Deck 14: Managing Projects

Full screen (f)
exit full mode
Question
An expectation that a new building's foundation would be poured and cured by the end of the year is an example of a(n):

A)activity.
B)scope.
C)milestone.
D)precedence.
Use Space or
up arrow
down arrow
to flip the card.
Question
In what ways are projects distinct from typical business activities?
Question
During the ________, project planners identify how to accomplish the work, how to organize for the project, and the key personnel and resources needed.
Question
A performance or time target for each major group of activities in a project is a(n)________.
Question
Execution of the project's constituent activities begins in the project's:

A)planning phase.
B)concept phase.
C)post-completion phase.
D)performance phase.
Question
A project is a temporary undertaking designed to create a unique, product, service or results.
Question
The Triskaidekaphobia Project is starting its tenth week and the Gantt chart appears below. Which of these statements about the project is incorrect? <strong>The Triskaidekaphobia Project is starting its tenth week and the Gantt chart appears below. Which of these statements about the project is incorrect?  </strong> A)The critical path is BCEF. B)Five of the activities are complete. C)Activity D had one week of slack. D)The project is behind schedule. <div style=padding-top: 35px>

A)The critical path is BCEF.
B)Five of the activities are complete.
C)Activity D had one week of slack.
D)The project is behind schedule.
Question
This Gantt chart can be used to show: <strong>This Gantt chart can be used to show:  </strong> A)activity D must come before activity C. B)activity F can be done at the same time as D. C)activity E can begin as soon as activity A is complete. D)activities D and B can be done simultaneously. <div style=padding-top: 35px>

A)activity D must come before activity C.
B)activity F can be done at the same time as D.
C)activity E can begin as soon as activity A is complete.
D)activities D and B can be done simultaneously.
Question
One of the primary characteristics of projects as a form of work is the movement of personnel from project to project.
Question
Discuss the recent business trends that have increased the attention and interest in project management skills.
Question
In what way are projects and typical business activities similar?

A)For most companies, projects and typical business activities can be described as routine.
B)Both projects and typical business activities have a defined ending point at which time they are complete.
C)Projects and routine business activities require significant levels of cross-functional and interorganizational coordination.
D)The successful completion of projects and business activities is essential to a firm's competitive position.
Question
Performance or time targets for each major group of activities in a project are set during the planning phase of a project.
Question
There are more resources required during the performance phase of a project than the project definition phase.
Question
Key points in a project, such as when a major activity or phase should be completed, are referred to as lodestones.
Question
PERT is an acronym meaning:

A)Project Evaluation and Review Technique.
B)Project Execution and Review Technique.
C)Program Evaluation and Review Technique.
D)Plan Estimation and Review Technique.
Question
Project planners develop a broad definition of what the project is and what its scope will be during the:

A)concept phase.
B)project definition phase.
C)planning phase.
D)performance phase.
Question
The actual work gets done during the ________ phase of a project.
Question
What are the phases of a project and the activities within each?
Question
The budget estimates made during the concept phase are usually accurate to within:

A)20 percent.
B)30 percent.
C)40 percent.
D)50 percent.
Question
In the project definition phase, project planners identify, among other tasks, how to accomplish the work and how to organize for the project.
Question
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A ā‹Æ712 B ā‹Æ8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. What is the earliest start time for activity H?

A)Week 14
B)Week 15
C)Week 16
D)Week 17
Question
A Gantt chart provides both a planning function and a control function.
Question
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements are listed in the table immediately below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A āˆ’7 B  A 6 C  A 10 D  C 12 E  B, C 5 F  D, E 11 G  F 8\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & - & 7 \\\hline \text { B } & \text { A } & 6 \\\hline \text { C } & \text { A } & 10 \\\hline \text { D } & \text { C } & 12 \\\hline \text { E } & \text { B, C } & 5 \\\hline \text { F } & \text { D, E } & 11 \\\hline \text { G } & \text { F } & 8 \\\hline\end{array}

-Refer to the scenario above. Which of these statements is BEST?

