Deck 9: Reducing Project Duration

Full screen (f)
exit full mode
Question
In selecting the best activity to crash you would first select the activity with the

A) Earliest start time.
B) Most steep slope.
C) Least steep slope.
D) Longest duration.
E) Largest crash time.
Use Space or
up arrow
down arrow
to flip the card.
Question
When reducing project duration,the duration for a project that is optimal is at the point where

A) Direct costs are the lowest.
B) Indirect costs are the lowest.
C) Direct costs equal indirect costs.
D) Total project costs are the lowest.
E) The project changes from time-constrained to resource-constrained.
Question
As a project is crashed and project duration is reduced,indirect costs typically

A) Increase.
B) Become unstable.
C) Decrease.
D) Become unreliable.
E) Stay the same.
Question
Cost slope can be determined by dividing the

A) Run by the rise.
B) Rise by the run.
C) Crash cost by the normal cost.
D) Normal cost by the crash cost.
E) Indirect cost by direct cost.
Question
Without any formal planning,the president of a software company remarks in a speech that new technologically advanced software will be available in one year.This may lead to a project that must be done faster than anticipated.This is an example of reducing project duration caused by

A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.
Question
An activity's crash cost includes ________ costs.

A) Direct
B) Indirect
C) Overhead
D) Total
E) Normal
Question
The direct cost for completing an activity in the shortest time it can realistically be completed in is called its __________ cost.

A) Normal
B) Reserve
C) Crash
D) Accelerated
E) Expedited
Question
Emily has recently learned that she needs to reduce the duration of her project to meet an imposed deadline.She has calculated the crash cost per unit and knows the maximum units each activity can be reduced.What is the next step?

A) Find the activity with the lowest crash cost
B) Calculate the optimum cost-time point
C) Calculate the crash point
D) Identify the critical path
E) Find the activity with the highest crash cost
Question
Intense global competition and rapid technological advances create pressure to develop projects rapidly.This is an example of reducing project duration caused by

A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.
Question
Which of the following correctly calculates an activity's cost slope?

A) (normal cost - crash cost)/(normal time - crash time)
B) (crash cost - normal cost)/(normal time - crash time)
C) (normal time - crash time)/(crash cost - normal cost)
D) (normal time - crash time)/(normal cost - crash cost)
E) (crash cost - normal cost)/(crash time - normal time)
Question
The less steep the cost slope of an activity,the

A) Less it costs to shorten one time period.
B) More it costs to shorten one time period.
C) Smaller the crash time is.
D) Larger the crash time is.
E) Cannot be determined by the information given.
Question
When reducing project duration,the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known.After this,the critical path must be identified.What is the next step?

A) Find the activity with the lowest crash cost
B) Calculate the optimum cost-time point
C) Calculate the crash point
D) Calculate indirect cost per time unit
E) Find the activity with the steepest cost slope
Question
When determining which activity to crash,there are other factors that should be assessed beyond cost.Which of the following is NOT one of these factors?

A) The inherent risk associated with the activity
B) How crashing will impact the morale and motivation of the individuals working on that activity
C) Resource availability after crashing that activity
D) The level of difficulty involved in completing the activity
E) When during the project the activity will occur
Question
Before crashing,direct costs for an activity represent normal costs,which typically mean low-cost,efficient methods for completing the activity in a(n)________ amount of time.

A) Normal
B) Budgeted
C) Optimized
D) Expected
E) Targeted
Question
The shortest possible time an activity can be completed realistically is called ___­­­_____ time.

A) Expedited
B) Accelerated
C) Crash
D) Optimistic
E) Optimal
Question
As a project is crashed and project duration is reduced,direct costs typically

A) Increase.
B) Become unstable.
C) Decrease.
D) Become unreliable.
E) Stay the same.
Question
Which of the following is NOT considered a project indirect cost?

A) Supervision
B) Consultants
C) Equipment
D) Interest
E) The project manager's salary
Question
Adverse weather,design flaws,and equipment breakdown can create negative slack.This is an example of reducing project duration caused by

A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.
Question
In a Project Cost-Duration Graph,total project costs are a sum of

A) Labor,material and equipment costs.
B) Direct costs plus interest.
C) Direct labor costs and the project manager's salary.
D) Direct costs and the project manager's salary.
E) Direct and indirect costs.
Question
A contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion.This is an example of reducing project duration caused by

A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.
Question
Which of the following is NOT a rational reason to reduce project duration?

A) Incentive contracts
B) High network sensitivity
C) Imposed deadlines
D) High overhead costs
E) Unforeseen delays
Question
Which of the following projects would be least benefited if additional resources were added?

A) Splitting and stacking a cord of wood
B) Developing new software
C) Harvesting a crop by hand
D) Building a cabin
E) Moving to a new house
Question
All of the following are disadvantages of scheduling overtime EXCEPT

A) Overtime is associated the with additional costs of coordination and communication.
B) Sustained overtime work by salaried employees may incur burnout.
C) Productivity is reduced the longer one is working.
D) More hours results in higher expenses if paying workers hourly.
E) Continued overtime can lead to a higher turnover rate.
Question
One way of reducing project costs is identifying tasks that _________ can do themselves.

A) Vendors
B) Suppliers
C) Customers
D) Company employees
E) Project teams
Question
Sometimes very high __________ costs are recognized before a project begins and reducing these costs through shorter project durations becomes a high priority.

A) Labor
B) Direct
C) Project
D) Overhead
E) Interest
Question
The relationship between the normal point and the crash point is assumed to be

A) Linear.
B) Curvilinear.
C) Variable.
D) Conversely related.
E) Exponentially related.
Question
Intense global competition and rapid technological advances combine to create a(n)________-imposed project duration date.
Question
When a project manager must reduce project duration but resources are constrained,creating a software program that will have fewer features than originally planned or building a house without the bonus room the owner originally specified in the plans would both be examples of

A) Fast-tracking.
B) Using critical-chain project management.
C) Reducing project scope.
D) Compromising quality.
E) Doing it twice-first fast and then correctly.
Question
When it is necessary to reduce project duration and resources are constrained,which of the following is NOT a reasonable option?

A) Establishing a core project team
B) Fast-tracking
C) Reduce project scope
D) Compromise quality
E) Critical-chain project management
Question
Which of the following is NOT a technique for accelerating project completion when resources are not constrained?

A) Assign additional staff and equipment
B) Establish a core team
C) Do it twice-first fast and then correctly
D) Reduce project scope
E) Compromise quality
Question
Without any formal planning,the president of a software company remarks in a speech that new technologically advanced software will be available in one year.This may lead to a project that must be done faster than anticipated.The completion date has been __________.
Question
It is going to cost $80,000 a day simply to house and feed a construction crew in the farthest reaches of northern Alaska.This would be an example of a situation requiring reducing the project duration due to

A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.
Question
Which of the following is NOT one of the more commonly used options for cutting project costs?

A) Reduce project scope
B) Have owner take more responsibility
C) Move the completion date further out
D) Brainstorm cost savings options
E) Outsource project activities
Question
There are fewer options available for reducing project time if you are __________________ than if you can spend more than your original budget.
Question
Reducing project duration

A) Involves crashing all activities to their crash point.
B) Can only be done when resources are not constrained.
C) Is always more expensive.
D) Tends to increase network sensitivity.
E) Should be considered for all projects.
Question
The ________ project cost is the sum of the indirect and direct costs.
Question
According to Brooks' Law,adding more people to a late project is most likely to have which of the following impacts?

A) Keep the project from slipping any further
B) Get the project back on schedule
C) Make the project slip further
D) Lead to burnout
E) Decrease team motivation
Question
Sometimes very high ________ costs are recognized before a project begins and reducing these costs through shorter project duration becomes a high priority.
Question
An activity's normal time and cost are 8 and $100,respectively.Its estimated crash time and cost are 6 and $160,respectively.What is this activity's crash cost per time unit?

