The Contract Change Control System Should Include Procedures for Handling

Question 71

True/False

The contract change control system should include procedures for handling any changes to deliverables, completing tracking of the change request and associated implications for cost and schedule, handling dispute resolutions, and getting required approvals to enact any contractual change.

Correct Answer: