is essential for large projects.
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
74
Activity 4-5 in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 10 days.Its expected time is approximately:
A)5
B)6
C)7
D)8
E)9
A)5
B)6
C)7
D)8
E)9
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
75
Gantt charts are most closely associated with
A)JIT
B)PERT
C)MRP
D)MRPII
E)Six Sigma
A)JIT
B)PERT
C)MRP
D)MRPII
E)Six Sigma
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
76
Activity C has an early start time of 8, an early finish time of 12, a latest start time of 13, and a latest finish time of 17.Its slack is:
A)0
B)1
C)4
D)5
E)9
A)0
B)1
C)4
D)5
E)9
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
77
Which of the following are advantages of PERT? (I) It is visual.
(II) It is automatically updated.
(III) Activities that need to be watched closely can be identified.
A)I and II
B)II and III
C)III only
D)I and III
E)I, II, and III
(II) It is automatically updated.
(III) Activities that need to be watched closely can be identified.
A)I and II
B)II and III
C)III only
D)I and III
E)I, II, and III
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
78
When developing probabilistic estimates of project duration, it is necessary to know which of the following?
A)the mean and variance of every activity
B)the mean and variance of activities on the critical path
C)the standard deviation of activities on the critical path
D)each activity's probability of completion
E)the distribution of activity times
A)the mean and variance of every activity
B)the mean and variance of activities on the critical path
C)the standard deviation of activities on the critical path
D)each activity's probability of completion
E)the distribution of activity times
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
79
The project management strategy of injecting additional resources in order to reduce the length of the project is called:
A)expediting
B)rushing
C)panicking
D)crashing
E)loading
A)expediting
B)rushing
C)panicking
D)crashing
E)loading
Unlock Deck
Unlock for access to all 137 flashcards in this deck.
Unlock Deck
k this deck
80
In project network analysis, "slack" refers to the difference between:
A)observed and predicted times
B)optimistic and pessimistic times
C)mean and modal times
D)finish and start times
E)latest and earliest times
A)observed and predicted times
B)optimistic and pessimistic times
C)mean and modal times
D)finish and start times
E)latest and earliest times