Thirty samples of 100 items each were inspected at the Rummy Candy Company and 150 items were found to be defective. Compute control limits for a p -chart for this process.
Thirty samples of 100 items each were inspected at the Rummy Candy Company and 150 items were found to be defective. Compute control limits for a p -chart for this process.
Explanation
Computing control limit:
It is given th...