Deck 8: Scheduling Resources and Costs

Full screen (f)
exit full mode
Question
Most of the scheduling methods available today require the project manager to classify the project as either _______ constrained or ______ constrained.

A)Time, quality
B)Quality, resource
C)Cost, time
D)Quality, cost
E)Time, resource
Use Space or
up arrow
down arrow
to flip the card.
Question
Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test.This is an example of a _________ constraint.

A)Physical
B)Technical
C)Resource
D)Scheduling
E)Time
Question
Resource leveling can provide

A)Lower peak demand
B)Reduced resource need over the life of the project
C)Reduced fluctuations in resource demand
D)Both A and B are correct
E)A, B, and C are all correct
Question
Delaying noncritical activities to lower peak demand on resources is known as resource

A)Shifting
B)Effectiveness
C)Manipulating
D)Resource smoothing
E)Allocation
Question
Jan is trying to reallocate resources in a time-constrained project to create smoother resource utilization with a low level of risk.She should move to activities with the

A)Smallest duration
B)Least slack
C)Most slack
D)Lowest identification number
E)Highest cost
Question
Scheduling time-constrained projects focuses on resource

A)Demands
B)Increases
C)Assumptions
D)Utilization
E)All are correct
Question
Which of the following is not one of the types of project constraints?

A)Physical
B)Technical
C)Resource
D)Time
E)All of these are types of project constraints
Question
In reviewing the status of her project with top management, Shirley was told that there only were two programmers that she could use for her project.Her project is __________ constrained.

A)Time
B)Quality
C)Cost
D)Performance
E)Resource
Question
All resource leveling techniques involve

A)Delaying noncritical activities
B)Delaying critical activities
C)Using negative slack
D)Both A and C are correct
E)A, B, and C are all correct
Question
If resources are not adequate to meet peak demands, the resulting reschedule is termed

A)Resource-constrained scheduling
B)Time-constrained scheduling
C)Mandatory leveling
D)Project resource adjustment
E)Allocation
Question
The most widely used approach to apply heuristics, which have been found to consistently minimize project delay over a large variety of projects is the

A)Parallel method
B)Resource method
C)Materials
D)Both A and C are correct
E)A, B, and C are all correct
Question
Which of the following is a potential consequence of failing to schedule limited resources?

A)Costly activity delays
B)Costly project delays
C)Difficulty in taking quick corrective action
D)Both A and B are correct
E)A, B, and C are all correct
Question
Sam is trying to order the concrete needed to continue his project.However, the supplier won't be able to deliver it until next week.This is an example of a _______ constraint.

A)Working capital
B)People
C)Equipment
D)Information
E)Materials
Question
Regina's boss has told her that her project is very important.If the critical path is delayed, she will be given whatever she needs to get it back on schedule.Her project is ________ constrained.

A)Time
B)Quality
C)Cost
D)Performance
E)Resource
Question
In a resource-constrained project, which of the following is most likely to be changed?

A)The completion date
B)The budget
C)Project quality
D)Both A and B are equally likely
E)A, B, and C are all equally likely
Question
A special truck that George needs on his project has been scheduled on another project.This is a ______ constraint.

A)Working capital
B)People
C)Equipment
D)Information
E)Materials
Question
When developing a new software package, the software must be designed, the code must be written, and the code must be tested.This is an example of a ______ constraint.

A)Physical
B)Technical
C)Resource
D)Schedule
E)Time
Question
All of the following are kinds of resource constraints except

A)Materials
B)People
C)Equipment
D)Information
E)All of the above are resource constraints
Question
In a resource-constrained project, the first priority in assigning resources is usually given to activities with the

A)Smallest duration
B)Least slack
C)Most slack
D)Lowest identification number
E)Highest cost
Question
Sam the project engineer has been scheduled to run the product system test at the same time he is to build a marketing prototype.This is an example of a ______ constraint.

A)Physical
B)Technical
C)Resource
D)Scheduling
E)Time
Question
Having one person responsible for performing several activities, all due at the same time, is an example of a(n) ________ constraint.
Question
Project budgets are developed by time-phasing which of the following?

