Deck 13: Progress and Performance Measurement and Evaluation

Full screen (f)
exit full mode
Question
In monitoring project time (schedule)performance,actual performance should be compared to

A) Budgets for the current year.
B) Top management's targets.
C) Project network schedule derived from the WBS/OBS.
D) Progress on similar past projects.
E) Previous status reports.
Use Space or
up arrow
down arrow
to flip the card.
Question
A project monitoring system involves all of the following EXCEPT

A) Determining what data to collect.
B) Determining how,when,and who will collect the data.
C) Adjusting the data.
D) Analysis of the data.
E) Reporting current progress.
Question
Nancy tells her supervisor that as of right now,$1.05 worth of work has been accomplished for each $1 worth of scheduled work.Nancy got this information from viewing the

A) SV.
B) TCPI.
C) CPI.
D) SPI.
E) PCIB.
Question
A ___________ Gantt chart is a simple and effective way to depict progress on a project.

A) Baseline
B) Control
C) Variance
D) Tracking
E) Simple
Question
The second step in the project control process for measuring and evaluating project performance is to

A) Review the baseline plan with top management.
B) Analyze inputs to control system.
C) Compare plan against actual.
D) Measure progress and performance.
E) Review spending with team members.
Question
Which performance index is the most potentially misleading?

A) CPI
B) EV
C) CV
D) SV
E) EAC
Question
Which of the following methods of variance analysis is the best indicator of how far off the budget a project will be at completion?

A) BAC
B) EAC
C) ETC
D) VAC
E) TCPI
Question
Jessica just received the following information on her project: PV = 200,EV = 300,AC = 250,BAC = 1500,EAC = 1208.In terms of cost at completion.

A) The project will currently finish under budget.
B) The project will currently finish over budget.
C) The project will currently finish on budget.
D) The project will currently finish behind schedule.
E) There is insufficient information to draw conclusions.
Question
Of the following costs,which are NOT included in baseline?

A) Suppliers
B) Equipment
C) Labor
D) Budget reserves
E) Contractors
Question
The first step in the project control process for measuring and evaluating project performance is to

A) Set a baseline plan.
B) Determine the project objectives.
C) Determine the project deliverables.
D) Analyze the project budget.
E) Review the project priority matrix.
Question
The final step in the project control process for measuring and evaluating project performance is to

A) Take appropriate action.
B) Prepare a report to top management.
C) Follow up on corrective action.
D) Measure progress and performance.
E) Review spending with team members.
Question
The schedule variance for a project is calculated by:

A) EV - AC
B) AC - SV
C) PV - EV
D) CV - EV
E) EV - PV
Question
When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains,they are creating a method for assigning costs to the baseline called the

A) 0/100 percent rule.
B) Task complete rule.
C) Degree complete rule.
D) Work complete rule.
E) Percent complete rule.
Question
A tool used to monitor past project schedule performance and current performance,and to estimate future schedule trends is a simple line chart known as a

A) Project control chart.
B) Gantt chart.
C) PERT chart.
D) Network diagram.
E) Milestone chart.
Question
Which of the following are required to assess the current status of a project using the earned-value cost/schedule system?

A) BAC,EAC,and ETC
B) VAC,EAC,and BAC
C) CV,SV,and BAC
D) PV,EV,and AC
E) TCPI,EV,and PV
Question
The cost variance for a project is calculated by

A) EV - AC.
B) AC - SV.
C) PV - EV.
D) CV - EV.
E) EV - PV.
Question
Baseline project budgets are derived from

A) The organization's overall budget.
B) Time-phasing the work packages.
C) Top management directions.
D) The total direct,direct project overhead and G&A overhead costs.
E) The earned value system.
Question
The third step in the project control process for measuring and evaluating project performance is to

A) Review the baseline plan with top management.
B) Analyze inputs to the control system.
C) Compare the plan against actual performance.
D) Measure both progress and performance.
E) Review spending with team members.
Question
The earned value of a project is the

A) Project cost to date adjusted for project scope changes.
B) Total project cost to date.
C) Cost incurred minus the planned cost.
D) Percent of the original budget that has been earned by actual work.
E) The planned time-phased baseline of the value of work scheduled.
Question
The earned value system starts with the time-phased costs that provide the project baseline,which is called the

A) Planned budgeted value of work scheduled.
B) Planned budgeted value of work completed.
C) Earned value of work scheduled.
D) Scheduled value of work scheduled.
E) Scheduled value of work completed.
Question
Jim receives the following information on his project: PV = 1000,EV = 1200,AC = 800,BAC = 2000,EAC = 1333.How is the project doing in terms of schedule?

A) More work has been done than planned
B) Less work has been done than planned
C) The same amount of work has been done than planned
D) The project has cost less than planned
E) There is not enough information to draw a conclusion
Question
Because of their easy-to-understand visual format,________ charts are the most favored,used,and understandable tool used to report project schedule status.
Question
The value that tells you the planned value of the actual work completed is ___________.
Question
Which of the following methods will measure the scheduling efficiency of the work accomplished to date?

A) SV/CV
B) EV/PV
C) EV/AC
D) AC/SV
E) AC/CV
Question
Sally receives the following information on her project: PV = 100,AC = 75,EV = 100.How well is the project doing in terms of budget?

A) Right on budget
B) 25 under budget
C) 25 over budget
D) 50 under budget
E) 50 over budget
Question
________ is simply the percent complete times the original budget.
Question
A project manager notices that $1,000 worth of work that was scheduled to be completed at this time has not been accomplished.They know this by looking at the

A) EV.
B) TCPI.
C) SV.
D) PCIB.
E) EAC.
Question
Which of the following methods will measure the cost efficiency of the work accomplished to date?

A) SV/CV
B) EV/PV
C) EV/AC
D) AC/SV
E) AC/CV
Question
The indicator that tells you the amount each remaining dollar must earn in order for the project to stay within budget is the

A) PCIC.
B) VAC.
C) CPI.
D) SPI.
E) TCPI.
Question
The ________ variance is the difference between the earned value and the actual costs for the work completed to date.
Question
The value that tells you the planned value of work that has actually been completed is the

A) SV.
B) PV.
C) EV.
D) AC.
E) CV.
Question
A project manager learns that the project is only earning $.90 of planned work for each dollar spent by looking at the

A) EV.
B) BAC.
C) SV.
D) SPI.
E) CPI.
Question
________ holds people accountable,prevents small problems from mushrooming into large problems,and keeps focus.
Question
The first step in creating a project control system for measuring and evaluating project performance is to set a ________.
Question
When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains,they are creating a method for assigning costs to the baseline called the ____________ rule.
Question
Which of the following is NOT true regarding scope creep?

A) It commonly occurs late in projects
B) It is frequently unnoticed until time delays or cost overruns are observed
C) It wears down team motivation and cohesiveness
D) Project suppliers resent frequent changes
E) Scope changes can represent significant opportunity
Question
The indicator that tells you the planned time-phased value of the work that is scheduled is the _______________.
Question
Baseline project budgets are derived from time-phasing the work ________.
Question
A CPI or SPI value less than one indicates that the project is

