Exam 9: Reducing Project Duration

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

As a project is crashed and project duration is reduced,direct costs typically

Free
(Multiple Choice)
4.9/5
(31)
Correct Answer:
Verified

A

Costs such as labor,materials,equipment,or contractors are examples of ________ project costs.

Free
(Short Answer)
4.8/5
(29)
Correct Answer:
Verified

direct
Explanation: Direct costs commonly represent labor,materials,equipment,and sometimes subcontractors.Direct costs are assigned directly to a work package and activity.

An activity's ________ is calculated by dividing the rise by the run.

Free
(Short Answer)
4.9/5
(31)
Correct Answer:
Verified

slope
Explanation: Cost Slope = Rise/Run.

What if cost,not time,is the issue? What are some options available to project managers? Identify and briefly describe three.

(Not Answered)
This question doesn't have any answer yet
Ask our community

Given that an activity's normal time and cost are 10 days and $400,respectively,and its crash time and cost are 5 days and $800,respectively,what is the activity's slope?

(Not Answered)
This question doesn't have any answer yet
Ask our community

Which of the following is NOT a technique for accelerating project completion when resources are not constrained?

(Multiple Choice)
4.9/5
(28)

Emily has recently learned that she needs to reduce the duration of her project to meet an imposed deadline.She has calculated the crash cost per unit and knows the maximum units each activity can be reduced.What is the next step?

(Multiple Choice)
4.8/5
(39)

When adding resources,there are limits as to how much speed can be gained.

(True/False)
4.7/5
(40)

Crashing can negatively impact the morale and motivation of the project team.

(True/False)
4.8/5
(33)

The relationship between the normal point and the crash point is assumed to be

(Multiple Choice)
4.7/5
(37)

In selecting the best activity to crash you would first select the activity with the

(Multiple Choice)
4.7/5
(38)

Without any formal planning,the president of a software company remarks in a speech that new technologically advanced software will be available in one year.This may lead to a project that must be done faster than anticipated.The completion date has been __________.

(Short Answer)
4.8/5
(30)

Which of the following is NOT a rational reason to reduce project duration?

(Multiple Choice)
4.9/5
(36)

The accuracy of crash times and costs is frequently rough at best,when compared with normal time and cost.

(True/False)
4.8/5
(35)

Adverse weather,design flaws,and equipment breakdown can create negative slack.This is an example of reducing project duration caused by

(Multiple Choice)
4.8/5
(37)

Cost slope can be determined by dividing the

(Multiple Choice)
4.9/5
(34)

In a Project Cost-Duration Graph,total project costs are a sum of

(Multiple Choice)
4.9/5
(31)

How is the optimum cost-time point determined? What are the conditions that must exist for one to be present at a project duration other than the duration originally created under normal conditions?

(Not Answered)
This question doesn't have any answer yet
Ask our community

Which of the following is NOT considered a project indirect cost?

(Multiple Choice)
4.9/5
(37)

When reducing project duration,the duration for a project that is optimal is at the point where

(Multiple Choice)
4.7/5
(32)
Showing 1 - 20 of 94