A)Resource schedules
B)Work packages
C)The network diagram
D)Both A and C are correct
E)A, B, and C are all correct
Question
The shortage of computer chips to produce a circuit board is an example of a(n) ________ type of resource constraint.
Question
If three copiers are needed to produce a final report on time and only two are available, the project is facing a(n) ________ type of resource constraint.
Question
The U.S.Forest Service "snapshot from practice" illustrated the importance of

A)Time constraints
B)Resource constraints
C)Cost constraints
D)Both B and C are correct
E)A, B, and C are all correct
Question
Hector wants to bring on another programmer to work on the project but the company does not have anyone who has the needed skills.Hector's project is facing a(n) ________ constraint.
Question
More common problems associated with managing multiproject resources include all of the following except

A)Inefficient resource utilization
B)Delays in one project cause delays in other projects
C)Reducing "downtime" created by lack of tasks to perform
D)Resource bottlenecks
E)All of these are common problems
Question
Which of the following is not one of the more common problems associated with scheduling multiproject resources?

A)Overall schedule slippage
B)Inefficient resource utilization
C)Resource bottlenecks
D)Both A and C are correct
E)A, B, and C are all correct
Question
In a resource-constrained project the second priority in assigning resources is usually given to activities with the

A)Smallest duration
B)Least slack
C)Most slack
D)Lowest identification number
E)Highest cost
Question
A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000.Which of the following is true?

A)We are spending less than we should for the project
B)We are doing a good job managing the project
C)We should check to see if all the bills have been paid
D)Both A and B are correct
E)We can't be sure how the project is going
Question
In a resource-constrained project the third priority in assigning resources is usually given to activities with the

A)Smallest duration
B)Least slack
C)Most slack
D)Lowest identification number
E)Highest cost
Question
In order that the new product is on the shelf for the Christmas buying season, the development of the new product would be classified as a(n) ________ constrained project.
Question
In the Botanical Garden example, which of the following was used to solve the resource problem?

A)Resource allocation
B)Smoothing resource demand
C)The parallel method
D)Both A and C are correct
E)A, B, and C are all correct
Question
Trying to renovate a ship compartment that is too small for more than one person is an example of a(n) ________ constraint.
Question
Delaying noncritical activities to lower peak demand and, thus, increase resource utilization is called _______ leveling.
Question
The word Heuristics means

A)Resource constraints
B)Flexibility
C)The critical path changed
D)Parallel activities become sequential
E)Rule of thumb
Question
Splitting an activity creates the following situation:

A)More people working on the same activity
B)There are possible startup and shutdown costs
C)A resource may be moved from one activity to another and then back
D)Both B and C are correct
E)A, B, and C are all correct
Question
A(n) ________ constraint addresses the sequence in which project activities must occur.
Question
A shortage of programmers to write software is an example of a(n) ________ type of resource constraint.
Question
When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is called

A)Outsourcing
B)Redistribution of projects
C)Project allocation
D)Task sharing
E)Both B and D are correct
Question
When using the ________ scheduling technique, the work in an activity is interrupted to work on another activity and is then resumed at a later point in time.
Question
In scheduling resource-constrained projects, _________ are typically used rather than optimum mathematical solutions.
Question
Without a time-phased __________ good project schedule and cost control are impossible.
Question
Resource Bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules.
Question
Scheduling activities in a constrained project typically has ________ as the top heuristic rule.
Question
The ________ is the most widely used approach to apply heuristic rules to scheduling activities in a constrained project.
Question
Many companies are using ________ from contractors and consultants as a means of dealing with the peaks and valleys of resource allocation among projects.
Question
The ______________ is the most widely used approach to apply heuristics in resource-constrained projects.
Question
Beth has two engineers assigned to her project and cannot get any more even if it means slipping the due date on her project.She is managing a(n) ________ constrained project.
Question
To deal with problems related to having several concurrent projects, companies are creating ________ to oversee the scheduling of resources across multiple projects.
Question
In scheduling terms, ________ constrained means that a specific resource is fixed and the duration of the project is flexible.
Question
A project cost baseline is also called __________.
Question
The ability to more efficiently manage the ebbs and flows of project work is one of the major driving forces behind ____________ today.
Question
Start-up and shutdown costs are major considerations when using the ________________ scheduling technique.
Question
A project that is not resource-constrained is time-constrained.
Question
Resource leveling is only used on projects which are resource-constrained.
Question
Too many parallel activities for one individual are an example of a resource constraint.
Question
The sequence of (1) pour foundation, (2) build frame, and (3) cover roof is a type of physical constraint.
Question
In scheduling terms, ________ constrained means that project duration is fixed and resources are flexible.
Question
All leveling techniques delay noncritical activities by using ________ to reduce peak demand.
Question
All leveling techniques delay noncritical activities by using positive slack to smooth out the resource requirements.
Question
What is the difference in project goals when using resource leveling on time-constrained projects and using it on resource-constrained projects?
Question
Having too few programmers and too many engineers is an example of a people resource constraint.
Question
Scheduling time-constrained projects focuses on the optimal utilization of resources.
Question
The most obvious and important kind of resource constraint is a lack of materials.
Question
The critical path in a resource-constrained schedule can be a group of disjointed, unconnected activities.
Question
To determine if a project is time-constrained or resource-constrained you would consult the project priority matrix.
Question
If a project needs one earth-mover six months from now and the organization has four such machines, there is no equipment resource constraint.
Question
The inability to get more than two earth movers on a construction site at the same time is an example of a physical constraint.
Question
Splitting is a scheduling technique used to get a better schedule or better resource utilization.
Question
Identify and briefly describe the three types of project constraints.
Question
A lack of readily available engineers is a technical constraint.
Question
The top priority in using heuristics to allocate scare resources is those activities with the smallest duration.
Question
Without a time-phased budget good project schedule and cost control are impossible.
Question
Scheduling resource-constrained projects focuses on completing the project as soon as possible under the given constraints.
Question
Identify the potential impacts of project constraints.
Question
All projects are usually either time-constrained or resource-constrained.
Question
Heuristics are used in resource-constrained projects to develop the optimal schedule.
Question
Many companies are using outsourcing as a means for dealing with their resource allocation problems associated with managing multiproject resources.
Question
Scheduling time-constrained projects focuses on resource utilization.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/90
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 8: Scheduling Resources and Costs
1
Most of the scheduling methods available today require the project manager to classify the project as either _______ constrained or ______ constrained.

A)Time, quality
B)Quality, resource
C)Cost, time
D)Quality, cost
E)Time, resource
E
Explanation: Most of the scheduling methods available today require the project manager to classify the project as either time constrained or resource constrained.
2
Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test.This is an example of a _________ constraint.

A)Physical
B)Technical
C)Resource
D)Scheduling
E)Time
A
Explanation: Since space allows only one person to work at one time, all tasks have to be performed sequentially this is a physical constraint.
3
Resource leveling can provide

A)Lower peak demand
B)Reduced resource need over the life of the project
C)Reduced fluctuations in resource demand
D)Both A and B are correct
E)A, B, and C are all correct
E
Explanation: Practitioners have attacked the utilization problem using resource leveling techniques that balance or smooth demand for a resource.Basically, all leveling techniques delay noncritical activities by using positive slack to reduce peak demand and fill in the valleys for the resources.
4
Delaying noncritical activities to lower peak demand on resources is known as resource

A)Shifting
B)Effectiveness
C)Manipulating
D)Resource smoothing
E)Allocation
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
5
Jan is trying to reallocate resources in a time-constrained project to create smoother resource utilization with a low level of risk.She should move to activities with the

A)Smallest duration
B)Least slack
C)Most slack
D)Lowest identification number
E)Highest cost
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
6
Scheduling time-constrained projects focuses on resource

A)Demands
B)Increases
C)Assumptions
D)Utilization
E)All are correct
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
7
Which of the following is not one of the types of project constraints?

A)Physical
B)Technical
C)Resource
D)Time
E)All of these are types of project constraints
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
8
In reviewing the status of her project with top management, Shirley was told that there only were two programmers that she could use for her project.Her project is __________ constrained.

A)Time
B)Quality
C)Cost
D)Performance
E)Resource
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
9
All resource leveling techniques involve

A)Delaying noncritical activities
B)Delaying critical activities
C)Using negative slack
D)Both A and C are correct
E)A, B, and C are all correct
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
10
If resources are not adequate to meet peak demands, the resulting reschedule is termed

A)Resource-constrained scheduling
B)Time-constrained scheduling
C)Mandatory leveling
D)Project resource adjustment
E)Allocation
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
11
The most widely used approach to apply heuristics, which have been found to consistently minimize project delay over a large variety of projects is the

A)Parallel method
B)Resource method
C)Materials
D)Both A and C are correct
E)A, B, and C are all correct
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
12
Which of the following is a potential consequence of failing to schedule limited resources?

