Deck 8: Scheduling Resources and Costs

Full screen (f)
exit full mode
Question
All resource leveling techniques involve

A) Delaying noncritical activities.
B) Delaying critical activities.
C) Using negative slack.
D) Delaying the project.
E) Adding resources.
Use Space or
up arrow
down arrow
to flip the card.
Question
Jan is trying to reallocate resources in a time-constrained project to create smoother resource utilization.She should first identify activities with the

A) Smallest duration.
B) Least slack.
C) Most slack.
D) Lowest identification number.
E) Highest cost.
Question
Most of the scheduling methods available today require the project manager to classify the project as either _______ constrained or ______ constrained.

A) Time,quality
B) Quality,resource
C) Cost,time
D) Quality,cost
E) Time,resource
Question
In reviewing the status of her project with top management,Shirley was told that there are only two programmers that she can use for her project.Her project is classified as __________ constrained.

A) Time
B) Quality
C) Cost
D) Performance
E) Resource
Question
Rachel is working on a project that technically allows three activities to be done at the same time.If they were to be implemented at the same time,she would need 5 contractors in order for the activities to be completed on time.There are only 3 available for her to use.This is an example of what type of constraint?

A) Technical
B) People
C) Equipment
D) Physical
E) Materials
Question
Resources are adequate,but demand varies widely over the life of the project.Delaying noncritical activities to lower peak demand on resources is known as resource

A) Shifting.
B) Effectiveness.
C) Manipulating.
D) Smoothing.
E) Allocation.
Question
Sam,the project engineer,has been scheduled to run the product system test at the same time he is to build a marketing prototype.This is an example of what type of resource constraint?

A) Physical
B) Technical
C) People
D) Equipment
E) Time
Question
Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test.This is an example of a constraint that could impact the sequence and timing of activities in a project network.What type of constraint is it?

A) Physical
B) Technical
C) Resource
D) Scheduling
E) Time
Question
Technical constraints have been carefully considered when developing a project network.Which of the following is true at this point?

A) Resources have been assigned to each activity so they are adequate to complete the project on time
B) Technical dependencies between activities are known
C) The project completion date can be established
D) The project is ready to be implemented
E) All of these are true statements once technical constraints have been established
Question
Regina's boss has told her that her project is very important.If the critical path is delayed,she will be given whatever she needs to get it back on schedule.Her project is classified as ________ constrained.

A) Time
B) Quality
C) Cost
D) Performance
E) Resource
Question
When developing a new software package,logically,the software must be designed before the code is written,and the code must be written before it is tested.These activities are dependent on each other by _________ constraints.

A) Physical
B) Technical
C) Resource
D) Schedule
E) Time
Question
Resource leveling or smoothing can have all the following results on a project EXCEPT

A) Lower peak resource demand.
B) Reduced resource need over the life of the project.
C) Reduced fluctuations in resource demand.
D) A longer project duration.
E) A more sensitive network.
Question
All of the following are types of resource constraints EXCEPT

A) Materials.
B) People.
C) Equipment.
D) Information.
E) Human.
Question
Gene is trying to order the concrete needed to continue his project.However,the supplier will not be able to deliver it until next week.This is an example of what kind of resource constraint?

A) Working capital
B) People
C) Equipment
D) Information
E) Materials
Question
When considering the sequence and timing of activities,which of the following is NOT one of the types of project network constraints?

A) Physical
B) Technical
C) Resource
D) Time
E) All of these are types of constraints that could impact structure of the project network
Question
A special truck that George needs on his project has been scheduled on another project.This is an example of what type of resource constraint?

A) Working capital
B) People
C) Equipment
D) Information
E) Materials
Question
In a resource-constrained project,which of the following is most likely to be changed?

A) The completion date
B) The budget
C) Project quality
D) Resource levels
E) Scope creep
Question
Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation?

