Exam 13: Progress and Performance Measurement and Evaluation
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection87 Questions
Exam 3: Organization: Structure and Culture90 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk86 Questions
Exam 8: Scheduling Resources and Costs91 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects95 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management86 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
The schedule variance for a project is calculated by:
Free
(Multiple Choice)
4.9/5
(44)
Correct Answer:
E
In monitoring project time (schedule)performance,actual performance should be compared to
Free
(Multiple Choice)
4.8/5
(36)
Correct Answer:
C
What is scope creep and how does it impact project control?
Free
(Not Answered)
This question doesn't have any answer yet
Two major reasons for creating a baseline are to monitor and report progress and to estimate cash flow.
(True/False)
4.8/5
(34)
The PCIC index measures the project percent complete in relation to the resources that have actually been used so far on the project.
(True/False)
4.8/5
(25)
What is a "rubber baseline" and how does it undermine project control?
(Not Answered)
This question doesn't have any answer yet
Deciding what data to collect,actually collecting the data and analyzing it,and reporting this data are all parts of structuring a project monitoring information system.
(True/False)
4.7/5
(36)
A negative VAC indicates that the project will be completed over budget.
(True/False)
4.8/5
(29)
The ________ variance is the difference between the earned value to date and the baseline schedule.
(Short Answer)
4.9/5
(35)
The value that tells you the planned value of work that has actually been completed is the
(Multiple Choice)
4.9/5
(42)
The second step in the project control process for measuring and evaluating project performance is to
(Multiple Choice)
4.9/5
(38)
The value that tells you the planned value of the actual work completed is ___________.
(Short Answer)
4.9/5
(34)
In some cases,conditions or scope can change,which,in turn,will require a change in the baseline plan to recognize new information.
(True/False)
4.8/5
(31)
Rachel notices that the current EV for her project is higher than both the PV and the AC.Rachel has reason to be concerned.
(True/False)
4.8/5
(30)
Given a BAC of 5,500 and an EAC of 6,000,the project is expected to be completed _________ budget.
(Short Answer)
4.8/5
(32)
The final step in the project control process for measuring and evaluating project performance is to
(Multiple Choice)
4.9/5
(36)
Conducting an earned value analysis requires three data elements.Identify the acronyms for each and describe what they are.
(Not Answered)
This question doesn't have any answer yet
When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains,they are creating a method for assigning costs to the baseline called the
(Multiple Choice)
4.8/5
(21)