The schedule variance for a project is calculated by:

Free
(Multiple Choice)
4.9/5
(44)
Correct Answer:
Verified

E

In monitoring project time (schedule)performance,actual performance should be compared to

Free
(Multiple Choice)
4.8/5
(36)
Correct Answer:
Verified

C

What is scope creep and how does it impact project control?

Free
(Not Answered)
This question doesn't have any answer yet
Ask our community

Two major reasons for creating a baseline are to monitor and report progress and to estimate cash flow.

(True/False)
4.8/5
(34)

The PCIC index measures the project percent complete in relation to the resources that have actually been used so far on the project.

(True/False)
4.8/5
(25)

What is a "rubber baseline" and how does it undermine project control?

(Not Answered)
This question doesn't have any answer yet
Ask our community

Deciding what data to collect,actually collecting the data and analyzing it,and reporting this data are all parts of structuring a project monitoring information system.

(True/False)
4.7/5
(36)

A negative VAC indicates that the project will be completed over budget.

(True/False)
4.8/5
(29)

The ________ variance is the difference between the earned value to date and the baseline schedule.

(Short Answer)
4.9/5
(35)

The value that tells you the planned value of work that has actually been completed is the

(Multiple Choice)
4.9/5
(42)

The second step in the project control process for measuring and evaluating project performance is to

(Multiple Choice)
4.9/5
(38)

Of the following costs,which are NOT included in baseline?

(Multiple Choice)
4.8/5
(29)

The value that tells you the planned value of the actual work completed is ___________.

(Short Answer)
4.9/5
(34)

In some cases,conditions or scope can change,which,in turn,will require a change in the baseline plan to recognize new information.

(True/False)
4.8/5
(31)

Rachel notices that the current EV for her project is higher than both the PV and the AC.Rachel has reason to be concerned.

(True/False)
4.8/5
(30)

Given a BAC of 5,500 and an EAC of 6,000,the project is expected to be completed _________ budget.

(Short Answer)
4.8/5
(32)

The final step in the project control process for measuring and evaluating project performance is to

(Multiple Choice)
4.9/5
(36)

Conducting an earned value analysis requires three data elements.Identify the acronyms for each and describe what they are.

(Not Answered)
This question doesn't have any answer yet
Ask our community

Baseline project budgets are derived from

(Multiple Choice)
4.8/5
(30)

When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains,they are creating a method for assigning costs to the baseline called the