A) Activity delays
B) Project delays
C) Difficulty in taking quick corrective action
D) Increase costs
E) Scope creep
Question
In a resource-constrained project,the first priority in assigning resources is usually given to activities with the

A) Smallest duration.
B) Least slack.
C) Most slack.
D) Lowest identification number.
E) Highest cost.
Question
If resources are not adequate to meet peak demands,the resulting reschedule is termed

A) Resource-constrained scheduling.
B) Time-constrained scheduling.
C) Mandatory leveling.
D) Project resource adjustment.
E) Allocation.
Question
If three copiers are needed to produce a final report on time and only two are available,the project is facing a(n)________ type of resource constraint.
Question
A(n)________ constraint addresses the sequence in which project activities must occur even after considering resource constraints.
Question
A shortage of programmers to write software is an example of a(n)________ type of resource constraint.
Question
These are all guidelines a project manager should consider when assigning project work EXCEPT

A) Select people with compatible work habits and personalities.
B) Always assign the best people to the most difficult tasks.
C) When possible,team veterans up with new hires.
D) Select individuals with skillsets that complement each other.
E) Have people work together early so that they can become familiar with each other.
Question
All of the following are benefits of scheduling resources before project implementation EXCEPT

A) It allows time for considering reasonable options if resource constraints do exist.
B) The project completion date can be established.
C) Work packages can be time-phased.
D) It allows managers to share resources with other project managers if it is requested without negatively impacting their project.
E) It ensures low network sensitivity.
Question
Splitting an activity can result in all of the following EXCEPT

A) More people working on the same activity.
B) Possible startup and shutdown costs.
C) A resource being moved from one activity to another and then back.
D) Activity work being placed on hold for a period until more resources are available.
E) A better project schedule.
Question
Trying to renovate a ship compartment that is too small for more than one person is an example of a(n)________ resource constraint.
Question
Resource dependency takes priority over the technological dependency but does not violate ___________ dependencies.
Question
The shortage of computer chips to produce a circuit board is an example of a(n)________ type of resource constraint.
Question
Project budgets are developed by time-phasing which of the following?

A) Resource schedules
B) Work packages
C) The network diagram
D) Critical activities
E) None of these are time-phased to develop a project budget
Question
In order that the new product is on the shelf for the Christmas buying season,the development of the new product would be classified as a(n)________ -constrained project.
Question
Having one person responsible for performing several activities,all due at the same time,is an example of a(n)________ constraint.
Question
When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is called

A) Outsourcing.
B) Redistribution of projects.
C) Project allocation.
D) Task sharing.
E) Referring.
Question
Which of the following is NOT one of the more common problems associated with scheduling multiproject resources?

A) Overall schedule slippage
B) Inefficient resource utilization
C) Decline in project quality
D) Resource bottlenecks
E) Delays in one project causing delays in other projects
Question
Delaying noncritical activities to lower peak demand and,thus,increase resource utilization is called resource __________.
Question
A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000.Which of the following is true?

A) We are spending less than we should for the project
B) We are doing a good job managing the project
C) We should check to see if all the bills have been paid
D) We have more money to put into budget reserves
E) We can't be sure how the project is going
Question
Tony has realized that two activities in his project cannot be done at the same time because not enough resources are available.Activity 3 is critical and has a duration of 5 days.Activity 4 has 2 days of slack and a duration of 2 days.How will he decide which activity should be scheduled first?

A) The activity with the smallest duration
B) The activity with the least slack
C) The activity with the most slack
D) The activity with the lowest identification number
E) The activity with the highest cost
Question
Why is it necessary to have a time-phased budget baseline?