A)Costly activity delays
B)Costly project delays
C)Difficulty in taking quick corrective action
D)Both A and B are correct
E)A, B, and C are all correct
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
13
Sam is trying to order the concrete needed to continue his project.However, the supplier won't be able to deliver it until next week.This is an example of a _______ constraint.

A)Working capital
B)People
C)Equipment
D)Information
E)Materials
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
14
Regina's boss has told her that her project is very important.If the critical path is delayed, she will be given whatever she needs to get it back on schedule.Her project is ________ constrained.

A)Time
B)Quality
C)Cost
D)Performance
E)Resource
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
15
In a resource-constrained project, which of the following is most likely to be changed?

A)The completion date
B)The budget
C)Project quality
D)Both A and B are equally likely
E)A, B, and C are all equally likely
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
16
A special truck that George needs on his project has been scheduled on another project.This is a ______ constraint.

A)Working capital
B)People
C)Equipment
D)Information
E)Materials
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
17
When developing a new software package, the software must be designed, the code must be written, and the code must be tested.This is an example of a ______ constraint.

A)Physical
B)Technical
C)Resource
D)Schedule
E)Time
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
18
All of the following are kinds of resource constraints except

A)Materials
B)People
C)Equipment
D)Information
E)All of the above are resource constraints
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
19
In a resource-constrained project, the first priority in assigning resources is usually given to activities with the

A)Smallest duration
B)Least slack
C)Most slack
D)Lowest identification number
E)Highest cost
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
20
Sam the project engineer has been scheduled to run the product system test at the same time he is to build a marketing prototype.This is an example of a ______ constraint.

A)Physical
B)Technical
C)Resource
D)Scheduling
E)Time
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
21
Having one person responsible for performing several activities, all due at the same time, is an example of a(n) ________ constraint.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
22
Project budgets are developed by time-phasing which of the following?

A)Resource schedules
B)Work packages
C)The network diagram
D)Both A and C are correct
E)A, B, and C are all correct
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
23
The shortage of computer chips to produce a circuit board is an example of a(n) ________ type of resource constraint.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
24
If three copiers are needed to produce a final report on time and only two are available, the project is facing a(n) ________ type of resource constraint.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
25
The U.S.Forest Service "snapshot from practice" illustrated the importance of

A)Time constraints
B)Resource constraints
C)Cost constraints
D)Both B and C are correct
E)A, B, and C are all correct
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
26
Hector wants to bring on another programmer to work on the project but the company does not have anyone who has the needed skills.Hector's project is facing a(n) ________ constraint.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
27
More common problems associated with managing multiproject resources include all of the following except

A)Inefficient resource utilization
B)Delays in one project cause delays in other projects
C)Reducing "downtime" created by lack of tasks to perform
D)Resource bottlenecks
E)All of these are common problems
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
28
Which of the following is not one of the more common problems associated with scheduling multiproject resources?

A)Overall schedule slippage
B)Inefficient resource utilization
C)Resource bottlenecks
D)Both A and C are correct
E)A, B, and C are all correct
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
29
In a resource-constrained project the second priority in assigning resources is usually given to activities with the

A)Smallest duration
B)Least slack
C)Most slack
D)Lowest identification number
E)Highest cost
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
30
A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000.Which of the following is true?

A)We are spending less than we should for the project
B)We are doing a good job managing the project
C)We should check to see if all the bills have been paid
D)Both A and B are correct
E)We can't be sure how the project is going
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
31
In a resource-constrained project the third priority in assigning resources is usually given to activities with the

A)Smallest duration
B)Least slack
C)Most slack
D)Lowest identification number
E)Highest cost
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
32
In order that the new product is on the shelf for the Christmas buying season, the development of the new product would be classified as a(n) ________ constrained project.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
33
In the Botanical Garden example, which of the following was used to solve the resource problem?

