Exam 8: Scheduling Resources and Costs

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

What is the difference in project goals when using resource leveling on time-constrained projects and using it on resource-constrained projects?

Free
(Not Answered)
This question doesn't have any answer yet
Ask our community

Splitting an activity can result in all of the following EXCEPT

Free
(Multiple Choice)
4.8/5
(35)
Correct Answer:
Verified

A

Resource leveling or smoothing is only used on projects which are resource constrained.

Free
(True/False)
4.8/5
(37)
Correct Answer:
Verified

False

Resource dependency takes priority over technological dependency but it does not violate it.

(True/False)
4.8/5
(41)

Without a __________ budget a good project schedule and cost control are impossible.

(Short Answer)
4.8/5
(38)

A(n)________ constraint addresses the sequence in which project activities must occur even after considering resource constraints.

(Short Answer)
4.9/5
(28)

All leveling techniques delay noncritical activities by using positive slack to smooth out the resource requirements.

(True/False)
5.0/5
(33)

In a resource-constrained project the second priority in assigning resources is usually given to activities with the

(Multiple Choice)
4.9/5
(35)

Which of the following is NOT one of the more common problems associated with scheduling multiproject resources?

(Multiple Choice)
4.8/5
(37)

In a resource-constrained project the third priority in assigning resources is usually given to activities with the

(Multiple Choice)
4.7/5
(44)

Startup and shutdown costs are major considerations when using the ________________ scheduling technique.

(Short Answer)
4.9/5
(47)

Too many parallel activities for one individual is an example of a resource constraint.

(True/False)
4.9/5
(41)

When scheduling activities in a resource-constrained project,typically the activity scheduled first has the __________ amount of slack.

(Short Answer)
4.8/5
(36)

The inability to fit more than two earth movers on a construction site at the same time when more are needed to complete the activity on time is an example of a physical constraint.

(True/False)
4.9/5
(30)

Why is a schedule not a schedule until resources have been assigned? Provide a real life example that illustrates your explanation.

(Not Answered)
This question doesn't have any answer yet
Ask our community

When classifying projects,________ constrained means that a specific resource is fixed and the duration of the project is flexible.

(Short Answer)
4.8/5
(32)

Scheduling projects classified as resource-constrained focuses on completing the project as soon as possible under the given resource constraints.

(True/False)
4.9/5
(35)

If resources are truly limited and activity time estimates are accurate,the resource-constrained schedule will materialize as the project is implemented,not the time-constrained schedule.

(True/False)
4.9/5
(32)

All of the following are types of resource constraints EXCEPT

(Multiple Choice)
5.0/5
(31)

Sam,the project engineer,has been scheduled to run the product system test at the same time he is to build a marketing prototype.This is an example of what type of resource constraint?

(Multiple Choice)
4.9/5
(36)
Showing 1 - 20 of 91