A) It allows proper resource allocation
B) It shows how much work was accomplished for the money spent
C) It reduces schedule slippage when scheduling multiproject resources
D) It is not necessary to have a time-phased budget baseline
E) It reduces fluctuations in cash flow during the project
Question
In a resource-constrained project the third priority in assigning resources is usually given to activities with the

A) Smallest duration.
B) Least slack.
C) Most slack.
D) Lowest identification number.
E) Highest cost.
Question
In a resource-constrained project the second priority in assigning resources is usually given to activities with the

A) Smallest duration.
B) Least slack.
C) Most slack.
D) Lowest identification number.
E) Highest cost.
Question
After resource leveling or smoothing one goal is that the amount of resources needed over the life of the project will be ___________.
Question
The fact that you must pour foundation before you frame the house and that you have to frame the house before you can put on the roof demonstrates scheduling constraints.
Question
A project cost baseline is also called __________.
Question
Beth has two engineers assigned to her project and does not have access to more even if the result means extending the completion date on her project.She is managing a(n)________ -constrained project.
Question
Since resource leveling or smoothing delays noncritical activities,a common result is an increase in network ___________.
Question
When a project is classified as resource-constrained and a resource constraint exists,the project duration is typically __________.
Question
Resource bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules.
Question
The level of resources each activity will need to be completed in the given amount of time has been estimated;therefore,there are no resource constraints.
Question
When scheduling activities in a resource-constrained project,typically the activity scheduled first has the __________ amount of slack.
Question
Startup and shutdown costs are major considerations when using the ________________ scheduling technique.
Question
In reality resource allocation generally occurs in a(n)___________ environment where the demands of one project have to be reconciled with the needs of other projects.
Question
Without a __________ budget a good project schedule and cost control are impossible.
Question
Resource leveling or smoothing is only used on projects which are resource constrained.
Question
All leveling techniques delay noncritical activities by using ________ to reduce peak demand.
Question
Many companies are ________ project work to contractors and consultants as a means of dealing with the peaks and valleys of resource allocation among projects.
Question
When the work in an activity is interrupted to work on another activity and is then resumed at a later point in time,it is called _________.
Question
When classifying projects,________ constrained means that project duration is fixed and resources are flexible.
Question
In scheduling resource-constrained projects,_________ are typically used rather than optimum mathematical solutions.
Question
When classifying projects,________ constrained means that a specific resource is fixed and the duration of the project is flexible.
Question
Too many parallel activities for one individual is an example of a resource constraint.
Question
Sequential activities hold just as much potential for resource conflicts as parallel activities.
Question
When resource constraints are added to technical constraints the original project network may change as well as the completion date.
Question
Having too few programmers and too many engineers is an example of a people resource constraint.
Question
Since resource leveling or smoothing delays noncritical activities,a common result is a decrease in network sensitivity.
Question
The inability to fit more than two earth movers on a construction site at the same time when more are needed to complete the activity on time is an example of a physical constraint.
Question
What is the difference in project goals when using resource leveling on time-constrained projects and using it on resource-constrained projects?
Question
A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000.We can assume that everything is going as planned and that we are under budget.
Question
In a resource-constrained project,the completion date is most likely to change.
Question
To determine if a project is time-constrained or resource-constrained you would consult the project priority matrix.
Question
Identify and briefly describe the three types of project constraints that could impact or change the structure of project network.
Question
Resource dependency takes priority over technological dependency but it does not violate it.
Question
Project managers should always assign the best people to the most difficult tasks.
Question
When scheduling activities in a resource-constrained project typically the activity scheduled first has the most amount of slack.
Question
Splitting is a scheduling technique used to get a better schedule or better resource utilization and should be used without hesitation.
Question
Without a time-phased budget a good project schedule and cost control are impossible.
Question
A lack of readily available engineers is a technical constraint.
Question
All leveling techniques delay noncritical activities by using positive slack to smooth out the resource requirements.
Question
If a project needs one earth mover six months from now in order to complete one activity,and the organization has four such machines,there is no equipment resource constraint.
Question
Scheduling projects classified as resource-constrained focuses on completing the project as soon as possible under the given resource constraints.
Question
If resources are truly limited and activity time estimates are accurate,the resource-constrained schedule will materialize as the project is implemented,not the time-constrained schedule.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/91
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 8: Scheduling Resources and Costs
1
All resource leveling techniques involve

A) Delaying noncritical activities.
B) Delaying critical activities.
C) Using negative slack.
D) Delaying the project.
E) Adding resources.
A
Explanation: All leveling techniques delay noncritical activities by using positive slack to reduce peak demand and fill in the valleys for the resources.
2
Jan is trying to reallocate resources in a time-constrained project to create smoother resource utilization.She should first identify activities with the

A) Smallest duration.
B) Least slack.
C) Most slack.
D) Lowest identification number.
E) Highest cost.
C
Explanation: Activities with the most slack may be delayed to reduce the level of resources needed at a particular time.
3
Most of the scheduling methods available today require the project manager to classify the project as either _______ constrained or ______ constrained.

