    Prevention Attempts to Keep Errors Out of a Process, Whereas
Solved

Prevention Attempts to Keep Errors Out of a Process, Whereas

Question 40

Question 40

Multiple Choice

Prevention attempts to keep errors out of a process, whereas ________ attempts to keep errors from reaching the final customer.


A) monitoring
B) control
C) reaction
D) inspection

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q35: Each risk owner is responsible for monitoring

Q36: Decisions concerning project changes must be based

Q37: The triple constraint of project management includes

Q38: A contract or seller _ system needs

Q39: A benefit of control chart analysis is

Q41: A _-also called an Ishikawa diagram after

Q42: Name and describe three tools used to

Q43: The sample source is the number of

Q44: Reporting uses the information supplied by the

Q45: Explain the concerns of the seller and

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines