Exam 17: Project Management
Exam 1: Introduction to Operations Management70 Questions
Exam 2: Competitiveness, Strategy, and Productivity73 Questions
Exam 3: Forecasting164 Questions
Exam 4: Product and Service Design77 Questions
Exam 5: Strategic Capacity Planning for Products and Services103 Questions
Exam 6: Process Selection and Facility Layout151 Questions
Exam 7: Work Design and Measurement151 Questions
Exam 8: Location Planning and Analysis80 Questions
Exam 9: Management of Quality102 Questions
Exam 10: Quality Control141 Questions
Exam 11: Aggregate Planning and Master Scheduling81 Questions
Exam 12: MRP and ERP89 Questions
Exam 13: Inventory Management162 Questions
Exam 14: Jit and Lean Operations88 Questions
Exam 15: Supply Chain Management89 Questions
Exam 16: Scheduling134 Questions
Exam 17: Project Management137 Questions
Exam 18: Management of Waiting Lines81 Questions
Exam 19: Linear Programming105 Questions
Exam 20: Extension 4: Reliability10 Questions
Exam 21: Extension 5: Decision Theory126 Questions
Exam 22: Extension 7: Learning Curves68 Questions
Exam 23: Extension 8: The Transportation Model20 Questions
Exam 24: Extension 10: Acceptance Sampling65 Questions
Exam 25: Extension 14: Maintenance38 Questions
Select questions type
What is the estimated expected (mean) time for project completion?
Free
(Multiple Choice)
4.8/5
(43)
Correct Answer:
C
A popular tool for planning and scheduling simple projects, and for initial planning on more complex projects, is the:
Free
(Multiple Choice)
4.8/5
(36)
Correct Answer:
C
Activity J has a duration of 7 and an earliest finish time of 21.If J's latest start time is 16, this must mean that J's slack is ________.
Free
(Multiple Choice)
4.8/5
(35)
Correct Answer:
D
What is the probability that the critical path for this project will be completed within 210 days?
(Multiple Choice)
4.7/5
(34)
Simulation can be used for cases in which network activity times are dependent.
(True/False)
4.8/5
(38)
Matrix organizations transfer control of workers to project managers for the duration of the project.
(True/False)
4.8/5
(31)
What is the estimated expected (mean) time (in weeks) for project completion?
(Short Answer)
4.7/5
(40)
Although PERT and CPM were originally developed for somewhat different types of projects, they are now nearly identical in terms of analysis and procedures.
(True/False)
4.9/5
(32)
A disadvantage of activity-on-node diagrams is the occasional need for dummy activities.
(True/False)
4.8/5
(34)
Deterministic networks use three time estimates - shortest, most likely and longest - for each activity in order to best determine the activity's estimated time.
(True/False)
4.9/5
(31)
There are four activities on the critical path.Coincidentally, their standard deviations are all equal to 4.The standard deviation of the critical path is therefore equal to:
(Multiple Choice)
4.9/5
(41)
Good project management is especially important with virtual teams.
(True/False)
4.9/5
(32)
Only activities on the critical path are initial candidates for crashing.
(True/False)
4.7/5
(33)
Within what amount of time (in weeks) is there a 90% probability that the critical path for this project will be completed? 95%? 99%?
(Short Answer)
4.9/5
(37)