Exam 7: Additional Spc Techniques for Variables

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

Determine the plotted point for a PTPCC, where the specification for a part number is 5.23 ± 0.03 and an inspected measured value is 5.24.

Free
(Short Answer)
5.0/5
(35)
Correct Answer:
Verified

0.33 or 33%

What type of process is the packaging of tooth paste?

Free
(Multiple Choice)
4.8/5
(45)
Correct Answer:
Verified

A

Which of the following type(s) of short-run control is/are based on specifications?

Free
(Multiple Choice)
4.7/5
(25)
Correct Answer:
Verified

B

What type of process is the production of soup?

(Multiple Choice)
4.8/5
(32)

Determine the central lines for Z and MW charts and draw the charts. If the target X is 2.00 and the target R is 0.05, determine the plotted points for the following values. Subgroup Observed Value 1 2.05 2 2.08 3 1.97

(Short Answer)
5.0/5
(37)

Which of the following type(s ) of short-run control is/are derived from the X and R charts?

(Multiple Choice)
4.8/5
(33)

Before changing from the set up mode to the run mode in precontrol there must be

(Multiple Choice)
4.8/5
(38)