    Every Documented Requested Change Must Be Either Accepted or Rejected
Solved

Every Documented Requested Change Must Be Either Accepted or Rejected

Question 55

Question 55

True/False

Every documented requested change must be either accepted or rejected by an authority from the project management team; the proper authority is called a change advisory board (CAB) or a change control board (CCB).

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q50: What do the following acronyms stand for

Q51: Monitoring and control involves a set of

Q52: Scope creep (which happens during IT projects

Q53: The scope control process is responsible for

Q54: List the types and examples of project

Q56: In configuration management, this is validating the

Q57: Cost performance index (CPI) equals the ratio

Q58: Monitoring and control processes are used to

Q59: The process of verifying scope is responsible

Q60: The organization and project manager must foster

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines