Deck 7: Additional Spc Techniques for Variables

Full screen (f)
exit full mode
Question
What type of process is the packaging of tooth paste?

A) continuance
B) batch
C) discrete
D) none of the above
Use Space or
up arrow
down arrow
to flip the card.
Question
Which of the following type(s) of short-run control is/are based on specifications?

A) Z and W
B) precontrol
C) deviation chart
D) a and b
Question
Before changing from the set up mode to the run mode in precontrol there must be

A) 3 consecutive goods in the green zone
B) 5 consecutive goods in the green zone
C) 7 consecutive goods in the green zone
D) acceptable parts
Question
Determine the plotted point for a PTPCC, where the specification for a part number is 5.23 ± 0.03 and an inspected measured value is 5.24.
Question
Determine the central lines for Z and MW charts and draw the charts. If the target X is 2.00 and the target R is 0.05, determine the plotted points for the following values. Determine the central lines for Z and MW charts and draw the charts. If the target X is 2.00 and the target R is 0.05, determine the plotted points for the following values.    <div style=padding-top: 35px>
Determine the central lines for Z and MW charts and draw the charts. If the target X is 2.00 and the target R is 0.05, determine the plotted points for the following values.    <div style=padding-top: 35px>
Question
Which of the following type(s) of short-run control is/are derived from the X and R charts?

A) Z and W charts
B ) precontrol
C) specification chart
D) b and c
Question
What type of process is the production of soup?

A) continuance
B) batch
C) discrete
D) none of the above
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/7
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 7: Additional Spc Techniques for Variables
1
What type of process is the packaging of tooth paste?

A) continuance
B) batch
C) discrete
D) none of the above
A
2
Which of the following type(s) of short-run control is/are based on specifications?

A) Z and W
B) precontrol
C) deviation chart
D) a and b
B
3
Before changing from the set up mode to the run mode in precontrol there must be

A) 3 consecutive goods in the green zone
B) 5 consecutive goods in the green zone
C) 7 consecutive goods in the green zone
D) acceptable parts
B
4
Determine the plotted point for a PTPCC, where the specification for a part number is 5.23 ± 0.03 and an inspected measured value is 5.24.
Unlock Deck
Unlock for access to all 7 flashcards in this deck.
Unlock Deck
k this deck
5
Determine the central lines for Z and MW charts and draw the charts. If the target X is 2.00 and the target R is 0.05, determine the plotted points for the following values. Determine the central lines for Z and MW charts and draw the charts. If the target X is 2.00 and the target R is 0.05, determine the plotted points for the following values.
Determine the central lines for Z and MW charts and draw the charts. If the target X is 2.00 and the target R is 0.05, determine the plotted points for the following values.
Unlock Deck
Unlock for access to all 7 flashcards in this deck.
Unlock Deck
k this deck
6
Which of the following type(s) of short-run control is/are derived from the X and R charts?

A) Z and W charts
B ) precontrol
C) specification chart
D) b and c
Unlock Deck
Unlock for access to all 7 flashcards in this deck.
Unlock Deck
k this deck
7
What type of process is the production of soup?

A) continuance
B) batch
C) discrete
D) none of the above