Deck 7: Scheduling Activities

Full screen (f)
exit full mode
Question
The critical path is the sequence of activities that represent the shortest path through the project,which determines the shortest possible duration of the project.
Use Space or
up arrow
down arrow
to flip the card.
Question
When developing a project schedule,total float (or slack)refers to the amount of time a schedule activity may be delayed from its early start date without delaying the project finish date.
Question
The length of time to perform an activity is often dependent upon who will do that work.
Question
PERT refers to the Program Evaluation and Review Technique,which was developed in the 1950s to better understand how variability in the duration of individual activity durations impacts the entire project schedule.
Question
While the lowest level of decomposition in a Work Breakdown Structure is the work package,work packages can still be decomposed further into project activities.
Question
The first process in developing a project schedule is to identify all the resources available to work on the project.
Question
The enumeration method of determining the critical path relies upon identification of all paths through the project network.
Question
A mandatory dependency in a relationship that is contractually required or inherent in the nature of the work.
Question
Except in rare circumstances,project teams should not attempt to decompose work packages into project activities because work packages provide sufficient detail to develop a project schedule.
Question
A successor activity follows a predecessor activity based on their logical relationship.
Question
A Gantt chart is an easy-to-understand tool that can be used to communicate a project schedule.
Question
GANTT refers to the Generalized Activity Network Tracking Technique which was developed to better understand how variability in the duration of individual activities impacts the expected project duration.
Question
The primary advantage of PERT is that it removes uncertainty from the estimates of activity durations,thereby increasing confidence in the reliability of a project schedule.
Question
The most common type of logical dependency to determine the sequence of project activities is "finish-to-finish".
Question
There is often terrific pressure to complete a project as quickly as possible.To confront this pressure,a project manager should quickly promise to meet the deadlines requested by the sponsor and then assemble a team to create the corresponding schedule.
Question
Even small delays on "near-critical" activities can change the critical path of a project.
Question
Monte Carlo simulation is a process which generates hundreds of thousands of probable performance outcomes based on probability distributions for cost and schedule on individual tasks.
Question
The "start-to-start" logical relationship used in activity sequencing applies to the case in which a successor activity cannot start until a predecessor activity has started.
Question
In order for activities to be useful as schedule building blocks,they should have tangible output that can be verified.
Question
If a project manager delays the start of an activity on the critical path,then the expected completion date of the project will occur at a later date than originally planned.
Question
All of the following strategies can help a project team to develop realistic time estimates for project activities EXCEPT:

A) adding a significant buffer to each activity
B) be sure to consider learning curves,interruptions and competing priorities
C) estimate times of completion without initial reference to a calendar
D) verify the time estimates with the people doing the work
Question
Which of the following responses identifies a common type of logical dependency used to sequence project activities?

A) first-in; first-out
B) last-in; last-out
C) finish-to-start
D) last-in; first-out
Question
Creating a realistic schedule is often an iterative process because several factors can limit how fast a project can be completed.All of the following factors can limit how fast a project can be scheduled and completed EXCEPT:

A) logical order
B) imposed dates
C) resource availability
D) quality metrics
Question
The sequencing of activities is often based upon dependencies between the activities.The dependencies that should guide activity sequencing can be either:

A) critical or non-critical
B) opportunities or threats
C) mandatory or discretionary
D) interior or exterior
Question
All of the following problems contribute to difficulty in estimating activity durations accurately EXCEPT:

A) merging - multiple predecessors
B) omissions - leaving out key activities
C) general uncertainty in the estimate
D) poor vendor selection
Question
Figure 7-3 System Integration Project
<strong>Figure 7-3 System Integration Project   Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,what is the expected duration of this project?</strong> A) 15 days B) 16 days C) 17 days D) 30 days <div style=padding-top: 35px>
Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,what is the expected duration of this project?

A) 15 days
B) 16 days
C) 17 days
D) 30 days
Question
Figure 7-1 Assembly Project
Consider the Assembly Project depicted in Figure 7-1.Based on the information provided,what is the early start date for activity D - "Attach Modules 1 & 2"?

A) Day 0
B) Day 3
C) Day 4
D) Day 5
Question
Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the slack associated with activity C - "Review Reports"?