A) Under cost or behind schedule.
B) Over cost or ahead of schedule.
C) Under cost or ahead of schedule.
D) Over cost or behind schedule.
E) On cost or on schedule.
Question
The ________ variance is the difference between the earned value to date and the baseline schedule.
Question
A negative CV indicates the project is ________ budget.
Question
The _________ index measures the project percent complete in relation to the resources that were budgeted.
Question
Because of their easy-to-understand visual format,tracking Gantt charts are the most favored,used,and understandable option for reporting project status.
Question
The baseline is derived from merging information from the work packages with the project network.
Question
Given that the AC = 300,PV = 400 and EV = 500,this project is _________ budget.
Question
Given a BAC of 5,500 and an EAC of 6,000,the project is expected to be completed _________ budget.
Question
Schedule variance measures progress in time units.
Question
Although it is very difficult to measure,measuring ________ performance is as important as measuring schedule and cost performance.
Question
The only accurate method for determining the true time progress of the project is to compare the project network schedule against the actual network schedule to measure if the project is on time.
Question
Earned value is defined as the budgeted cost of the actual work performed.
Question
The ratio that measures the amount of value each remaining dollar in the budget must earn to stay within the budget is the _________.
Question
The PCIC index measures the project percent complete in relation to the resources that have actually been used so far on the project.
Question
The project network schedule is derived from the _______ and it serves as the baseline to compare against actual performance.
Question
In some cases,conditions or scope can change,which,in turn,will require a change in the baseline plan to recognize new information.
Question
Conditions or scope can change,which,in turn,will require a change to the __________ plan to recognize the new information.
Question
An SPI index of 1.22 indicates that the project is ________ of schedule.
Question
When revising the estimated cost at completion,there are two approaches.The EACre is determined by experts in the field and the EACf is a mathematical approach which assumes the CPI as the basis for forecasting cost at completion.
Question
The final step in the project control process for measuring and evaluating project performance is to take appropriate ________.
Question
The PV,AC and CV are all required to assess the current status of the project.
Question
The ________ rule assumes credit is earned for having performed the work once it is completed.This rule is usually used for work packages having very short durations.
Question
Identify the steps in creating a control process that measures and evaluates project performance.
Question
A project control system allows for comparing actual performance against plan to identify deviations;however,the system doesn't impact the quality of communication between stakeholders.
Question
A project manager would be glad to see a TCPI of 1.07.
Question
Although it is very difficult to measure,measuring technical performance is as important as measuring schedule and cost performance.
Question
A CPI index of 0.97 indicates that the project has spent less money than budgeted.
Question
Most changes will not result in serious scope changes and should be absorbed as positive or negative variances.
Question
What is the difference between a baseline Gantt chart and a tracking Gantt chart?
Question
A "rubber baseline" occurs when,in an effort to disguise poor performance,the baseline changes to constantly match results.
Question
A project manager learns that her project has an EV of 1200,AC of 1100 and PV of 1000.What can the project manager report regarding this project?
Question
An undesirable schedule variance always indicates that the project is running behind schedule.
Question
In calculating schedule variance and cost variance,a negative variance indicates a desirable condition,and a positive variance suggests problems.
Question
Baseline costs typically include labor,equipment,materials and direct overhead cost.
Question
Two major reasons for creating a baseline are to monitor and report progress and to estimate cash flow.
Question
Rachel notices that the current EV for her project is higher than both the PV and the AC.Rachel has reason to be concerned.
Question
Deciding what data to collect,actually collecting the data and analyzing it,and reporting this data are all parts of structuring a project monitoring information system.
Question
A negative VAC indicates that the project will be completed over budget.
Question
The best method for assigning costs to the baseline under the 50/50 rule is to establish frequent checkpoints over the duration of the work package and assign completion percentages in dollar terms.
Question
Progress and performance can be measured quantitatively as well as qualitatively.
Question
All scope changes that result in increased costs should be avoided.
Question
Conducting an earned value analysis requires three data elements.Identify the acronyms for each and describe what they are.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/88
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 13: Progress and Performance Measurement and Evaluation
1
In monitoring project time (schedule)performance,actual performance should be compared to

A) Budgets for the current year.
B) Top management's targets.
C) Project network schedule derived from the WBS/OBS.
D) Progress on similar past projects.
E) Previous status reports.
C
Explanation: A major goal of progress reporting is to catch any negative variances from plan as early as possible to determine if corrective action is necessary.Fortunately,monitoring schedule performance is relatively easy.The project network schedule,derived from the WBS/OBS,serves as the baseline to compare against actual performance.
2
A project monitoring system involves all of the following EXCEPT

A) Determining what data to collect.
B) Determining how,when,and who will collect the data.
C) Adjusting the data.
D) Analysis of the data.
E) Reporting current progress.
C
Explanation: A project monitoring system involves determining what data to collect;how,when,and who will collect the data;analysis of the data;and reporting current progress.
3
Nancy tells her supervisor that as of right now,$1.05 worth of work has been accomplished for each $1 worth of scheduled work.Nancy got this information from viewing the

A) SV.
B) TCPI.
C) CPI.
D) SPI.
E) PCIB.
D
Explanation: The SPI would tell Nancy that $1.05 worth of work has been accomplished for each $1 worth of scheduled work.
4
A ___________ Gantt chart is a simple and effective way to depict progress on a project.

A) Baseline
B) Control
C) Variance
D) Tracking
E) Simple
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
5
The second step in the project control process for measuring and evaluating project performance is to

A) Review the baseline plan with top management.
B) Analyze inputs to control system.
C) Compare plan against actual.
D) Measure progress and performance.
E) Review spending with team members.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
6
Which performance index is the most potentially misleading?

A) CPI
B) EV
C) CV
D) SV
E) EAC
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
7
Which of the following methods of variance analysis is the best indicator of how far off the budget a project will be at completion?

A) BAC
B) EAC
C) ETC
D) VAC
E) TCPI
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
8
Jessica just received the following information on her project: PV = 200,EV = 300,AC = 250,BAC = 1500,EAC = 1208.In terms of cost at completion.

A) The project will currently finish under budget.
B) The project will currently finish over budget.
C) The project will currently finish on budget.
D) The project will currently finish behind schedule.
E) There is insufficient information to draw conclusions.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
9
Of the following costs,which are NOT included in baseline?