A)Only four of these activities have zero slack.
B)The late finish of D minus the latest finish of C is less than the slack of B.
C)B's latest start plus its slack equals F's latest finish.
D)The sum of the latest start times for activities A through E is less than the sum of the latest start times for F and G.
Question
A Gantt chart explicitly shows precedence requirements for a project's constituent activities.
Question
A project is composed of 6 activities that have durations and precedence requirements shown in the table. Which of these activities is NOT on the critical path?  Activity  Length  Predecessor  A 5⋯ B 7 A  C 4 A  D 7 B,C  E 7 B  F 6 D, E \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 5 & \cdots \\\hline \text { B } & 7 & \text { A } \\\hline \text { C } & 4 & \text { A } \\\hline \text { D } & 7 & \text { B,C } \\\hline \text { E } & 7 & \text { B } \\\hline \text { F } & 6 & \text { D, E } \\\hline\end{array}

A)A
B)B
C)C
D)D
Question
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A ā‹Æ10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array}

-Refer to the scenario above. The fastest the project can be completed is:

A)49 weeks
B)46 weeks
C)38 weeks
D)35 weeks
Question
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A ā‹Æ10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array}

-Refer to the scenario above. Which of these activities has the least slack?

A)E
B)B
C)G
D)F
Question
Program evaluation and review technique, PERT, is a network-based technique in which there are multiple time estimates for each activity.
Question
Most project management software represents a project in AON format.
Question
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A ā‹Æ10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array}

-Refer to the scenario above. What is the slack for activity G?

A)4 weeks
B)3 weeks
C)2 weeks
D)1 week
Question
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question.  Activity  Predecessors  Time (weeks)  A ā‹Æ10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array} Refer to the scenario above. One activity has identical earliest finish and latest start times. What is the common number for this unusual activity?

A)17
B)18
C)21
D)29
Question
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A ā‹Æ712 B ā‹Æ8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. What is the duration of activity H?

A)7 weeks
B)8 weeks
C)9 weeks
D)10 weeks
Question
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A ā‹Æ712 B ā‹Æ8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. What is the latest start time for activity K?

A)Week 20
B)Week 19
C)Week 18
D)Week 17
Question
What is the latest that activity B can start if A lasts 35 days, B lasts 5, days C lasts 6 days, and D lasts 7 days? <strong>What is the latest that activity B can start if A lasts 35 days, B lasts 5, days C lasts 6 days, and D lasts 7 days?  </strong> A)35 B)36 C)40 D)41 <div style=padding-top: 35px>

A)35
B)36
C)40
D)41
Question
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements are listed in the table immediately below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A āˆ’7 B  A 6 C  A 10 D  C 12 E  B, C 5 F  D, E 11 G  F 8\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & - & 7 \\\hline \text { B } & \text { A } & 6 \\\hline \text { C } & \text { A } & 10 \\\hline \text { D } & \text { C } & 12 \\\hline \text { E } & \text { B, C } & 5 \\\hline \text { F } & \text { D, E } & 11 \\\hline \text { G } & \text { F } & 8 \\\hline\end{array}

-Refer to the scenario above. Which of these activities has slack?

A)G
B)E
C)F
D)D
Question
What is the latest that activity D can start if A lasts 5 days, B lasts 7 days, C lasts 4 days, D lasts 5 days, E lasts 7 days, and F is 6 days long? <strong>What is the latest that activity D can start if A lasts 5 days, B lasts 7 days, C lasts 4 days, D lasts 5 days, E lasts 7 days, and F is 6 days long?  </strong> A)14 B)15 C)16 D)17 <div style=padding-top: 35px>

A)14
B)15
C)16
D)17
Question
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A ā‹Æ712 B ā‹Æ8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. What is the earliest finish time for activity G?

