In the Final Project Report, This Information Answers Questions Such

Question 4

Multiple Choice

In the final project report, this information answers questions such as: How well did the decision makers perform on the project in terms of speed and accuracy, based on the quality of the information available for decisions? How well did the organizational structure aid the project or hinder the project? Did the decision makers have the correct levels of authority?


A) Project performance
B) Product performance
C) Administrative performance
D) Team member performance