A)Resource allocation
B)Smoothing resource demand
C)The parallel method
D)Both A and C are correct
E)A, B, and C are all correct
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
34
Trying to renovate a ship compartment that is too small for more than one person is an example of a(n) ________ constraint.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
35
Delaying noncritical activities to lower peak demand and, thus, increase resource utilization is called _______ leveling.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
36
The word Heuristics means

A)Resource constraints
B)Flexibility
C)The critical path changed
D)Parallel activities become sequential
E)Rule of thumb
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
37
Splitting an activity creates the following situation:

A)More people working on the same activity
B)There are possible startup and shutdown costs
C)A resource may be moved from one activity to another and then back
D)Both B and C are correct
E)A, B, and C are all correct
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
38
A(n) ________ constraint addresses the sequence in which project activities must occur.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
39
A shortage of programmers to write software is an example of a(n) ________ type of resource constraint.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
40
When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is called

A)Outsourcing
B)Redistribution of projects
C)Project allocation
D)Task sharing
E)Both B and D are correct
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
41
When using the ________ scheduling technique, the work in an activity is interrupted to work on another activity and is then resumed at a later point in time.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
42
In scheduling resource-constrained projects, _________ are typically used rather than optimum mathematical solutions.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
43
Without a time-phased __________ good project schedule and cost control are impossible.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
44
Resource Bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
45
Scheduling activities in a constrained project typically has ________ as the top heuristic rule.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
46
The ________ is the most widely used approach to apply heuristic rules to scheduling activities in a constrained project.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
47
Many companies are using ________ from contractors and consultants as a means of dealing with the peaks and valleys of resource allocation among projects.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
48
The ______________ is the most widely used approach to apply heuristics in resource-constrained projects.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
49
Beth has two engineers assigned to her project and cannot get any more even if it means slipping the due date on her project.She is managing a(n) ________ constrained project.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
50
To deal with problems related to having several concurrent projects, companies are creating ________ to oversee the scheduling of resources across multiple projects.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
51
In scheduling terms, ________ constrained means that a specific resource is fixed and the duration of the project is flexible.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
52
A project cost baseline is also called __________.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
53
The ability to more efficiently manage the ebbs and flows of project work is one of the major driving forces behind ____________ today.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
54
Start-up and shutdown costs are major considerations when using the ________________ scheduling technique.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
55
A project that is not resource-constrained is time-constrained.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
56
Resource leveling is only used on projects which are resource-constrained.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
57
Too many parallel activities for one individual are an example of a resource constraint.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
58
The sequence of (1) pour foundation, (2) build frame, and (3) cover roof is a type of physical constraint.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
59
In scheduling terms, ________ constrained means that project duration is fixed and resources are flexible.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
60
All leveling techniques delay noncritical activities by using ________ to reduce peak demand.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
61
All leveling techniques delay noncritical activities by using positive slack to smooth out the resource requirements.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
62
What is the difference in project goals when using resource leveling on time-constrained projects and using it on resource-constrained projects?
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
63
Having too few programmers and too many engineers is an example of a people resource constraint.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
64
Scheduling time-constrained projects focuses on the optimal utilization of resources.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
65
The most obvious and important kind of resource constraint is a lack of materials.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
66
The critical path in a resource-constrained schedule can be a group of disjointed, unconnected activities.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
67
To determine if a project is time-constrained or resource-constrained you would consult the project priority matrix.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
68
If a project needs one earth-mover six months from now and the organization has four such machines, there is no equipment resource constraint.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
69
The inability to get more than two earth movers on a construction site at the same time is an example of a physical constraint.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
70
Splitting is a scheduling technique used to get a better schedule or better resource utilization.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
71
Identify and briefly describe the three types of project constraints.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
72
A lack of readily available engineers is a technical constraint.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
73
The top priority in using heuristics to allocate scare resources is those activities with the smallest duration.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
74
Without a time-phased budget good project schedule and cost control are impossible.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
75
Scheduling resource-constrained projects focuses on completing the project as soon as possible under the given constraints.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
76
Identify the potential impacts of project constraints.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
77
All projects are usually either time-constrained or resource-constrained.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
78
Heuristics are used in resource-constrained projects to develop the optimal schedule.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
79
Many companies are using outsourcing as a means for dealing with their resource allocation problems associated with managing multiproject resources.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
80
Scheduling time-constrained projects focuses on resource utilization.