A) $33
B) $30
C) $60
D) $65
E) $153
Question
When the project team is salaried,which of the following is the preferred choice for accelerating project completion?

A) Assigning additional staff and equipment
B) Subcontract work
C) Schedule overtime
D) Outsource project work
E) Establish a core project team
Question
When considering whether to move the project to its optimum cost-time position,the manager should also consider ________.
Question
There are more options available for reducing project time if you are not resource constrained.
Question
Direct costs are assignable directly to a particular ________.
Question
In order to shorten the duration of a project the project manager should limit the choices of activities to just those which are on the __________.
Question
____________ is the rearranging of the project network logic so that critical activities are done in parallel rather than sequentially.
Question
As a project's duration is reduced,indirect costs are ___________.
Question
Because direct costs are assumed to be developed from normal methods and in a normal amount of time,any reduction in activity time should ________ the cost of the activity.
Question
The less steep the cost slope of an activity,the ________ it costs to shorten one time period.
Question
Overhead costs such as supervision,administration,consultants,and interest are examples of ________ project costs.
Question
When you schedule ________,you avoid the additional costs of coordination and communication when new people are added.
Question
According to ________ law,adding more manpower to a late software project makes it later.
Question
The ________ time for an activity represents low-costs,realistic,efficient methods for completing the activity under typical conditions.
Question
Costs such as labor,materials,equipment,or contractors are examples of ________ project costs.
Question
An activity's ________ is calculated by dividing the rise by the run.
Question
When project managers know an activity's ________,they are able to compare which critical activities to shorten.
Question
Reducing the duration of an activity is called ________.
Question
The direct cost for completing an activity as early as possible is called its ________ cost.
Question
Creation of the ___________ graph keeps the importance of indirect costs in the forefront of decision making.
Question
One way of reducing project costs is identifying tasks that _________ can do themselves.
Question
An activity's normal time and cost are 5 and $40,respectively.Its estimated crash time and cost are 4 and $70,respectively.This activity's crash cost per time unit is ________.
Question
Indirect costs generally represent overhead costs such as supervision,administration,consultants,and interest.
Question
The total cost for each time unit of a project is the sum of labor,materials,and equipment.
Question
Crashing can negatively impact the morale and motivation of the project team.
Question
Crashing a more expensive activity may be wise if fewer inherent risks are involved.
Question
Incentive contracts can make the reduction of project time rewarding-usually for both the project contractor and owner.
Question
Direct costs are so named because they can be assigned directly to a work package and activity.
Question
When reducing project duration,there will always be an optimum cost-time point where the total cost of the project is less than it was when the project was initially planned under normal conditions.
Question
An activity must be crashed on each critical path in order to reduce project duration.
Question
Managers have several effective methods for crashing specific project activities when resources are not constrained.
Question
When adding resources,there are limits as to how much speed can be gained.
Question
Total cost for specific project durations is computed and then compared with the benefits of reducing project time,before the project begins or while it is in progress.
Question
When crashing an activity,you always crash to its crash point.
Question
Shortening an activity's duration is termed crashing.
Question
Because direct costs are assumed to be developed from "normal" methods and in a "normal" amount of time,any reduction in activity time should add to the costs of the activity.
Question
The cost slope of an activity is calculated by dividing the run by the rise.
Question
If indirect costs are a significant percentage of total project costs,reductions in project time can represent very real savings.
Question
Brooks' law states that adding manpower to a software project helps keep it on schedule.
Question
Crashing frequently results in overallocation of resources.
Question
The accuracy of crash times and costs is frequently rough at best,when compared with normal time and cost.
Question
The higher the cost slope of an activity the lower the cost to reduce its duration.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/94
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 9: Reducing Project Duration
1
In selecting the best activity to crash you would first select the activity with the

A) Earliest start time.
B) Most steep slope.
C) Least steep slope.
D) Longest duration.
E) Largest crash time.
C
Explanation: The less steep the cost slope of an activity,the less it costs to shorten one time period.
2
When reducing project duration,the duration for a project that is optimal is at the point where

A) Direct costs are the lowest.
B) Indirect costs are the lowest.
C) Direct costs equal indirect costs.
D) Total project costs are the lowest.
E) The project changes from time-constrained to resource-constrained.
D
Explanation: The optimum cost-time point for a project is when the total project costs are the lowest.
3
As a project is crashed and project duration is reduced,indirect costs typically

A) Increase.
B) Become unstable.
C) Decrease.
D) Become unreliable.
E) Stay the same.
C
Explanation: Indirect costs vary with time.That is,any reduction in time should result in a reduction of indirect costs.
4
Cost slope can be determined by dividing the

A) Run by the rise.
B) Rise by the run.
C) Crash cost by the normal cost.
D) Normal cost by the crash cost.
E) Indirect cost by direct cost.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
5
Without any formal planning,the president of a software company remarks in a speech that new technologically advanced software will be available in one year.This may lead to a project that must be done faster than anticipated.This is an example of reducing project duration caused by

A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
6
An activity's crash cost includes ________ costs.

A) Direct
B) Indirect
C) Overhead
D) Total
E) Normal
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
7
The direct cost for completing an activity in the shortest time it can realistically be completed in is called its __________ cost.

A) Normal
B) Reserve
C) Crash
D) Accelerated
E) Expedited
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
8
Emily has recently learned that she needs to reduce the duration of her project to meet an imposed deadline.She has calculated the crash cost per unit and knows the maximum units each activity can be reduced.What is the next step?

A) Find the activity with the lowest crash cost
B) Calculate the optimum cost-time point
C) Calculate the crash point
D) Identify the critical path
E) Find the activity with the highest crash cost
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
9
Intense global competition and rapid technological advances create pressure to develop projects rapidly.This is an example of reducing project duration caused by

A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
10
Which of the following correctly calculates an activity's cost slope?

A) (normal cost - crash cost)/(normal time - crash time)
B) (crash cost - normal cost)/(normal time - crash time)
C) (normal time - crash time)/(crash cost - normal cost)
D) (normal time - crash time)/(normal cost - crash cost)
E) (crash cost - normal cost)/(crash time - normal time)
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
11
The less steep the cost slope of an activity,the

A) Less it costs to shorten one time period.
B) More it costs to shorten one time period.
C) Smaller the crash time is.
D) Larger the crash time is.
E) Cannot be determined by the information given.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
12
When reducing project duration,the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known.After this,the critical path must be identified.What is the next step?

A) Find the activity with the lowest crash cost
B) Calculate the optimum cost-time point
C) Calculate the crash point
D) Calculate indirect cost per time unit
E) Find the activity with the steepest cost slope
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
13
When determining which activity to crash,there are other factors that should be assessed beyond cost.Which of the following is NOT one of these factors?

A) The inherent risk associated with the activity
B) How crashing will impact the morale and motivation of the individuals working on that activity
C) Resource availability after crashing that activity
D) The level of difficulty involved in completing the activity
E) When during the project the activity will occur
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
14
Before crashing,direct costs for an activity represent normal costs,which typically mean low-cost,efficient methods for completing the activity in a(n)________ amount of time.

A) Normal
B) Budgeted
C) Optimized
D) Expected
E) Targeted
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
15
The shortest possible time an activity can be completed realistically is called ___­­­_____ time.

A) Expedited
B) Accelerated
C) Crash
D) Optimistic
E) Optimal
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
16
As a project is crashed and project duration is reduced,direct costs typically

A) Increase.
B) Become unstable.
C) Decrease.
D) Become unreliable.
E) Stay the same.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
17
Which of the following is NOT considered a project indirect cost?

A) Supervision
B) Consultants
C) Equipment
D) Interest
E) The project manager's salary
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
18
Adverse weather,design flaws,and equipment breakdown can create negative slack.This is an example of reducing project duration caused by

A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
19
In a Project Cost-Duration Graph,total project costs are a sum of

A) Labor,material and equipment costs.
B) Direct costs plus interest.
C) Direct labor costs and the project manager's salary.
D) Direct costs and the project manager's salary.
E) Direct and indirect costs.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
20
A contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion.This is an example of reducing project duration caused by

A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
21
Which of the following is NOT a rational reason to reduce project duration?

A) Incentive contracts
B) High network sensitivity
C) Imposed deadlines
D) High overhead costs
E) Unforeseen delays
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
22
Which of the following projects would be least benefited if additional resources were added?

A) Splitting and stacking a cord of wood
B) Developing new software
C) Harvesting a crop by hand
D) Building a cabin
E) Moving to a new house
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
23
All of the following are disadvantages of scheduling overtime EXCEPT

A) Overtime is associated the with additional costs of coordination and communication.
B) Sustained overtime work by salaried employees may incur burnout.
C) Productivity is reduced the longer one is working.
D) More hours results in higher expenses if paying workers hourly.
E) Continued overtime can lead to a higher turnover rate.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
24
One way of reducing project costs is identifying tasks that _________ can do themselves.

A) Vendors
B) Suppliers
C) Customers
D) Company employees
E) Project teams
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
25
Sometimes very high __________ costs are recognized before a project begins and reducing these costs through shorter project durations becomes a high priority.

A) Labor
B) Direct
C) Project
D) Overhead
E) Interest
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
26
The relationship between the normal point and the crash point is assumed to be

A) Linear.
B) Curvilinear.
C) Variable.
D) Conversely related.
E) Exponentially related.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
27
Intense global competition and rapid technological advances combine to create a(n)________-imposed project duration date.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
28
When a project manager must reduce project duration but resources are constrained,creating a software program that will have fewer features than originally planned or building a house without the bonus room the owner originally specified in the plans would both be examples of

A) Fast-tracking.
B) Using critical-chain project management.
C) Reducing project scope.
D) Compromising quality.
E) Doing it twice-first fast and then correctly.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
29
When it is necessary to reduce project duration and resources are constrained,which of the following is NOT a reasonable option?

A) Establishing a core project team
B) Fast-tracking
C) Reduce project scope
D) Compromise quality
E) Critical-chain project management
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
30
Which of the following is NOT a technique for accelerating project completion when resources are not constrained?

A) Assign additional staff and equipment
B) Establish a core team
C) Do it twice-first fast and then correctly
D) Reduce project scope
E) Compromise quality
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
31
Without any formal planning,the president of a software company remarks in a speech that new technologically advanced software will be available in one year.This may lead to a project that must be done faster than anticipated.The completion date has been __________.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
32
It is going to cost $80,000 a day simply to house and feed a construction crew in the farthest reaches of northern Alaska.This would be an example of a situation requiring reducing the project duration due to

A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
33
Which of the following is NOT one of the more commonly used options for cutting project costs?

A) Reduce project scope
B) Have owner take more responsibility
C) Move the completion date further out
D) Brainstorm cost savings options
E) Outsource project activities
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
34
There are fewer options available for reducing project time if you are __________________ than if you can spend more than your original budget.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
35
Reducing project duration

A) Involves crashing all activities to their crash point.
B) Can only be done when resources are not constrained.
C) Is always more expensive.
D) Tends to increase network sensitivity.
E) Should be considered for all projects.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
36
The ________ project cost is the sum of the indirect and direct costs.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
37
According to Brooks' Law,adding more people to a late project is most likely to have which of the following impacts?

A) Keep the project from slipping any further
B) Get the project back on schedule
C) Make the project slip further
D) Lead to burnout
E) Decrease team motivation
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
38
Sometimes very high ________ costs are recognized before a project begins and reducing these costs through shorter project duration becomes a high priority.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
39
An activity's normal time and cost are 8 and $100,respectively.Its estimated crash time and cost are 6 and $160,respectively.What is this activity's crash cost per time unit?

A) $33
B) $30
C) $60
D) $65
E) $153
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
40
When the project team is salaried,which of the following is the preferred choice for accelerating project completion?

A) Assigning additional staff and equipment
B) Subcontract work
C) Schedule overtime
D) Outsource project work
E) Establish a core project team
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
41
When considering whether to move the project to its optimum cost-time position,the manager should also consider ________.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
42
There are more options available for reducing project time if you are not resource constrained.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
43
Direct costs are assignable directly to a particular ________.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
44
In order to shorten the duration of a project the project manager should limit the choices of activities to just those which are on the __________.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
45
____________ is the rearranging of the project network logic so that critical activities are done in parallel rather than sequentially.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
46
As a project's duration is reduced,indirect costs are ___________.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
47
Because direct costs are assumed to be developed from normal methods and in a normal amount of time,any reduction in activity time should ________ the cost of the activity.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
48
The less steep the cost slope of an activity,the ________ it costs to shorten one time period.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
49
Overhead costs such as supervision,administration,consultants,and interest are examples of ________ project costs.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
50
When you schedule ________,you avoid the additional costs of coordination and communication when new people are added.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
51
According to ________ law,adding more manpower to a late software project makes it later.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
52
The ________ time for an activity represents low-costs,realistic,efficient methods for completing the activity under typical conditions.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
53
Costs such as labor,materials,equipment,or contractors are examples of ________ project costs.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
54
An activity's ________ is calculated by dividing the rise by the run.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
55
When project managers know an activity's ________,they are able to compare which critical activities to shorten.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
56
Reducing the duration of an activity is called ________.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
57
The direct cost for completing an activity as early as possible is called its ________ cost.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
58
Creation of the ___________ graph keeps the importance of indirect costs in the forefront of decision making.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
59
One way of reducing project costs is identifying tasks that _________ can do themselves.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
60
An activity's normal time and cost are 5 and $40,respectively.Its estimated crash time and cost are 4 and $70,respectively.This activity's crash cost per time unit is ________.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
61
Indirect costs generally represent overhead costs such as supervision,administration,consultants,and interest.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
62
The total cost for each time unit of a project is the sum of labor,materials,and equipment.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
63
Crashing can negatively impact the morale and motivation of the project team.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
64
Crashing a more expensive activity may be wise if fewer inherent risks are involved.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
65
Incentive contracts can make the reduction of project time rewarding-usually for both the project contractor and owner.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
66
Direct costs are so named because they can be assigned directly to a work package and activity.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
67
When reducing project duration,there will always be an optimum cost-time point where the total cost of the project is less than it was when the project was initially planned under normal conditions.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
68
An activity must be crashed on each critical path in order to reduce project duration.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
69
Managers have several effective methods for crashing specific project activities when resources are not constrained.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
70
When adding resources,there are limits as to how much speed can be gained.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
71
Total cost for specific project durations is computed and then compared with the benefits of reducing project time,before the project begins or while it is in progress.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
72
When crashing an activity,you always crash to its crash point.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
73
Shortening an activity's duration is termed crashing.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
74
Because direct costs are assumed to be developed from "normal" methods and in a "normal" amount of time,any reduction in activity time should add to the costs of the activity.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
75
The cost slope of an activity is calculated by dividing the run by the rise.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
76
If indirect costs are a significant percentage of total project costs,reductions in project time can represent very real savings.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
77
Brooks' law states that adding manpower to a software project helps keep it on schedule.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
78
Crashing frequently results in overallocation of resources.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
79
The accuracy of crash times and costs is frequently rough at best,when compared with normal time and cost.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
80
The higher the cost slope of an activity the lower the cost to reduce its duration.
Unlock Deck
Unlock for access to all 94 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 94 flashcards in this deck.