A) 0 days
B) 1 day
C) 2 days
D) 4 days
Question
Which of the following statements correctly describes the critical path?

A) The sequence of activities that represents the shortest path through the project network.
B) It determines the latest possible end date of the project.
C) It consists only of activities with zero float (slack).
D) It consists only of activities with lag times
Question
An activity that logically comes before a dependent activity in a schedule is called a ___:

A) leader activity
B) predecessor activity
C) successor activity
D) mandatory activity
Question
The total number of work periods (not including holidays or other non-work periods)required to complete a schedule activity is known as:

A) effort
B) elapsed time
C) duration
D) resource days
Question
All of the following items can provide useful assistance to a project team to define the activities of a project EXCEPT:

A) the work packages from the Work Breakdown Structure
B) issue logs
C) checklists for projects of the same type
D) schedules from similar projects that are already completed
Question
Estimating the number of work periods that will be needed to complete individual schedule activities characterizes which of the following time management processes?

A) Define activities
B) Sequence activities
C) Estimate activity duration
D) Create WBS
Question
Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity C - "Review Reports"?

A) Day 0
B) Day 2
C) Day 4
D) Day 10
Question
Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity A - "Plan Research"?

A) Day 0
B) Day 2
C) Day 4
D) Day 10
Question
Milestones are important points in a project schedule that can serve as check points for project managers and sponsors.All of the following reasons might justify the decision to establish a milestone EXCEPT:

A) completion of a major deliverable
B) the time right before a large amount of money needs to be committed
C) a merging point where multiple activities must be completed before progress can continue
D) scheduling team status meetings
Question
Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2.Based on the information provided,which activity can you delay by one day without impacting the expected completion date for the project?

A) Activity A
B) Activity B
C) Activity C
D) Activity D
Question
Which of the following remedies may reduce the likelihood of omissions when developing activity duration estimates?

A) lessons learned
B) resource buffers
C) learning curve
D) staggering project start dates
Question
Faced with significant schedule challenges,the project manager has several responsibilities.All of the following are among the project manager's responsibilities EXCEPT:

A) willingly accept end dates dictated by customers or sponsors
B) persuade all stakeholders that the schedule makes sense
C) deliver the project according to the agreed-upon schedule
D) determine a schedule that is possible to achieve
Question
The amount of time a schedule activity can be delayed without delaying the early start date of any successor is known as:

A) reserve
B) free float
C) contingency
D) lead
Question
Describe "slack" and how you can use slack to your advantage in managing a project.
Question
<strong>  Figure 7-4 Lab Experiment Project Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,which activity can be delayed one day without impacting the expected project completion date?</strong> A) Activity B - Calibrate Instruments B) Activity C - Review Studies C) Activity D - Monitor Instruments D) Activity E - Test Samples <div style=padding-top: 35px> Figure 7-4 Lab Experiment Project
Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,which activity can be delayed one day without impacting the expected project completion date?

A) Activity B - Calibrate Instruments
B) Activity C - Review Studies
C) Activity D - Monitor Instruments
D) Activity E - Test Samples
Question
<strong>  Figure 7-5 Duration Estimates Consider the activity duration estimates presented in Figure 7-5.Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - Package Item?</strong> A) 9 days B) 9.5 days C) 10 days D) 12 days <div style=padding-top: 35px> Figure 7-5 Duration Estimates
Consider the activity duration estimates presented in Figure 7-5.Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - "Package Item"?

A) 9 days
B) 9.5 days
C) 10 days
D) 12 days
Question
<strong>  Figure 7-4 Lab Experiment Project Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,what is the expected duration of this project?</strong> A) 22 days B) 24 days C) 26 days D) 28 days <div style=padding-top: 35px> Figure 7-4 Lab Experiment Project
Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,what is the expected duration of this project?

A) 22 days
B) 24 days
C) 26 days
D) 28 days
Question
Figure 7-3 System Integration Project
<strong>Figure 7-3 System Integration Project   Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,how many days can you delay the purchase of software (Activity C),without impacting the expected project completion date?</strong> A) 0 days B) 1 day C) 2 days D) 4 days <div style=padding-top: 35px>
Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,how many days can you delay the purchase of software (Activity C),without impacting the expected project completion date?

A) 0 days
B) 1 day
C) 2 days
D) 4 days
Question
<strong>  Figure 7-6 Network Scheduling Data Consider the network scheduling data provided in Figure 7-6.Which activities constitute the critical path for this project network?</strong> A) A-D-F-I B) A-C-E-H-I C) A-B-E-H-I D) A-B-E-G-I <div style=padding-top: 35px> Figure 7-6 Network Scheduling Data
Consider the network scheduling data provided in Figure 7-6.Which activities constitute the critical path for this project network?

A) A-D-F-I
B) A-C-E-H-I
C) A-B-E-H-I
D) A-B-E-G-I
Question
<strong>  Figure 7-6 Network Scheduling Data Consider the network scheduling data presented in Figure 7-6.How many days of slack are associated with activity F?</strong> A) 0 B) 15 C) 80 D) 107 <div style=padding-top: 35px> Figure 7-6 Network Scheduling Data
Consider the network scheduling data presented in Figure 7-6.How many days of slack are associated with activity F?

A) 0
B) 15
C) 80
D) 107
Question
<strong>  Figure 7-4 Lab Experiment Project Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,how many days can you delay the calibration of the instrumentation (Activity B),without impacting the expected project completion date?</strong> A) 0 days B) 1 day C) 2 days D) 4 days <div style=padding-top: 35px> Figure 7-4 Lab Experiment Project
Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,how many days can you delay the calibration of the instrumentation (Activity B),without impacting the expected project completion date?

A) 0 days
B) 1 day
C) 2 days
D) 4 days
Question
Figure 7-3 System Integration Project
<strong>Figure 7-3 System Integration Project   Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities constitute the critical path for this project?</strong> A) A-B-E-F B) A-C-E-F C) A-D-E-F D) A-D-F <div style=padding-top: 35px>
Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities constitute the critical path for this project?

A) A-B-E-F
B) A-C-E-F
C) A-D-E-F
D) A-D-F
Question
All of the following statements correctly describe an advantage or disadvantage associated with the use of Monte Carlo Analysis EXCEPT:

A) The flexibility of Monte Carlo Analysis allows for more realistic estimates.
B) Monte Carlo simulation aids in the identification of near-critical paths.
C) Monte Carlo simulations typically require the use of special software and skills.
D) Monte Carlo simulations do not consider risks
Question
Figure 7-3 System Integration Project
<strong>Figure 7-3 System Integration Project   Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities can be delayed one day without impacting the expected project completion date?</strong> A) Activity E - Install Software and Activity F - Test System B) Activity C - Purchase Software and Activity E - Install Software C) Activity C - Purchase Software and Activity D - Prepare Test Plan D) none of these <div style=padding-top: 35px>
Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities can be delayed one day without impacting the expected project completion date?

A) Activity E - Install Software and Activity F - Test System
B) Activity C - Purchase Software and Activity E - Install Software
C) Activity C - Purchase Software and Activity D - Prepare Test Plan
D) none of these
Question
<strong>  Figure 7-6 Network Scheduling Data Consider the network scheduling data provided in Figure 7-6.What is the expected duration of this project?</strong> A) 97 days B) 102 days C) 107 days D) 112 days <div style=padding-top: 35px> Figure 7-6 Network Scheduling Data
Consider the network scheduling data provided in Figure 7-6.What is the expected duration of this project?

A) 97 days
B) 102 days
C) 107 days
D) 112 days
Question
Despite the insights that PERT provides,there are still practical limitations that impact its usefulness.All of the following difficulties are associated with the use of PERT EXCEPT:

A) It often requires more effort to generate three estimates than one.
B) It highlights uncertainty in project duration
C) It does not accurately address the case when two activities both need to be accomplished before a third can begin.
D) There is no assurance that three estimates are any more accurate than one
Question
Describe how you would use the members of your project team to develop and execute a project schedule.
Question
Many factors can impact the accuracy of activity duration estimates.Describe four of the problems associated with estimating time accurately,and the techniques you would use as a project manager to overcome them.
Question
<strong>  Figure 7-4 Lab Experiment Project Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,identify the critical path(s)for this project?</strong> A) A-C-F only B) A-B-D-F only C) A-B-E-F only D) Both A-B-D-F and A-B-E-F are critical paths <div style=padding-top: 35px> Figure 7-4 Lab Experiment Project
Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,identify the critical path(s)for this project?

A) A-C-F only
B) A-B-D-F only
C) A-B-E-F only
D) Both A-B-D-F and A-B-E-F are critical paths
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/56
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 7: Scheduling Activities
1
The critical path is the sequence of activities that represent the shortest path through the project,which determines the shortest possible duration of the project.
False
2
When developing a project schedule,total float (or slack)refers to the amount of time a schedule activity may be delayed from its early start date without delaying the project finish date.
True
3
The length of time to perform an activity is often dependent upon who will do that work.
True
4
PERT refers to the Program Evaluation and Review Technique,which was developed in the 1950s to better understand how variability in the duration of individual activity durations impacts the entire project schedule.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
5
While the lowest level of decomposition in a Work Breakdown Structure is the work package,work packages can still be decomposed further into project activities.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
6
The first process in developing a project schedule is to identify all the resources available to work on the project.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
7
The enumeration method of determining the critical path relies upon identification of all paths through the project network.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
8
A mandatory dependency in a relationship that is contractually required or inherent in the nature of the work.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
9
Except in rare circumstances,project teams should not attempt to decompose work packages into project activities because work packages provide sufficient detail to develop a project schedule.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
10
A successor activity follows a predecessor activity based on their logical relationship.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
11
A Gantt chart is an easy-to-understand tool that can be used to communicate a project schedule.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
12
GANTT refers to the Generalized Activity Network Tracking Technique which was developed to better understand how variability in the duration of individual activities impacts the expected project duration.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
13
The primary advantage of PERT is that it removes uncertainty from the estimates of activity durations,thereby increasing confidence in the reliability of a project schedule.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
14
The most common type of logical dependency to determine the sequence of project activities is "finish-to-finish".
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
15
There is often terrific pressure to complete a project as quickly as possible.To confront this pressure,a project manager should quickly promise to meet the deadlines requested by the sponsor and then assemble a team to create the corresponding schedule.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
16
Even small delays on "near-critical" activities can change the critical path of a project.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
17
Monte Carlo simulation is a process which generates hundreds of thousands of probable performance outcomes based on probability distributions for cost and schedule on individual tasks.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
18
The "start-to-start" logical relationship used in activity sequencing applies to the case in which a successor activity cannot start until a predecessor activity has started.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
19
In order for activities to be useful as schedule building blocks,they should have tangible output that can be verified.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
20
If a project manager delays the start of an activity on the critical path,then the expected completion date of the project will occur at a later date than originally planned.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
21
All of the following strategies can help a project team to develop realistic time estimates for project activities EXCEPT:

A) adding a significant buffer to each activity
B) be sure to consider learning curves,interruptions and competing priorities
C) estimate times of completion without initial reference to a calendar
D) verify the time estimates with the people doing the work
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
22
Which of the following responses identifies a common type of logical dependency used to sequence project activities?

A) first-in; first-out
B) last-in; last-out
C) finish-to-start
D) last-in; first-out
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
23
Creating a realistic schedule is often an iterative process because several factors can limit how fast a project can be completed.All of the following factors can limit how fast a project can be scheduled and completed EXCEPT:

A) logical order
B) imposed dates
C) resource availability
D) quality metrics
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
24
The sequencing of activities is often based upon dependencies between the activities.The dependencies that should guide activity sequencing can be either:

A) critical or non-critical
B) opportunities or threats
C) mandatory or discretionary
D) interior or exterior
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
25
All of the following problems contribute to difficulty in estimating activity durations accurately EXCEPT:

A) merging - multiple predecessors
B) omissions - leaving out key activities
C) general uncertainty in the estimate
D) poor vendor selection
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
26
Figure 7-3 System Integration Project
<strong>Figure 7-3 System Integration Project   Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,what is the expected duration of this project?</strong> A) 15 days B) 16 days C) 17 days D) 30 days
Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,what is the expected duration of this project?

A) 15 days
B) 16 days
C) 17 days
D) 30 days
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
27
Figure 7-1 Assembly Project
Consider the Assembly Project depicted in Figure 7-1.Based on the information provided,what is the early start date for activity D - "Attach Modules 1 & 2"?

A) Day 0
B) Day 3
C) Day 4
D) Day 5
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
28
Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the slack associated with activity C - "Review Reports"?

