Exam 14: Managing Projects
Exam 1: Introduction to Operations and Supply Chain Management83 Questions
Exam 2: Operations and Supply Chain Strategies85 Questions
Exam 3: Process Choice and Layout Decisions in Manufacturing and Services100 Questions
Exam 4: Business Processes83 Questions
Exam 5: Managing Quality66 Questions
Exam 6: Managing Capacity71 Questions
Exam 6: S: Advanced Waiting Line Theory and Simulation Modeling70 Questions
Exam 7: Supply Management92 Questions
Exam 8: Logistics90 Questions
Exam 9: Forecasting79 Questions
Exam 10: Sales and Operations Planning Aggregate Planning80 Questions
Exam 11: Managing Inventory Throughout the Supply Chain78 Questions
Exam 12: Managing Production Across the Supply Chain96 Questions
Exam 12: S: Supply Chain Information Systems62 Questions
Exam 13: Jitlean Production75 Questions
Exam 14: Managing Projects65 Questions
Exam 15: Developing Products and Services88 Questions
Select questions type
Project planners develop a broad definition of what the project is and what its scope will be during the:
Free
(Multiple Choice)
4.7/5
(30)
Correct Answer:
A
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question(s).
Activity Predecessors Time (weeks) A \@cdots 10 B A 8 C A 7 D C 11 E D 12 F B 11 G E, F 6 H E, F 9
-Refer to the scenario above. What is the slack for activity G?
Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
B
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).
Activity Predecessors Time (weeks) A - 7 B A 6 C A 10 D C 12 E B, C 5 F D, E 11 G F 8
-Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.
Free
(Essay)
4.7/5
(41)
Correct Answer:
Gantt chart is shown below; project duration is 48.
A performance or time target for each major group of activities in a project is a(n)________.
(Short Answer)
4.8/5
(36)
A Gantt chart can be used for project planning and also project ________ .
(Short Answer)
4.8/5
(31)
Execution of the project's constituent activities begins in the project's:
(Multiple Choice)
4.9/5
(26)
There are more resources required during the performance phase of a project than the project definition phase.
(True/False)
4.8/5
(34)
The professional organization that serves the needs of project management professionals is ________.
(Short Answer)
4.8/5
(37)
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
Activity Predecessors Time ES EF LS LF A \@cdots 7 12 B \@cdots 8 C A 13 20 D A 11 12 E B 14 17 F B 11 G D, E 6 H C 20 K F 29 L G,H,K 9
-Refer to the scenario above. What is the earliest finish time for activity G?
(Multiple Choice)
4.7/5
(33)
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Determine earliest and latest start and finish times for all of the activities.
Activity Predecessors Time (weeks) A \@cdots 10 B A 8 C A 7 D C 11 E D 12 F B 11 G E, F 6 H E, F 9
(Essay)
4.9/5
(30)
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).
Activity Predecessors Time (weeks) A - 7 B A 6 C A 10 D C 12 E B, C 5 F D, E 11 G F 8
-Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.
(Essay)
4.9/5
(42)
During the ________, project planners identify how to accomplish the work, how to organize for the project, and the key personnel and resources needed.
(Short Answer)
4.8/5
(36)
The Triskaidekaphobia Project is starting its tenth week and the Gantt chart appears below. Which of these statements about the project is incorrect? 

(Multiple Choice)
4.8/5
(31)
The budget estimates made during the concept phase are usually accurate to within:
(Multiple Choice)
4.8/5
(39)
Most project management software represents a project in AON format.
(True/False)
4.7/5
(27)
The earliest finish time is calculated by adding the activity's duration to the predecessor's earliest finish time.
(True/False)
4.8/5
(39)
The tablet unearthed by the archaeologist revealed an ancient culture's project plan, however the sands of time had erased much of the information that the table once contained. Unlock the ancient project's secrets by completing all of the information missing from this fragmentary record.
Activity Predecessors Time ES EF LS LF A \@cdots 7 12 B \@cdots 8 C A 13 20 D A 11 12 E B 14 17 F B 11 G D, E 6 H C 20 K F 29 L G,H,K 9
(Essay)
4.7/5
(34)
The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.
Activity Duration Predecessor A 3 - B 8 - 8 A 7 B 4 4 , , 8 8 4 2 6 10 I, K
-What is the critical path for this morale-lowering project?
(Essay)
4.9/5
(38)
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
Activity Predecessors Time ES EF LS LF A \@cdots 7 12 B \@cdots 8 C A 13 20 D A 11 12 E B 14 17 F B 11 G D, E 6 H C 20 K F 29 L G,H,K 9
-Refer to the scenario above. What is the duration of activity H?
(Multiple Choice)
4.9/5
(39)
In the project definition phase, project planners identify, among other tasks, how to accomplish the work and how to organize for the project.
(True/False)