Deck 7: The Project Schedule and Budget
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/64
Play
Full screen (f)
Deck 7: The Project Schedule and Budget
1
A start-to-finish activity is the most common relationship between two activities.
False
2
Parallel activities can shorten the project schedule,but can have an impact on project resources if a resource is assigned to two tasks at the same time.
True
3
The PMBOK area called project cost management includes estimate costs,determine budget,and control costs.
True
4
Start-to-Start and Finish-to-Finish relationships allow activities to be worked on in parallel.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
5
Identifying the critical path is important because any change in the duration of the activities or tasks on the critical path will affect the project's schedule.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
6
The project budget is determined by the project schedule,the cost of the resources assigned to each of the tasks,and by any other direct or indirect costs and reserves.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
7
The critical path has zero slack or float)
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
8
The tool most closely associated with activity bars across a horizontal time axis is:
A)Project Network Diagrams
B)Gantt Charts
C)PERT
D)Activity on the Node
E)Critical Path Analysis
A)Project Network Diagrams
B)Gantt Charts
C)PERT
D)Activity on the Node
E)Critical Path Analysis
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
9
Project network diagrams provide valuable information about the logical sequence and dependencies among the various activities and tasks so that a completion date or deadline can be determined.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
10
The critical path is the longest path in the project network and also is the shortest time in which the project can be completed.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
11
Sunk costs include such things as rent,utilities,insurance,and other administrative costs.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
12
Identifying the critical path is important because a project can only have one critical path and it never changes.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
13
The direct costs of using a resource is the only type of cost that should be considered when developing the project budget.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
14
A reserve can provide a cushion when unexpected situations arise.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
15
PERT was developed in the 1950s to create a visual representation of scheduled activities,their logical sequence,and interrelationships using a statistical probability distribution.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
16
Installing a server before loading the operating system is an example of a finish-to-start relationship.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
17
A parallel activity is a task that can be worked on at the same time as another activity.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
18
An over allocated resource would arise when Mary is assigned to work on two tasks scheduled at the same time.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
19
Predecessor activities are activities that can be worked on at the same time as another activity.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
20
The critical path is the shortest path in the project network and also is the longest time in which the project can be completed.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
21
Under the Precedence Diagramming Method,the situation which occurs when two activities can start at different times,have different durations,but are planned to be competed at the same time is called:
A)Finish-To-Start FS)
B)Start-To-Start SS)
C)Finish-To-Finish FF)
D)Start-To-Finish SF)
E)none of the above
A)Finish-To-Start FS)
B)Start-To-Start SS)
C)Finish-To-Finish FF)
D)Start-To-Finish SF)
E)none of the above
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
22
Adding resources to an activity to shorten the critical path is called_____
A)slacking.
B)floating.
C)diverting.
D)crashing.
E)fast tracking
A)slacking.
B)floating.
C)diverting.
D)crashing.
E)fast tracking
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
23
Under the Precedence Diagramming Method,the situation which occurs when a relationship between two tasks that can or must start at the same time is called:
A)Finish-To-Start FS)
B)Start-To-Start SS)
C)Finish-To-Finish FF)
D)Start-To-Finish SF)
E)none of the above
A)Finish-To-Start FS)
B)Start-To-Start SS)
C)Finish-To-Finish FF)
D)Start-To-Finish SF)
E)none of the above
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
24
_____ is considered the most useful and widely used project management tool.
A)Project Network Diagrams
B)Gantt Charts
C)PERT
D)Activity on the Node
E)Critical Path Analysis
A)Project Network Diagrams
B)Gantt Charts
C)PERT
D)Activity on the Node
E)Critical Path Analysis
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
25
The technique used to help manage the Polaris submarine project and which bases activity estimates on probabilistic estimates of three scenarios is most closely associated with:
A)Project Network Diagrams
B)Gantt Charts
C)PERT
D)Activity on the Node
E)Critical Path Analysis
A)Project Network Diagrams
B)Gantt Charts
C)PERT
D)Activity on the Node
E)Critical Path Analysis
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
26
Under the Precedence Diagramming Method,the least common relationship between two activities which occurs when they must complete at the same time is called:
A)Finish-To-Start FS)
B)Start-To-Start SS)
C)Finish-To-Finish FF)
D)Start-To-Finish SF)
E)none of the above
A)Finish-To-Start FS)
B)Start-To-Start SS)
C)Finish-To-Finish FF)
D)Start-To-Finish SF)
E)none of the above
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
27
An activity being analyzed under PERT was judged to most likely have a duration of 40 days.When considering the time it would take to complete the activity if every relevant factor went well,it was estimated to be able to be doable in 20 days and even under the worst case imaginable,the task would be take 50 days.The estimates PERT duration of that activity is:
A)36.67 days
B)38.33 days
C)37.50 days
D)28.33 days
E)32.67 days
A)36.67 days
B)38.33 days
C)37.50 days
D)28.33 days
E)32.67 days
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
28
Under the Precedence Diagramming Method,the situation which occurs when task A cannot end until task B starts is called:
A)Finish-To-Start FS)
B)Start-To-Start SS)
C)Finish-To-Finish FF)
D)Start-To-Finish SF)
E)none of the above
A)Finish-To-Start FS)
B)Start-To-Start SS)
C)Finish-To-Finish FF)
D)Start-To-Finish SF)
E)none of the above
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
29
The amount of time an activity can be delayed before affecting the project deadline is _____
A)slack
B)crash
C)fast-track
D)diversion
E)delay in any activity will delay the project
A)slack
B)crash
C)fast-track
D)diversion
E)delay in any activity will delay the project
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
30
_____ can be useful for tracking and monitoring project progress because because they are simple and straightforward.
A)Project Network Diagrams
B)Gantt Charts
C)PERT
D)Activity on the Node
E)Critical Path Analysis
A)Project Network Diagrams
B)Gantt Charts
C)PERT
D)Activity on the Node
E)Critical Path Analysis
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
31
_____ can help manage the Critical Path by providing information about which activities can be delayed without affecting the deadline target date.
A)Work Breakdown Schedule
B)Gantt Charts
C)PART
D)Project Network Diagrams
E)Critical Path Analysis
A)Work Breakdown Schedule
B)Gantt Charts
C)PART
D)Project Network Diagrams
E)Critical Path Analysis
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
32
Waiting to leave your shift until another person shows up is an example of:
A)Finish-To-Start FS)
B)Start-To-Start SS)
C)Finish-To-Finish FF)
D)Start-To-Finish SF)
E)none of the above
A)Finish-To-Start FS)
B)Start-To-Start SS)
C)Finish-To-Finish FF)
D)Start-To-Finish SF)
E)none of the above
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
33
_____ provide valuable information about the logical sequence and dependencies among the various activities and tasks:
A)Work Breakdown Schedule
B)Gantt Charts
C)PART
D)Project Network Diagrams
E)Critical Path Analysis
A)Work Breakdown Schedule
B)Gantt Charts
C)PART
D)Project Network Diagrams
E)Critical Path Analysis
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
34
The Critical Path is:
A)the longest path in the project network.
B)the shortest path in the project network.
C)the longest time in which the project can be completed.
D)the interrelationships of project activities.
E)the most important identified tasks within the project.
A)the longest path in the project network.
B)the shortest path in the project network.
C)the longest time in which the project can be completed.
D)the interrelationships of project activities.
E)the most important identified tasks within the project.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
35
Starting the next task before the first task is complete is _____
A)lead
B)lag
C)negative lead
D)slack
E)float
A)lead
B)lag
C)negative lead
D)slack
E)float
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
36
The technique used to find the sequence of tasks with zero slack or float)is most closely associated with:
A)Project Network Diagrams
B)Gantt Charts
C)PERT
D)Activity on the Node
E)Critical Path Analysis
A)Project Network Diagrams
B)Gantt Charts
C)PERT
D)Activity on the Node
E)Critical Path Analysis
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
37
Installing the operating system on a computer before loading any application packages is an example of:
A)Finish-To-Start FS)
B)Start-To-Start SS)
C)Finish-To-Finish FF)
D)Start-To-Finish SF)
E)none of the above
A)Finish-To-Start FS)
B)Start-To-Start SS)
C)Finish-To-Finish FF)
D)Start-To-Finish SF)
E)none of the above
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
38
Completing activities in parallel is called_____
A)slacking.
B)floating.
C)diverting.
D)crashing.
E)fast tracking
A)slacking.
B)floating.
C)diverting.
D)crashing.
E)fast tracking
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
39
Under the Precedence Diagramming Method,the most common relationship between two activities which implies a logical sequence is called:
A)Finish-To-Start FS)
B)Start-To-Start SS)
C)Finish-To-Finish FF)
D)Start-To-Finish SF)
E)none of the above
A)Finish-To-Start FS)
B)Start-To-Start SS)
C)Finish-To-Finish FF)
D)Start-To-Finish SF)
E)none of the above
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
40
_____ is well suited for developing simulations where the project manager can conduct sensitivity analysis for schedule planning and risk analysis.
A)Project Network Diagrams
B)Gantt Charts
C)PERT
D)Activity on the Node
E)Critical Path Analysis
A)Project Network Diagrams
B)Gantt Charts
C)PERT
D)Activity on the Node
E)Critical Path Analysis
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
41
The final step in determining the cost of an activity is:
A)determine necessary resources.
B)determining resource quantity
C)determining the cost of each resource
D)ensuring resources are leveled
E)none of the above
A)determine necessary resources.
B)determining resource quantity
C)determining the cost of each resource
D)ensuring resources are leveled
E)none of the above
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
42
What is meant by slack or float)?
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
43
How can parallel activities help shorten the project schedule? Are there any trade-offs?
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
44
Critical Chain Project Management CCPM)is based on the idea that
A)people often inflate or add cushioning to their time estimates
B)PERT/CPM was developed in the 1950s so it is too old to be of any use
C)Precedence Diagramming only considers the critical path of a project
D)all of the above
E)none of the above
A)people often inflate or add cushioning to their time estimates
B)PERT/CPM was developed in the 1950s so it is too old to be of any use
C)Precedence Diagramming only considers the critical path of a project
D)all of the above
E)none of the above
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
45
_____is ensuring that project resources are not overallocated.
A)Resource leveling
B)Resource constraining
C)Resource starving
D)Resource management
E)Resource addition
A)Resource leveling
B)Resource constraining
C)Resource starving
D)Resource management
E)Resource addition
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
46
The cost of labor for using a resource are _____
A)Direct Costs
B)Indirect Costs
C)Sunk Costs
D)Learning Curve Costs
E)Reserves Costs
A)Direct Costs
B)Indirect Costs
C)Sunk Costs
D)Learning Curve Costs
E)Reserves Costs
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
47
To make a decision to attempt to build an application system based on what was left after a previous attempt ended in failure primarily because of the large investment the company made in the failed project most likely was made by a manager who did not fully understand:
A)Direct Costs
B)Indirect Costs
C)Sunk Costs
D)Learning Curve Costs
E)Reserves Costs
A)Direct Costs
B)Indirect Costs
C)Sunk Costs
D)Learning Curve Costs
E)Reserves Costs
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
48
Funds allocated for unexpected expenses are _____
A)Direct Costs
B)Indirect Costs
C)Sunk Costs
D)Learning Curve Costs
E)Reserves Costs
A)Direct Costs
B)Indirect Costs
C)Sunk Costs
D)Learning Curve Costs
E)Reserves Costs
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
49
Describe the PMBOK area of project cost management.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
50
Rent,utilities,insurance and administrative costs are examples of:
A)Direct Costs
B)Indirect Costs
C)Sunk Costs
D)Learning Curve Costs
E)Reserves Costs
A)Direct Costs
B)Indirect Costs
C)Sunk Costs
D)Learning Curve Costs
E)Reserves Costs
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
51
Scheduling other projects so that resources may be shared is_____
A)Critical Chain Project Management
B)Precedence Diagramming
C)PERT
D)Theory of Constraints
E)Critical Path Analysis
A)Critical Chain Project Management
B)Precedence Diagramming
C)PERT
D)Theory of Constraints
E)Critical Path Analysis
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
52
Rolling wave planning is:
A)developing a large plan encompassing all project items.
B)including the highest level of detail in project plans
C)preparing a summary plan and developing incremental detailed schedules
D)all of the above
E)none of the above
A)developing a large plan encompassing all project items.
B)including the highest level of detail in project plans
C)preparing a summary plan and developing incremental detailed schedules
D)all of the above
E)none of the above
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
53
What is the difference between crashing and fast tracking a project's schedule?
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
54
Define the following and give a real world example of each other than the ones described in this book): Finish-to-Start;Start-to-Start;Finish-to-Finish;Start-to-Finish.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
55
Costs incurred prior to the current project are _____
A)Direct Costs
B)Indirect Costs
C)Sunk Costs
D)Learning Curve Costs
E)Reserves Costs
A)Direct Costs
B)Indirect Costs
C)Sunk Costs
D)Learning Curve Costs
E)Reserves Costs
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
56
Time and effort needed to gather experience on a technology or process are _____
A)Direct Costs
B)Indirect Costs
C)Sunk Costs
D)Learning Curve Costs
E)Reserves Costs
A)Direct Costs
B)Indirect Costs
C)Sunk Costs
D)Learning Curve Costs
E)Reserves Costs
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
57
The idea that there is a cost associated with using a resource is _____
A)Prorated Costs
B)Indirect Costs
C)Sunk Costs
D)Learning Curve Costs
E)Reserves Costs
A)Prorated Costs
B)Indirect Costs
C)Sunk Costs
D)Learning Curve Costs
E)Reserves Costs
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
58
In the context of critical chain project management,what is resource contention?
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
59
Why do many people inflate their estimates?
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
60
Define predecessor,successor,and parallel activities.Give a real world example of each.
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
61
Why should assumptions used in estimating be documented?
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
62
Why should the project manager ensure that the project resources are leveled?
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
63
What does prorating the cost of a resource mean?
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck
64
What is a baseline plan?
Unlock Deck
Unlock for access to all 64 flashcards in this deck.
Unlock Deck
k this deck