A)Week 21
B)Week 22
C)Week 23
D)Week 24
Question
What is the fastest completion time of the project with activity lengths (in days)and precedence requirements as shown in the table?  Activity  Length  Predecessor  A 15⋯ B 7 A  C 4 A  D 8 B, C \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 15 & \cdots \\\hline \text { B } & 7 & \text { A } \\\hline \text { C } & 4 & \text { A } \\\hline \text { D } & 8 & \text { B, C } \\\hline\end{array}

A)22
B)25
C)27
D)30
Question
Which of the activities in this project has the greatest amount of slack?  Activity  Length  Predecessor  A 7⋯ B 4 A  C 8 A  D 3B,C E 2B F 8 D, E \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 7 & \cdots \\\hline \text { B } & 4 & \text { A } \\\hline \text { C } & 8 & \text { A } \\\hline \text { D } & 3 & B , C \\\hline \text { E } & 2 & B \\\hline \text { F } & 8 & \text { D, E } \\\hline\end{array}

A)B
B)C
C)D
D)E
Question
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A ā‹Æ712 B ā‹Æ8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. The project's duration is:

A)32 weeks.
B)33 weeks.
C)36 weeks.
D)38 weeks.
Question
The earliest start time of an activity is dependent on the earliest finish time of its immediate predecessors.
Question
The longest path in a network from the start of a project to the end of a project is the ________.
Question
An activity's duration added to its earliest start time yields the ________.
Question
The earliest finish time of an activity is always later than its latest start time.
Question
The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.
The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.   What are the early and late start and finish times for this morale-lowering project?<div style=padding-top: 35px> What are the early and late start and finish times for this morale-lowering project?
Question
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question.
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question.   Refer to the scenario above. What are the earliest and latest start and finish times for all of these activities?<div style=padding-top: 35px> Refer to the scenario above. What are the earliest and latest start and finish times for all of these activities?
Question
The earliest finish time is calculated by adding the activity's duration to the predecessor's earliest finish time.
Question
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).   Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.<div style=padding-top: 35px>
Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.
Question
A forward pass through a network is used to determine the earliest start times and earliest finish times for each project activity.
Question
Complete this table containing earliest and latest start times and activity lengths.
Complete this table containing earliest and latest start times and activity lengths.  <div style=padding-top: 35px>
Question
Given the earliest and latest finish times for each of these activities, what are the activity lengths?
Given the earliest and latest finish times for each of these activities, what are the activity lengths?  <div style=padding-top: 35px>
Question
For critical path activities, slack is equal to ________.
Question
A critical path is composed entirely of critical activities.
Question
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Determine earliest and latest start and finish times for all of the activities.
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Determine earliest and latest start and finish times for all of the activities.  <div style=padding-top: 35px>
Question
A project is composed of the twelve activities shown in the table. What are the earliest and latest start times for each of these activities?
A project is composed of the twelve activities shown in the table. What are the earliest and latest start times for each of these activities?  <div style=padding-top: 35px>
Question
A Gantt chart can be used for project planning and also project ________ .
Question
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).   Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.<div style=padding-top: 35px>
Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.
Question
Activities on the critical path may have positive or negative slack as long as the overall slack time of the critical path is zero.
Question
The tablet unearthed by the archaeologist revealed an ancient culture's project plan, however the sands of time had erased much of the information that the table once contained. Unlock the ancient project's secrets by completing all of the information missing from this fragmentary record.
The tablet unearthed by the archaeologist revealed an ancient culture's project plan, however the sands of time had erased much of the information that the table once contained. Unlock the ancient project's secrets by completing all of the information missing from this fragmentary record.  <div style=padding-top: 35px>
Question
A(n)________ is a graphical tool used to show a project's progress as time elapses.
Question
The professional organization that serves the needs of project management professionals is ________.
Question
Which of these needs does the Guide to the Project Management Body of Knowledge NOT serve?

A)It provides a common language for discussing project management issues.
B)It provides a blueprint for ISO certification of the project management process.
C)It identifies and disseminates generally accepted project management knowledge and practices.
D)It serves as a basic reference source for project management.
Question
The Guide to the Project Management Body of Knowledge (PMBOKĀ®)is divided into two main parts, the various business processes that organizations follow in carrying out projects and the nine knowledge areas applicable to nearly all projects.
Question
Describe some of the key features and advantages of project management software.
The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.
Describe some of the key features and advantages of project management software. The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.   Identify the activities that have slack and the amount of slack each has for this morale-lowering project?<div style=padding-top: 35px>
Identify the activities that have slack and the amount of slack each has for this morale-lowering project?
Question
Describe some of the key features and advantages of project management software.
The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.
Describe some of the key features and advantages of project management software. The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.   What is the critical path for this morale-lowering project?<div style=padding-top: 35px>
What is the critical path for this morale-lowering project?
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/65
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 14: Managing Projects
1
An expectation that a new building's foundation would be poured and cured by the end of the year is an example of a(n):

A)activity.
B)scope.
C)milestone.
D)precedence.
milestone.
2
In what ways are projects distinct from typical business activities?
Projects are distinct from typical business activities in four ways. First, projects are nonroutine. Second, the nonroutine nature of a project makes it very difficult to manage. Third, projects typically require significant levels of cross-functional and interorganizational coordination. Fourth, projects have a defined ending point at which time the project is complete.
3
During the ________, project planners identify how to accomplish the work, how to organize for the project, and the key personnel and resources needed.
project definition phase
4
A performance or time target for each major group of activities in a project is a(n)________.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
5
Execution of the project's constituent activities begins in the project's:

A)planning phase.
B)concept phase.
C)post-completion phase.
D)performance phase.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
6
A project is a temporary undertaking designed to create a unique, product, service or results.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
7
The Triskaidekaphobia Project is starting its tenth week and the Gantt chart appears below. Which of these statements about the project is incorrect? <strong>The Triskaidekaphobia Project is starting its tenth week and the Gantt chart appears below. Which of these statements about the project is incorrect?  </strong> A)The critical path is BCEF. B)Five of the activities are complete. C)Activity D had one week of slack. D)The project is behind schedule.

A)The critical path is BCEF.
B)Five of the activities are complete.
C)Activity D had one week of slack.
D)The project is behind schedule.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
8
This Gantt chart can be used to show: <strong>This Gantt chart can be used to show:  </strong> A)activity D must come before activity C. B)activity F can be done at the same time as D. C)activity E can begin as soon as activity A is complete. D)activities D and B can be done simultaneously.

A)activity D must come before activity C.
B)activity F can be done at the same time as D.
C)activity E can begin as soon as activity A is complete.
D)activities D and B can be done simultaneously.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
9
One of the primary characteristics of projects as a form of work is the movement of personnel from project to project.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
10
Discuss the recent business trends that have increased the attention and interest in project management skills.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
11
In what way are projects and typical business activities similar?

A)For most companies, projects and typical business activities can be described as routine.
B)Both projects and typical business activities have a defined ending point at which time they are complete.
C)Projects and routine business activities require significant levels of cross-functional and interorganizational coordination.
D)The successful completion of projects and business activities is essential to a firm's competitive position.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
12
Performance or time targets for each major group of activities in a project are set during the planning phase of a project.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
13
There are more resources required during the performance phase of a project than the project definition phase.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
14
Key points in a project, such as when a major activity or phase should be completed, are referred to as lodestones.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
15
PERT is an acronym meaning:

A)Project Evaluation and Review Technique.
B)Project Execution and Review Technique.
C)Program Evaluation and Review Technique.
D)Plan Estimation and Review Technique.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
16
Project planners develop a broad definition of what the project is and what its scope will be during the:

A)concept phase.
B)project definition phase.
C)planning phase.
D)performance phase.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
17
The actual work gets done during the ________ phase of a project.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
18
What are the phases of a project and the activities within each?
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
19
The budget estimates made during the concept phase are usually accurate to within:

A)20 percent.
B)30 percent.
C)40 percent.
D)50 percent.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
20
In the project definition phase, project planners identify, among other tasks, how to accomplish the work and how to organize for the project.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
21
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A ā‹Æ712 B ā‹Æ8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. What is the earliest start time for activity H?

A)Week 14
B)Week 15
C)Week 16
D)Week 17
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
22
A Gantt chart provides both a planning function and a control function.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
23
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements are listed in the table immediately below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A āˆ’7 B  A 6 C  A 10 D  C 12 E  B, C 5 F  D, E 11 G  F 8\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & - & 7 \\\hline \text { B } & \text { A } & 6 \\\hline \text { C } & \text { A } & 10 \\\hline \text { D } & \text { C } & 12 \\\hline \text { E } & \text { B, C } & 5 \\\hline \text { F } & \text { D, E } & 11 \\\hline \text { G } & \text { F } & 8 \\\hline\end{array}

-Refer to the scenario above. Which of these statements is BEST?

A)Only four of these activities have zero slack.
B)The late finish of D minus the latest finish of C is less than the slack of B.
C)B's latest start plus its slack equals F's latest finish.
D)The sum of the latest start times for activities A through E is less than the sum of the latest start times for F and G.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
24
A Gantt chart explicitly shows precedence requirements for a project's constituent activities.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
25
A project is composed of 6 activities that have durations and precedence requirements shown in the table. Which of these activities is NOT on the critical path?  Activity  Length  Predecessor  A 5⋯ B 7 A  C 4 A  D 7 B,C  E 7 B  F 6 D, E \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 5 & \cdots \\\hline \text { B } & 7 & \text { A } \\\hline \text { C } & 4 & \text { A } \\\hline \text { D } & 7 & \text { B,C } \\\hline \text { E } & 7 & \text { B } \\\hline \text { F } & 6 & \text { D, E } \\\hline\end{array}

A)A
B)B
C)C
D)D
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
26
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A ā‹Æ10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array}

-Refer to the scenario above. The fastest the project can be completed is:

A)49 weeks
B)46 weeks
C)38 weeks
D)35 weeks
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
27
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A ā‹Æ10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array}

-Refer to the scenario above. Which of these activities has the least slack?

A)E
B)B
C)G
D)F
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
28
Program evaluation and review technique, PERT, is a network-based technique in which there are multiple time estimates for each activity.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
29
Most project management software represents a project in AON format.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
30
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A ā‹Æ10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array}

-Refer to the scenario above. What is the slack for activity G?

A)4 weeks
B)3 weeks
C)2 weeks
D)1 week
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
31
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question.  Activity  Predecessors  Time (weeks)  A ā‹Æ10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array} Refer to the scenario above. One activity has identical earliest finish and latest start times. What is the common number for this unusual activity?

A)17
B)18
C)21
D)29
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
32
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A ā‹Æ712 B ā‹Æ8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. What is the duration of activity H?

A)7 weeks
B)8 weeks
C)9 weeks
D)10 weeks
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
33
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A ā‹Æ712 B ā‹Æ8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. What is the latest start time for activity K?

A)Week 20
B)Week 19
C)Week 18
D)Week 17
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
34
What is the latest that activity B can start if A lasts 35 days, B lasts 5, days C lasts 6 days, and D lasts 7 days? <strong>What is the latest that activity B can start if A lasts 35 days, B lasts 5, days C lasts 6 days, and D lasts 7 days?  </strong> A)35 B)36 C)40 D)41

A)35
B)36
C)40
D)41
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
35
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements are listed in the table immediately below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A āˆ’7 B  A 6 C  A 10 D  C 12 E  B, C 5 F  D, E 11 G  F 8\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & - & 7 \\\hline \text { B } & \text { A } & 6 \\\hline \text { C } & \text { A } & 10 \\\hline \text { D } & \text { C } & 12 \\\hline \text { E } & \text { B, C } & 5 \\\hline \text { F } & \text { D, E } & 11 \\\hline \text { G } & \text { F } & 8 \\\hline\end{array}

-Refer to the scenario above. Which of these activities has slack?

A)G
B)E
C)F
D)D
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
36
What is the latest that activity D can start if A lasts 5 days, B lasts 7 days, C lasts 4 days, D lasts 5 days, E lasts 7 days, and F is 6 days long? <strong>What is the latest that activity D can start if A lasts 5 days, B lasts 7 days, C lasts 4 days, D lasts 5 days, E lasts 7 days, and F is 6 days long?  </strong> A)14 B)15 C)16 D)17

A)14
B)15
C)16
D)17
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
37
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A ā‹Æ712 B ā‹Æ8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. What is the earliest finish time for activity G?

A)Week 21
B)Week 22
C)Week 23
D)Week 24
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
38
What is the fastest completion time of the project with activity lengths (in days)and precedence requirements as shown in the table?  Activity  Length  Predecessor  A 15⋯ B 7 A  C 4 A  D 8 B, C \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 15 & \cdots \\\hline \text { B } & 7 & \text { A } \\\hline \text { C } & 4 & \text { A } \\\hline \text { D } & 8 & \text { B, C } \\\hline\end{array}

A)22
B)25
C)27
D)30
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
39
Which of the activities in this project has the greatest amount of slack?  Activity  Length  Predecessor  A 7⋯ B 4 A  C 8 A  D 3B,C E 2B F 8 D, E \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 7 & \cdots \\\hline \text { B } & 4 & \text { A } \\\hline \text { C } & 8 & \text { A } \\\hline \text { D } & 3 & B , C \\\hline \text { E } & 2 & B \\\hline \text { F } & 8 & \text { D, E } \\\hline\end{array}

A)B
B)C
C)D
D)E
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
40
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A ā‹Æ712 B ā‹Æ8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. The project's duration is:

A)32 weeks.
B)33 weeks.
C)36 weeks.
D)38 weeks.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
41
The earliest start time of an activity is dependent on the earliest finish time of its immediate predecessors.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
42
The longest path in a network from the start of a project to the end of a project is the ________.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
43
An activity's duration added to its earliest start time yields the ________.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
44
The earliest finish time of an activity is always later than its latest start time.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
45
The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.
The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.   What are the early and late start and finish times for this morale-lowering project? What are the early and late start and finish times for this morale-lowering project?
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
46
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question.
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question.   Refer to the scenario above. What are the earliest and latest start and finish times for all of these activities? Refer to the scenario above. What are the earliest and latest start and finish times for all of these activities?
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
47
The earliest finish time is calculated by adding the activity's duration to the predecessor's earliest finish time.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
48
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).   Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.
Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
49
A forward pass through a network is used to determine the earliest start times and earliest finish times for each project activity.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
50
Complete this table containing earliest and latest start times and activity lengths.
Complete this table containing earliest and latest start times and activity lengths.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
51
Given the earliest and latest finish times for each of these activities, what are the activity lengths?
Given the earliest and latest finish times for each of these activities, what are the activity lengths?
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
52
For critical path activities, slack is equal to ________.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
53
A critical path is composed entirely of critical activities.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
54
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Determine earliest and latest start and finish times for all of the activities.
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Determine earliest and latest start and finish times for all of the activities.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
55
A project is composed of the twelve activities shown in the table. What are the earliest and latest start times for each of these activities?
A project is composed of the twelve activities shown in the table. What are the earliest and latest start times for each of these activities?
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
56
A Gantt chart can be used for project planning and also project ________ .
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
57
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).   Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.
Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
58
Activities on the critical path may have positive or negative slack as long as the overall slack time of the critical path is zero.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
59
The tablet unearthed by the archaeologist revealed an ancient culture's project plan, however the sands of time had erased much of the information that the table once contained. Unlock the ancient project's secrets by completing all of the information missing from this fragmentary record.
The tablet unearthed by the archaeologist revealed an ancient culture's project plan, however the sands of time had erased much of the information that the table once contained. Unlock the ancient project's secrets by completing all of the information missing from this fragmentary record.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
60
A(n)________ is a graphical tool used to show a project's progress as time elapses.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
61
The professional organization that serves the needs of project management professionals is ________.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
62
Which of these needs does the Guide to the Project Management Body of Knowledge NOT serve?

A)It provides a common language for discussing project management issues.
B)It provides a blueprint for ISO certification of the project management process.
C)It identifies and disseminates generally accepted project management knowledge and practices.
D)It serves as a basic reference source for project management.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
63
The Guide to the Project Management Body of Knowledge (PMBOKĀ®)is divided into two main parts, the various business processes that organizations follow in carrying out projects and the nine knowledge areas applicable to nearly all projects.
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
64
Describe some of the key features and advantages of project management software.
The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.
Describe some of the key features and advantages of project management software. The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.   Identify the activities that have slack and the amount of slack each has for this morale-lowering project?
Identify the activities that have slack and the amount of slack each has for this morale-lowering project?
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
65
Describe some of the key features and advantages of project management software.
The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.
Describe some of the key features and advantages of project management software. The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.   What is the critical path for this morale-lowering project?
What is the critical path for this morale-lowering project?
Unlock Deck
Unlock for access to all 65 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 65 flashcards in this deck.