A) Time,quality
B) Quality,resource
C) Cost,time
D) Quality,cost
E) Time,resource
E
Explanation: Most of the scheduling methods available today require the project manager to classify the project as either time constrained or resource constrained.
4
In reviewing the status of her project with top management,Shirley was told that there are only two programmers that she can use for her project.Her project is classified as __________ constrained.

A) Time
B) Quality
C) Cost
D) Performance
E) Resource
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
5
Rachel is working on a project that technically allows three activities to be done at the same time.If they were to be implemented at the same time,she would need 5 contractors in order for the activities to be completed on time.There are only 3 available for her to use.This is an example of what type of constraint?

A) Technical
B) People
C) Equipment
D) Physical
E) Materials
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
6
Resources are adequate,but demand varies widely over the life of the project.Delaying noncritical activities to lower peak demand on resources is known as resource

A) Shifting.
B) Effectiveness.
C) Manipulating.
D) Smoothing.
E) Allocation.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
7
Sam,the project engineer,has been scheduled to run the product system test at the same time he is to build a marketing prototype.This is an example of what type of resource constraint?

A) Physical
B) Technical
C) People
D) Equipment
E) Time
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
8
Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test.This is an example of a constraint that could impact the sequence and timing of activities in a project network.What type of constraint is it?

A) Physical
B) Technical
C) Resource
D) Scheduling
E) Time
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
9
Technical constraints have been carefully considered when developing a project network.Which of the following is true at this point?

A) Resources have been assigned to each activity so they are adequate to complete the project on time
B) Technical dependencies between activities are known
C) The project completion date can be established
D) The project is ready to be implemented
E) All of these are true statements once technical constraints have been established
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
10
Regina's boss has told her that her project is very important.If the critical path is delayed,she will be given whatever she needs to get it back on schedule.Her project is classified as ________ constrained.

A) Time
B) Quality
C) Cost
D) Performance
E) Resource
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
11
When developing a new software package,logically,the software must be designed before the code is written,and the code must be written before it is tested.These activities are dependent on each other by _________ constraints.

A) Physical
B) Technical
C) Resource
D) Schedule
E) Time
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
12
Resource leveling or smoothing can have all the following results on a project EXCEPT

A) Lower peak resource demand.
B) Reduced resource need over the life of the project.
C) Reduced fluctuations in resource demand.
D) A longer project duration.
E) A more sensitive network.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
13
All of the following are types of resource constraints EXCEPT

A) Materials.
B) People.
C) Equipment.
D) Information.
E) Human.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
14
Gene is trying to order the concrete needed to continue his project.However,the supplier will not be able to deliver it until next week.This is an example of what kind of resource constraint?

A) Working capital
B) People
C) Equipment
D) Information
E) Materials
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
15
When considering the sequence and timing of activities,which of the following is NOT one of the types of project network constraints?

A) Physical
B) Technical
C) Resource
D) Time
E) All of these are types of constraints that could impact structure of the project network
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
16
A special truck that George needs on his project has been scheduled on another project.This is an example of what type of resource constraint?

A) Working capital
B) People
C) Equipment
D) Information
E) Materials
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
17
In a resource-constrained project,which of the following is most likely to be changed?

A) The completion date
B) The budget
C) Project quality
D) Resource levels
E) Scope creep
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
18
Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation?

A) Activity delays
B) Project delays
C) Difficulty in taking quick corrective action
D) Increase costs
E) Scope creep
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
19
In a resource-constrained project,the first priority in assigning resources is usually given to activities with the

A) Smallest duration.
B) Least slack.
C) Most slack.
D) Lowest identification number.
E) Highest cost.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
20
If resources are not adequate to meet peak demands,the resulting reschedule is termed

A) Resource-constrained scheduling.
B) Time-constrained scheduling.
C) Mandatory leveling.
D) Project resource adjustment.
E) Allocation.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
21
If three copiers are needed to produce a final report on time and only two are available,the project is facing a(n)________ type of resource constraint.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
22
A(n)________ constraint addresses the sequence in which project activities must occur even after considering resource constraints.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
23
A shortage of programmers to write software is an example of a(n)________ type of resource constraint.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
24
These are all guidelines a project manager should consider when assigning project work EXCEPT

A) Select people with compatible work habits and personalities.
B) Always assign the best people to the most difficult tasks.
C) When possible,team veterans up with new hires.
D) Select individuals with skillsets that complement each other.
E) Have people work together early so that they can become familiar with each other.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
25
All of the following are benefits of scheduling resources before project implementation EXCEPT

A) It allows time for considering reasonable options if resource constraints do exist.
B) The project completion date can be established.
C) Work packages can be time-phased.
D) It allows managers to share resources with other project managers if it is requested without negatively impacting their project.
E) It ensures low network sensitivity.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
26
Splitting an activity can result in all of the following EXCEPT

A) More people working on the same activity.
B) Possible startup and shutdown costs.
C) A resource being moved from one activity to another and then back.
D) Activity work being placed on hold for a period until more resources are available.
E) A better project schedule.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
27
Trying to renovate a ship compartment that is too small for more than one person is an example of a(n)________ resource constraint.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
28
Resource dependency takes priority over the technological dependency but does not violate ___________ dependencies.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
29
The shortage of computer chips to produce a circuit board is an example of a(n)________ type of resource constraint.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
30
Project budgets are developed by time-phasing which of the following?

A) Resource schedules
B) Work packages
C) The network diagram
D) Critical activities
E) None of these are time-phased to develop a project budget
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
31
In order that the new product is on the shelf for the Christmas buying season,the development of the new product would be classified as a(n)________ -constrained project.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
32
Having one person responsible for performing several activities,all due at the same time,is an example of a(n)________ constraint.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
33
When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is called

A) Outsourcing.
B) Redistribution of projects.
C) Project allocation.
D) Task sharing.
E) Referring.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
34
Which of the following is NOT one of the more common problems associated with scheduling multiproject resources?

A) Overall schedule slippage
B) Inefficient resource utilization
C) Decline in project quality
D) Resource bottlenecks
E) Delays in one project causing delays in other projects
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
35
Delaying noncritical activities to lower peak demand and,thus,increase resource utilization is called resource __________.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
36
A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000.Which of the following is true?

A) We are spending less than we should for the project
B) We are doing a good job managing the project
C) We should check to see if all the bills have been paid
D) We have more money to put into budget reserves
E) We can't be sure how the project is going
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
37
Tony has realized that two activities in his project cannot be done at the same time because not enough resources are available.Activity 3 is critical and has a duration of 5 days.Activity 4 has 2 days of slack and a duration of 2 days.How will he decide which activity should be scheduled first?

A) The activity with the smallest duration
B) The activity with the least slack
C) The activity with the most slack
D) The activity with the lowest identification number
E) The activity with the highest cost
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
38
Why is it necessary to have a time-phased budget baseline?

