Deck 13: Project Closure
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/80
Play
Full screen (f)
Deck 13: Project Closure
1
Project managers need to learn that it is not okay if a project is cancelled before completion if there are valid reasons to abandon it.
False
2
Provide at least three examples of reasons a contract is terminated. Also, how is early termination handled?
As with project termination, contract termination can occur for many reasons: The deliverable may be completed and accepted, the technology required may have changed, the seller may have performed poorly, or the organization's priorities may have changed and the product may no longer be required. The conditions for terminating a contract early, before final deliverables, must be spelled out in the contract terms. Termination can be done by a mutual agreement of both parties or based on the seller or buyer defaulting on their part of the contract. Some reasons for early termination might include the seller missing key deadlines, the seller creating a product that doesn't meet minimal quality standards, the buyer missing payments, or the buyer continuously rejecting the seller's work and asking for changes.
3
With the aid of the data collected from the procurement audit, what questions can the team can review (describe at least five)?
With the aid of the data collected from the procurement audit, the team can review the following:
• Was the right type of contract used?
• Were milestones achieved by both the buyer and seller? (Referred to as the milestone hit-rate)
• Was the change control process timely and effective, and was it followed?
• Were the deliverables of acceptable quality?
• Was the communications plan effective?
• How well did the project meet financial goals?
• Were the right human resources assigned by the buyer and seller?
• How effective were risk mitigation strategies?
• Was the right type of contract used?
• Were milestones achieved by both the buyer and seller? (Referred to as the milestone hit-rate)
• Was the change control process timely and effective, and was it followed?
• Were the deliverables of acceptable quality?
• Was the communications plan effective?
• How well did the project meet financial goals?
• Were the right human resources assigned by the buyer and seller?
• How effective were risk mitigation strategies?
4
Describe the five areas of information included in the final project report.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
5
Describe the checklist elements that should be reviewed in the lessons learned session.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
6
The Integration Management knowledge area consists of which processes?
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
7
Describe the end of a project and the two general reasons projects terminate.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
8
A good practice in the process of closing a project is to use a final checklist to make sure everything is completed.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
9
Describe the four elements of the checklist used in the process of closing a project. Also, describe the activity categories.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
10
The closing process is extremely important to the continued success of an organization and a project team, and it must not be skipped, regardless of the size of the project.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
11
Provide at least six examples of the reasons projects are terminated.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
12
It is a good practice to get a final deliverable signoff that all has been delivered for the project.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
13
What are the eight steps in the process for project closure and contract closure?
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
14
The decision to terminate a project should be made by key stakeholders who have the authority to cancel the project.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
15
The closing process is needed at the end of each phase or iteration of a project as well as at the end of an entire project.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
16
The end of a project is either a termination due to some failure or a success in the eyes of the stakeholders.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
17
Describe at least three reasons projects aren't cancelled when they should be.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
18
The closing process must be a part of the project charter, with time and resources assigned.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
19
The main goal of the closing process is to finalize all project activities across all process groups to formally close the phase or project and, if needed, assume responsibility for the product from a support or operations department within the organization or perhaps to an external agency.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
20
The Project Management knowledge area consists of the following processes: develop project charter, develop project management plan, direct and manage project execution, monitor and control project work, perform integrated change control, and close project.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
21
The project management database needs to be available to more than just the project manager who ran the project so others can learn from the same information.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
22
The audit is used to review project spending to find errors and possibly fraud.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
23
The closing procurements process supports the overall project closing process in that it verifies that all deliverables from the contract are acceptable (meet quality standards) and officially approved.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
24
The closeout meeting, not to be confused with the lessons learned session or postmortem, is very important and should never be skipped.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
25
One of the steps in the process for project and contract closure is: Reassign any remaining personnel.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
26
Administrative performance information in the final project report answers questions such as: How well did the decision makers perform on the project in terms of speed and accuracy, based on the quality of the information available for decisions? How well did the organizational structure aid the project or hinder the project? Did the decision makers have the correct levels of authority?
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
27
The Procurement Management knowledge area consists of the following processes: plan procurements, conduct procurements, administer procurements, and close procurements.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
28
During the lessons learned process, the project-related information is finalized and moved to an archive status to protect it from being changed or deleted.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
29
The first step in the process for project and contract closure is: Publish results across the organization.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
30
In the final project report, team member performance information answers questions such as: How well did the team work together? Did the team motivation incentives work, or did the team-building exercises work? How well did this team's performance compare to the performance of other teams within the organization? Did the team have the right members assigned? If training was required, how well did it work, and was it done at the right time in the life of the project?
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
31
Project performance information mainly concerns the quality of the product created.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
32
The single best method project managers can use to improve how they run projects is to learn from past mistakes and past successes.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
33
A procurement audit should be performed to document an honest appraisal of the contract from both sides-the buyer's side and the seller's side.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
34
Project performance information includes all actual results compared to plan as well as an examination of project methodology issues.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
35
The first step in the process for project and contract closure is: Conduct final audits, if needed, of the project, product, contract, and personnel.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
36
The closeout meeting can be used in a variety of ways. For example, it can be a brainstorming session to list/review the things that went right and those that went wrong during the project. It is also used to review the entire project and provide a help session so that future projects avoid the same pitfalls.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
37
A task on the checklist is to get official acceptance of the system by the group that will support it during the development life cycle of the product; this is often a group called operational support or operations.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
38
If any special accommodations were required for the project team, such as rental of office space, the site will need to be closed and assets either returned to the organization or, if rented, returned to the owner.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
39
The requirements for the formal written contract closing are generally defined in the terms of the SOW.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
40
Some reasons for early contract termination might include the seller missing key deadlines, the seller creating a product that doesn't meet minimal quality standards, the buyer missing payments, or the buyer continuously rejecting the seller's work and asking for changes.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
41
In the final project report, this information includes all actual results compared to plan as well as an examination of project methodology issues.
A) Project performance
B) Product performance
C) Administrative performance
D) Benefits realized
A) Project performance
B) Product performance
C) Administrative performance
D) Benefits realized
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
42
There is just as much to learn from a bad project as from a good project.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
43
The main goal of the closing process is to finalize all project activities across all ________ groups to formally close the phase or project and, if needed, transfer responsibility for the product to a support or operations department within the organization or perhaps to an external agency.
A) project
B) stakeholder
C) WBS
D) process
A) project
B) stakeholder
C) WBS
D) process
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
44
Postmortem review of a project is a way of looking at lessons learned.
A) Postmortem
B) Final
C) Stakeholder
D) Lessons
A) Postmortem
B) Final
C) Stakeholder
D) Lessons
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
45
The procurement review process may or may not be needed, depending on whether outside vendors were used.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
46
The project-related data archived during the closing process consist of all planned and actual ________ data, including schedule, cost, scope, quality, team performance, risks, and communication issues. Information generated from the lessons learned sessions should also be added before the database is archived.
A) schedule
B) status
C) performance
D) monitored
A) schedule
B) status
C) performance
D) monitored
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
47
The closing process is needed at the end of each ________ of a project as well as at the end of an entire project.
A) phase
B) month
C) life cycle
D) review
A) phase
B) month
C) life cycle
D) review
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
48
The closing process must be a part of the project ________, with time and resources assigned.
A) charter
B) scope
C) schedule
D) plan
A) charter
B) scope
C) schedule
D) plan
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
49
Regardless of how a project is ________, the processes of project closure and contract closure should still be completed.
A) started
B) terminated
C) continued
D) operated
A) started
B) terminated
C) continued
D) operated
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
50
The end of a project is either a termination due to some failure or a success in the eyes of the ________.
