When developing a new software package, the software must be designed, the code must be written, and the code must be tested.This is an example of a ______ constraint.

Free
(Multiple Choice)
4.8/5
(35)
Correct Answer:
Verified

B

In scheduling terms, ________ constrained means that project duration is fixed and resources are flexible.

Free
(Short Answer)
4.9/5
(43)
Correct Answer:
Verified

time
Explanation: In scheduling terms, time constrained means time (project duration) is fixed and resources are flexible.

Scheduling resource-constrained projects focuses on completing the project as soon as possible under the given constraints.

Free
(True/False)
5.0/5
(30)
Correct Answer:
Verified

True

The sequence of (1) pour foundation, (2) build frame, and (3) cover roof is a type of physical constraint.

(True/False)
4.7/5
(32)

Most of the scheduling methods available today require the project manager to classify the project as either _______ constrained or ______ constrained.

(Multiple Choice)
5.0/5
(36)

Sam is trying to order the concrete needed to continue his project.However, the supplier won't be able to deliver it until next week.This is an example of a _______ constraint.

(Multiple Choice)
4.8/5
(34)

Identify and briefly describe the potential impacts of resource-constrained scheduling.

(Essay)
4.7/5
(25)

A special truck that George needs on his project has been scheduled on another project.This is a ______ constraint.

(Multiple Choice)
4.8/5
(40)

The most widely used approach to apply heuristics, which have been found to consistently minimize project delay over a large variety of projects is the

(Multiple Choice)
4.8/5
(34)

Having one person responsible for performing several activities, all due at the same time, is an example of a(n) ________ constraint.

(Short Answer)
4.9/5
(26)

All leveling techniques delay noncritical activities by using positive slack to smooth out the resource requirements.

(True/False)
4.8/5
(31)

What is the difference in project goals when using resource leveling on time-constrained projects and using it on resource-constrained projects?

(Essay)
4.8/5
(32)

Start-up and shutdown costs are major considerations when using the ________________ scheduling technique.

(Short Answer)
4.8/5
(31)

Identify and briefly describe the three types of project constraints.

(Essay)
4.9/5
(30)

Jan is trying to reallocate resources in a time-constrained project to create smoother resource utilization with a low level of risk.She should move to activities with the

(Multiple Choice)
4.8/5
(31)

All of the following are kinds of resource constraints except

(Multiple Choice)
4.8/5
(39)

What are the three most common heuristics (in order of priority) used to allocate resources to project activities?

(Essay)
4.9/5
(27)

All projects are usually either time-constrained or resource-constrained.

(True/False)
4.8/5
(34)

Resource Bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules.

(True/False)
4.8/5
(41)

A project that is not resource-constrained is time-constrained.

(True/False)
4.8/5
(30)