A) 0 days
B) 1 day
C) 2 days
D) 4 days
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
29
Which of the following statements correctly describes the critical path?

A) The sequence of activities that represents the shortest path through the project network.
B) It determines the latest possible end date of the project.
C) It consists only of activities with zero float (slack).
D) It consists only of activities with lag times
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
30
An activity that logically comes before a dependent activity in a schedule is called a ___:

A) leader activity
B) predecessor activity
C) successor activity
D) mandatory activity
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
31
The total number of work periods (not including holidays or other non-work periods)required to complete a schedule activity is known as:

A) effort
B) elapsed time
C) duration
D) resource days
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
32
All of the following items can provide useful assistance to a project team to define the activities of a project EXCEPT:

A) the work packages from the Work Breakdown Structure
B) issue logs
C) checklists for projects of the same type
D) schedules from similar projects that are already completed
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
33
Estimating the number of work periods that will be needed to complete individual schedule activities characterizes which of the following time management processes?

A) Define activities
B) Sequence activities
C) Estimate activity duration
D) Create WBS
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
34
Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity C - "Review Reports"?

A) Day 0
B) Day 2
C) Day 4
D) Day 10
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
35
Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity A - "Plan Research"?

A) Day 0
B) Day 2
C) Day 4
D) Day 10
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
36
Milestones are important points in a project schedule that can serve as check points for project managers and sponsors.All of the following reasons might justify the decision to establish a milestone EXCEPT:

A) completion of a major deliverable
B) the time right before a large amount of money needs to be committed
C) a merging point where multiple activities must be completed before progress can continue
D) scheduling team status meetings
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
37
Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2.Based on the information provided,which activity can you delay by one day without impacting the expected completion date for the project?

A) Activity A
B) Activity B
C) Activity C
D) Activity D
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
38
Which of the following remedies may reduce the likelihood of omissions when developing activity duration estimates?

A) lessons learned
B) resource buffers
C) learning curve
D) staggering project start dates
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
39
Faced with significant schedule challenges,the project manager has several responsibilities.All of the following are among the project manager's responsibilities EXCEPT:

A) willingly accept end dates dictated by customers or sponsors
B) persuade all stakeholders that the schedule makes sense
C) deliver the project according to the agreed-upon schedule
D) determine a schedule that is possible to achieve
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
40
The amount of time a schedule activity can be delayed without delaying the early start date of any successor is known as:

A) reserve
B) free float
C) contingency
D) lead
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
41
Describe "slack" and how you can use slack to your advantage in managing a project.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
42
<strong>  Figure 7-4 Lab Experiment Project Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,which activity can be delayed one day without impacting the expected project completion date?</strong> A) Activity B - Calibrate Instruments B) Activity C - Review Studies C) Activity D - Monitor Instruments D) Activity E - Test Samples Figure 7-4 Lab Experiment Project
Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,which activity can be delayed one day without impacting the expected project completion date?

A) Activity B - Calibrate Instruments
B) Activity C - Review Studies
C) Activity D - Monitor Instruments
D) Activity E - Test Samples
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
43
<strong>  Figure 7-5 Duration Estimates Consider the activity duration estimates presented in Figure 7-5.Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - Package Item?</strong> A) 9 days B) 9.5 days C) 10 days D) 12 days Figure 7-5 Duration Estimates
Consider the activity duration estimates presented in Figure 7-5.Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - "Package Item"?

A) 9 days
B) 9.5 days
C) 10 days
D) 12 days
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
44
<strong>  Figure 7-4 Lab Experiment Project Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,what is the expected duration of this project?</strong> A) 22 days B) 24 days C) 26 days D) 28 days Figure 7-4 Lab Experiment Project
Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,what is the expected duration of this project?

A) 22 days
B) 24 days
C) 26 days
D) 28 days
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
45
Figure 7-3 System Integration Project
<strong>Figure 7-3 System Integration Project   Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,how many days can you delay the purchase of software (Activity C),without impacting the expected project completion date?</strong> A) 0 days B) 1 day C) 2 days D) 4 days
Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,how many days can you delay the purchase of software (Activity C),without impacting the expected project completion date?

A) 0 days
B) 1 day
C) 2 days
D) 4 days
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
46
<strong>  Figure 7-6 Network Scheduling Data Consider the network scheduling data provided in Figure 7-6.Which activities constitute the critical path for this project network?</strong> A) A-D-F-I B) A-C-E-H-I C) A-B-E-H-I D) A-B-E-G-I Figure 7-6 Network Scheduling Data
Consider the network scheduling data provided in Figure 7-6.Which activities constitute the critical path for this project network?

A) A-D-F-I
B) A-C-E-H-I
C) A-B-E-H-I
D) A-B-E-G-I
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
47
<strong>  Figure 7-6 Network Scheduling Data Consider the network scheduling data presented in Figure 7-6.How many days of slack are associated with activity F?</strong> A) 0 B) 15 C) 80 D) 107 Figure 7-6 Network Scheduling Data
Consider the network scheduling data presented in Figure 7-6.How many days of slack are associated with activity F?

A) 0
B) 15
C) 80
D) 107
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
48
<strong>  Figure 7-4 Lab Experiment Project Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,how many days can you delay the calibration of the instrumentation (Activity B),without impacting the expected project completion date?</strong> A) 0 days B) 1 day C) 2 days D) 4 days Figure 7-4 Lab Experiment Project
Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,how many days can you delay the calibration of the instrumentation (Activity B),without impacting the expected project completion date?

A) 0 days
B) 1 day
C) 2 days
D) 4 days
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
49
Figure 7-3 System Integration Project
<strong>Figure 7-3 System Integration Project   Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities constitute the critical path for this project?</strong> A) A-B-E-F B) A-C-E-F C) A-D-E-F D) A-D-F
Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities constitute the critical path for this project?

A) A-B-E-F
B) A-C-E-F
C) A-D-E-F
D) A-D-F
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
50
All of the following statements correctly describe an advantage or disadvantage associated with the use of Monte Carlo Analysis EXCEPT:

A) The flexibility of Monte Carlo Analysis allows for more realistic estimates.
B) Monte Carlo simulation aids in the identification of near-critical paths.
C) Monte Carlo simulations typically require the use of special software and skills.
D) Monte Carlo simulations do not consider risks
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
51
Figure 7-3 System Integration Project
<strong>Figure 7-3 System Integration Project   Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities can be delayed one day without impacting the expected project completion date?</strong> A) Activity E - Install Software and Activity F - Test System B) Activity C - Purchase Software and Activity E - Install Software C) Activity C - Purchase Software and Activity D - Prepare Test Plan D) none of these
Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities can be delayed one day without impacting the expected project completion date?

A) Activity E - Install Software and Activity F - Test System
B) Activity C - Purchase Software and Activity E - Install Software
C) Activity C - Purchase Software and Activity D - Prepare Test Plan
D) none of these
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
52
<strong>  Figure 7-6 Network Scheduling Data Consider the network scheduling data provided in Figure 7-6.What is the expected duration of this project?</strong> A) 97 days B) 102 days C) 107 days D) 112 days Figure 7-6 Network Scheduling Data
Consider the network scheduling data provided in Figure 7-6.What is the expected duration of this project?

A) 97 days
B) 102 days
C) 107 days
D) 112 days
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
53
Despite the insights that PERT provides,there are still practical limitations that impact its usefulness.All of the following difficulties are associated with the use of PERT EXCEPT:

A) It often requires more effort to generate three estimates than one.
B) It highlights uncertainty in project duration
C) It does not accurately address the case when two activities both need to be accomplished before a third can begin.
D) There is no assurance that three estimates are any more accurate than one
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
54
Describe how you would use the members of your project team to develop and execute a project schedule.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
55
Many factors can impact the accuracy of activity duration estimates.Describe four of the problems associated with estimating time accurately,and the techniques you would use as a project manager to overcome them.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
56
<strong>  Figure 7-4 Lab Experiment Project Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,identify the critical path(s)for this project?</strong> A) A-C-F only B) A-B-D-F only C) A-B-E-F only D) Both A-B-D-F and A-B-E-F are critical paths Figure 7-4 Lab Experiment Project
Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,identify the critical path(s)for this project?

A) A-C-F only
B) A-B-D-F only
C) A-B-E-F only
D) Both A-B-D-F and A-B-E-F are critical paths
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 56 flashcards in this deck.