A) project manager
B) stakeholders
C) sponsor
D) project team
A) project manager
B) stakeholders
C) sponsor
D) project team
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
51
In the final project report, this information answers questions such as: How well did the decision makers perform on the project in terms of speed and accuracy, based on the quality of the information available for decisions? How well did the organizational structure aid the project or hinder the project? Did the decision makers have the correct levels of authority?
A) Project performance
B) Product performance
C) Administrative performance
D) Team member performance
A) Project performance
B) Product performance
C) Administrative performance
D) Team member performance
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
52
The ________ can be used in a variety of ways. For example, it can be a brainstorming session to list/review the things that went right and those that went wrong during the project. It is also used to review the entire project and provide a help session so that future projects avoid the same pitfalls.
A) lessons learned
B) closeout meeting
C) site closure
D) audit
A) lessons learned
B) closeout meeting
C) site closure
D) audit
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
53
Terminating a project, regardless of reason, is an easy choice, especially for large, complex projects.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
54
A task on the checklist is to get official acceptance of the system by the group that will support it during the normal life of the product; this is often a group called ________.
A) engineering
B) operations
C) operational support
D) B or C
A) engineering
B) operations
C) operational support
D) B or C
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
55
If a project manager and an organization want to continue making the same mistakes over and over again, they must learn from the past.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
56
During the closeout process, the project-related information is finalized and moved to an ________ status to protect it from being changed or deleted.
A) archive
B) active
C) available
D) unavailable
A) archive
B) active
C) available
D) unavailable
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
57
Closing the accounts ensures that erroneous charges don't appear and possibly signal the start of ________.
A) another project
B) an audit
C) collections
D) payroll
A) another project
B) an audit
C) collections
D) payroll
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
58
In the final project report, this information mainly concerns the quality of the product created.
A) Project performance
B) Product performance
C) Administrative performance
D) Benefits realized
A) Project performance
B) Product performance
C) Administrative performance
D) Benefits realized
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
59
The tendency is often to leave a completed project as soon as possible and move on to the next, without conducting much of a project closing process.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
60
Which of the following is NOT one of the processes of the Integration Management knowledge area?
A) Develop project charter.
B) Perform integrated change control.
C) Close project.
D) Conduct lessons learned.
A) Develop project charter.
B) Perform integrated change control.
C) Close project.
D) Conduct lessons learned.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
61
The project or phase closeout process must be completed, regardless of the size of the project or the reason for a project or phase ________.
A) termination
B) audit
C) review
D) reorganization
A) termination
B) audit
C) review
D) reorganization
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
62
As a part of the process "document and update all project data" in the checklist, an organization needs to make sure that all project-related information is ________ documented for future use.
A) partially
B) manually
C) electronically
D) confidentially
A) partially
B) manually
C) electronically
D) confidentially
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
63
Project managers need to learn that it is okay if a project is ________ before completion if there are valid reasons to abandon it,
A) extended
B) cancelled
C) revised
D) prolonged
A) extended
B) cancelled
C) revised
D) prolonged
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
64
In some organizations the financial or accounting department requires official signatures in order to close out ________.
A) projects
B) accounts
C) payroll
D) contracts
A) projects
B) accounts
C) payroll
D) contracts
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
65
Many projects become what Ed Yourdon (1997) calls ________ projects that never end.
A) "ongoing"
B) "infinite"
C) "death march"
D) "operational"
A) "ongoing"
B) "infinite"
C) "death march"
D) "operational"
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
66
The Procurement Management knowledge area consists of the following processes: plan procurements, conduct procurements, administer procurements, and ________ procurements.
A) close
B) review
C) analyze
D) evaluate
A) close
B) review
C) analyze
D) evaluate
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
67
The closeout meeting, also referred to as the ________ session, is very important and should never be skipped.
A) lessons learned
B) postmortem
C) Neither A nor B.
D) Either A or B.
A) lessons learned
B) postmortem
C) Neither A nor B.
D) Either A or B.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
68
Which of the following is NOT a general reason for a project termination?
A) The project is successful in meeting scope, time, cost, and/or quality objectives.
B) The project is not successful in meeting cost, and/or quality objectives.
C) The project is successful in meeting changes in objectives.
D) The project is not successful in meeting scope and/or time objectives
A) The project is successful in meeting scope, time, cost, and/or quality objectives.
B) The project is not successful in meeting cost, and/or quality objectives.
C) The project is successful in meeting changes in objectives.
D) The project is not successful in meeting scope and/or time objectives
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
69
The closing procurements process supports the overall project closing process in that it verifies that all ________ from the contract are acceptable (meet quality standards) and officially approved.
A) projects
B) resources
C) deliverables
D) tests
A) projects
B) resources
C) deliverables
D) tests
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
70
In the final project report, this information answers questions such as: How well did the team work together? Did the team motivation incentives work, or did the team-building exercises work? How well did this team's performance compare to the performance of other teams within the organization? Did the team have the right members assigned? If training was required, how well did it work, and was it done at the right time in the life of the project?
A) Project performance
B) Product performance
C) Administrative performance
D) Team member performance
A) Project performance
B) Product performance
C) Administrative performance
D) Team member performance
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
71
A project manager may be responsible for writing final ________ appraisals for each team member.
A) performance
B) personal
C) professional
D) group
A) performance
B) personal
C) professional
D) group
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
72
The ________ closing process should finalize the archiving of all data related to how the contract was administered and how the seller performed for future contract work with this seller.
A) contract
B) procurement
C) SOW
D) buyer
A) contract
B) procurement
C) SOW
D) buyer
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
73
The formality, number of people involved, and time devoted to the closure process are based on the ________.
A) schedule flexibility
B) project manager
C) sponsor decision
D) size of a project
A) schedule flexibility
B) project manager
C) sponsor decision
D) size of a project
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
74
The decision to terminate a project should be made by key stakeholders who have the ________ to cancel the project.
A) objectivity
B) time
C) nerve
D) authority
A) objectivity
B) time
C) nerve
D) authority
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
75
A ________ audit should be performed to document an honest appraisal of the contract from both sides-the buyer's side and the seller's side.
A) procurement
B) financial
C) vendor
D) seller
A) procurement
B) financial
C) vendor
D) seller
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
76
In the final project report, this information relates to the fact that the project was selected based on some perceived benefits to the organization. Are these still achievable, based on the final product?
A) Project performance
B) Product performance
C) Administrative performance
D) Benefits realized
A) Project performance
B) Product performance
C) Administrative performance
D) Benefits realized
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
77
This is the first step in the process for project and contract closure.
A) Update the project schedule for any remaining work.
B) Obtain final approvals/signatures from stakeholders, management, and sellers.
C) Conduct final audits, if needed, of the project, product, contract, and personnel.
D) Communicate final decisions and review the closure checklist.
A) Update the project schedule for any remaining work.
B) Obtain final approvals/signatures from stakeholders, management, and sellers.
C) Conduct final audits, if needed, of the project, product, contract, and personnel.
D) Communicate final decisions and review the closure checklist.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
78
Some reasons for early contract termination might include:
A) The seller missing key deadlines.
B) The seller creating a product that doesn't meet minimal quality standards.
C) The buyer continuously rejecting the seller's work and asking for changes.
D) All of the above
A) The seller missing key deadlines.
B) The seller creating a product that doesn't meet minimal quality standards.
C) The buyer continuously rejecting the seller's work and asking for changes.
D) All of the above
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
79
The tendency is often to leave a completed project as soon as possible and move on to the next, without conducting much of a project ________.
A) plan
B) closing process
C) review
D) evaluation
A) plan
B) closing process
C) review
D) evaluation
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
80
This process may or may not be needed, depending on whether outside vendors were used.
A) Closing contract process
B) Procurement review
C) Closing procurements process
D) Procurement evaluation
A) Closing contract process
B) Procurement review
C) Closing procurements process
D) Procurement evaluation
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck