Multiple Choice
The ________ can be used in a variety of ways. For example, it can be a brainstorming session to list/review the things that went right and those that went wrong during the project. It is also used to review the entire project and provide a help session so that future projects avoid the same pitfalls.
A) lessons learned
B) closeout meeting
C) site closure
D) audit
Correct Answer:

Verified
Correct Answer:
Verified