A) Suppliers
B) Equipment
C) Labor
D) Budget reserves
E) Contractors
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
10
The first step in the project control process for measuring and evaluating project performance is to

A) Set a baseline plan.
B) Determine the project objectives.
C) Determine the project deliverables.
D) Analyze the project budget.
E) Review the project priority matrix.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
11
The final step in the project control process for measuring and evaluating project performance is to

A) Take appropriate action.
B) Prepare a report to top management.
C) Follow up on corrective action.
D) Measure progress and performance.
E) Review spending with team members.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
12
The schedule variance for a project is calculated by:

A) EV - AC
B) AC - SV
C) PV - EV
D) CV - EV
E) EV - PV
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
13
When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains,they are creating a method for assigning costs to the baseline called the

A) 0/100 percent rule.
B) Task complete rule.
C) Degree complete rule.
D) Work complete rule.
E) Percent complete rule.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
14
A tool used to monitor past project schedule performance and current performance,and to estimate future schedule trends is a simple line chart known as a

A) Project control chart.
B) Gantt chart.
C) PERT chart.
D) Network diagram.
E) Milestone chart.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
15
Which of the following are required to assess the current status of a project using the earned-value cost/schedule system?

A) BAC,EAC,and ETC
B) VAC,EAC,and BAC
C) CV,SV,and BAC
D) PV,EV,and AC
E) TCPI,EV,and PV
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
16
The cost variance for a project is calculated by

A) EV - AC.
B) AC - SV.
C) PV - EV.
D) CV - EV.
E) EV - PV.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
17
Baseline project budgets are derived from

A) The organization's overall budget.
B) Time-phasing the work packages.
C) Top management directions.
D) The total direct,direct project overhead and G&A overhead costs.
E) The earned value system.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
18
The third step in the project control process for measuring and evaluating project performance is to

A) Review the baseline plan with top management.
B) Analyze inputs to the control system.
C) Compare the plan against actual performance.
D) Measure both progress and performance.
E) Review spending with team members.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
19
The earned value of a project is the

A) Project cost to date adjusted for project scope changes.
B) Total project cost to date.
C) Cost incurred minus the planned cost.
D) Percent of the original budget that has been earned by actual work.
E) The planned time-phased baseline of the value of work scheduled.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
20
The earned value system starts with the time-phased costs that provide the project baseline,which is called the

A) Planned budgeted value of work scheduled.
B) Planned budgeted value of work completed.
C) Earned value of work scheduled.
D) Scheduled value of work scheduled.
E) Scheduled value of work completed.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
21
Jim receives the following information on his project: PV = 1000,EV = 1200,AC = 800,BAC = 2000,EAC = 1333.How is the project doing in terms of schedule?

A) More work has been done than planned
B) Less work has been done than planned
C) The same amount of work has been done than planned
D) The project has cost less than planned
E) There is not enough information to draw a conclusion
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
22
Because of their easy-to-understand visual format,________ charts are the most favored,used,and understandable tool used to report project schedule status.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
23
The value that tells you the planned value of the actual work completed is ___________.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
24
Which of the following methods will measure the scheduling efficiency of the work accomplished to date?

A) SV/CV
B) EV/PV
C) EV/AC
D) AC/SV
E) AC/CV
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
25
Sally receives the following information on her project: PV = 100,AC = 75,EV = 100.How well is the project doing in terms of budget?

A) Right on budget
B) 25 under budget
C) 25 over budget
D) 50 under budget
E) 50 over budget
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
26
________ is simply the percent complete times the original budget.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
27
A project manager notices that $1,000 worth of work that was scheduled to be completed at this time has not been accomplished.They know this by looking at the

A) EV.
B) TCPI.
C) SV.
D) PCIB.
E) EAC.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
28
Which of the following methods will measure the cost efficiency of the work accomplished to date?

A) SV/CV
B) EV/PV
C) EV/AC
D) AC/SV
E) AC/CV
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
29
The indicator that tells you the amount each remaining dollar must earn in order for the project to stay within budget is the

A) PCIC.
B) VAC.
C) CPI.
D) SPI.
E) TCPI.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
30
The ________ variance is the difference between the earned value and the actual costs for the work completed to date.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
31
The value that tells you the planned value of work that has actually been completed is the

A) SV.
B) PV.
C) EV.
D) AC.
E) CV.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
32
A project manager learns that the project is only earning $.90 of planned work for each dollar spent by looking at the

A) EV.
B) BAC.
C) SV.
D) SPI.
E) CPI.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
33
________ holds people accountable,prevents small problems from mushrooming into large problems,and keeps focus.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
34
The first step in creating a project control system for measuring and evaluating project performance is to set a ________.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
35
When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains,they are creating a method for assigning costs to the baseline called the ____________ rule.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
36
Which of the following is NOT true regarding scope creep?

A) It commonly occurs late in projects
B) It is frequently unnoticed until time delays or cost overruns are observed
C) It wears down team motivation and cohesiveness
D) Project suppliers resent frequent changes
E) Scope changes can represent significant opportunity
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
37
The indicator that tells you the planned time-phased value of the work that is scheduled is the _______________.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
38
Baseline project budgets are derived from time-phasing the work ________.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
39
A CPI or SPI value less than one indicates that the project is

A) Under cost or behind schedule.
B) Over cost or ahead of schedule.
C) Under cost or ahead of schedule.
D) Over cost or behind schedule.
E) On cost or on schedule.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
40
The ________ variance is the difference between the earned value to date and the baseline schedule.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
41
A negative CV indicates the project is ________ budget.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
42
The _________ index measures the project percent complete in relation to the resources that were budgeted.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
43
Because of their easy-to-understand visual format,tracking Gantt charts are the most favored,used,and understandable option for reporting project status.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
44
The baseline is derived from merging information from the work packages with the project network.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
45
Given that the AC = 300,PV = 400 and EV = 500,this project is _________ budget.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
46
Given a BAC of 5,500 and an EAC of 6,000,the project is expected to be completed _________ budget.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
47
Schedule variance measures progress in time units.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
48
Although it is very difficult to measure,measuring ________ performance is as important as measuring schedule and cost performance.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
49
The only accurate method for determining the true time progress of the project is to compare the project network schedule against the actual network schedule to measure if the project is on time.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
50
Earned value is defined as the budgeted cost of the actual work performed.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
51
The ratio that measures the amount of value each remaining dollar in the budget must earn to stay within the budget is the _________.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
52
The PCIC index measures the project percent complete in relation to the resources that have actually been used so far on the project.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
53
The project network schedule is derived from the _______ and it serves as the baseline to compare against actual performance.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
54
In some cases,conditions or scope can change,which,in turn,will require a change in the baseline plan to recognize new information.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
55
Conditions or scope can change,which,in turn,will require a change to the __________ plan to recognize the new information.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
56
An SPI index of 1.22 indicates that the project is ________ of schedule.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
57
When revising the estimated cost at completion,there are two approaches.The EACre is determined by experts in the field and the EACf is a mathematical approach which assumes the CPI as the basis for forecasting cost at completion.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
58
The final step in the project control process for measuring and evaluating project performance is to take appropriate ________.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
59
The PV,AC and CV are all required to assess the current status of the project.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
60
The ________ rule assumes credit is earned for having performed the work once it is completed.This rule is usually used for work packages having very short durations.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
61
Identify the steps in creating a control process that measures and evaluates project performance.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
62
A project control system allows for comparing actual performance against plan to identify deviations;however,the system doesn't impact the quality of communication between stakeholders.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
63
A project manager would be glad to see a TCPI of 1.07.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
64
Although it is very difficult to measure,measuring technical performance is as important as measuring schedule and cost performance.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
65
A CPI index of 0.97 indicates that the project has spent less money than budgeted.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
66
Most changes will not result in serious scope changes and should be absorbed as positive or negative variances.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
67
What is the difference between a baseline Gantt chart and a tracking Gantt chart?
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
68
A "rubber baseline" occurs when,in an effort to disguise poor performance,the baseline changes to constantly match results.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
69
A project manager learns that her project has an EV of 1200,AC of 1100 and PV of 1000.What can the project manager report regarding this project?
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
70
An undesirable schedule variance always indicates that the project is running behind schedule.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
71
In calculating schedule variance and cost variance,a negative variance indicates a desirable condition,and a positive variance suggests problems.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
72
Baseline costs typically include labor,equipment,materials and direct overhead cost.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
73
Two major reasons for creating a baseline are to monitor and report progress and to estimate cash flow.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
74
Rachel notices that the current EV for her project is higher than both the PV and the AC.Rachel has reason to be concerned.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
75
Deciding what data to collect,actually collecting the data and analyzing it,and reporting this data are all parts of structuring a project monitoring information system.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
76
A negative VAC indicates that the project will be completed over budget.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
77
The best method for assigning costs to the baseline under the 50/50 rule is to establish frequent checkpoints over the duration of the work package and assign completion percentages in dollar terms.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
78
Progress and performance can be measured quantitatively as well as qualitatively.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
79
All scope changes that result in increased costs should be avoided.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
80
Conducting an earned value analysis requires three data elements.Identify the acronyms for each and describe what they are.
Unlock Deck
Unlock for access to all 88 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 88 flashcards in this deck.