A) It allows proper resource allocation
B) It shows how much work was accomplished for the money spent
C) It reduces schedule slippage when scheduling multiproject resources
D) It is not necessary to have a time-phased budget baseline
E) It reduces fluctuations in cash flow during the project
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
39
In a resource-constrained project the third priority in assigning resources is usually given to activities with the

A) Smallest duration.
B) Least slack.
C) Most slack.
D) Lowest identification number.
E) Highest cost.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
40
In a resource-constrained project the second priority in assigning resources is usually given to activities with the

A) Smallest duration.
B) Least slack.
C) Most slack.
D) Lowest identification number.
E) Highest cost.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
41
After resource leveling or smoothing one goal is that the amount of resources needed over the life of the project will be ___________.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
42
The fact that you must pour foundation before you frame the house and that you have to frame the house before you can put on the roof demonstrates scheduling constraints.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
43
A project cost baseline is also called __________.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
44
Beth has two engineers assigned to her project and does not have access to more even if the result means extending the completion date on her project.She is managing a(n)________ -constrained project.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
45
Since resource leveling or smoothing delays noncritical activities,a common result is an increase in network ___________.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
46
When a project is classified as resource-constrained and a resource constraint exists,the project duration is typically __________.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
47
Resource bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
48
The level of resources each activity will need to be completed in the given amount of time has been estimated;therefore,there are no resource constraints.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
49
When scheduling activities in a resource-constrained project,typically the activity scheduled first has the __________ amount of slack.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
50
Startup and shutdown costs are major considerations when using the ________________ scheduling technique.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
51
In reality resource allocation generally occurs in a(n)___________ environment where the demands of one project have to be reconciled with the needs of other projects.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
52
Without a __________ budget a good project schedule and cost control are impossible.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
53
Resource leveling or smoothing is only used on projects which are resource constrained.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
54
All leveling techniques delay noncritical activities by using ________ to reduce peak demand.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
55
Many companies are ________ project work to contractors and consultants as a means of dealing with the peaks and valleys of resource allocation among projects.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
56
When the work in an activity is interrupted to work on another activity and is then resumed at a later point in time,it is called _________.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
57
When classifying projects,________ constrained means that project duration is fixed and resources are flexible.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
58
In scheduling resource-constrained projects,_________ are typically used rather than optimum mathematical solutions.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
59
When classifying projects,________ constrained means that a specific resource is fixed and the duration of the project is flexible.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
60
Too many parallel activities for one individual is an example of a resource constraint.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
61
Sequential activities hold just as much potential for resource conflicts as parallel activities.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
62
When resource constraints are added to technical constraints the original project network may change as well as the completion date.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
63
Having too few programmers and too many engineers is an example of a people resource constraint.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
64
Since resource leveling or smoothing delays noncritical activities,a common result is a decrease in network sensitivity.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
65
The inability to fit more than two earth movers on a construction site at the same time when more are needed to complete the activity on time is an example of a physical constraint.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
66
What is the difference in project goals when using resource leveling on time-constrained projects and using it on resource-constrained projects?
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
67
A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000.We can assume that everything is going as planned and that we are under budget.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
68
In a resource-constrained project,the completion date is most likely to change.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
69
To determine if a project is time-constrained or resource-constrained you would consult the project priority matrix.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
70
Identify and briefly describe the three types of project constraints that could impact or change the structure of project network.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
71
Resource dependency takes priority over technological dependency but it does not violate it.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
72
Project managers should always assign the best people to the most difficult tasks.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
73
When scheduling activities in a resource-constrained project typically the activity scheduled first has the most amount of slack.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
74
Splitting is a scheduling technique used to get a better schedule or better resource utilization and should be used without hesitation.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
75
Without a time-phased budget a good project schedule and cost control are impossible.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
76
A lack of readily available engineers is a technical constraint.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
77
All leveling techniques delay noncritical activities by using positive slack to smooth out the resource requirements.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
78
If a project needs one earth mover six months from now in order to complete one activity,and the organization has four such machines,there is no equipment resource constraint.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
79
Scheduling projects classified as resource-constrained focuses on completing the project as soon as possible under the given resource constraints.
Unlock Deck
Unlock for access to all 91 flashcards in this deck.
Unlock Deck
k this deck
80
If resources are truly limited and activity time estimates are accurate,the resource-constrained schedule will materialize as the project is implemented,not the time-constrained schedule.