Every Documented Requested Change Must Be Either Accepted or Rejected

Question 40

Multiple Choice

Every documented requested change must be either accepted or rejected by an authority from the project management team; the proper authority is called a ________.


A) project management committee
B) change control board
C) change management database
D) change control matrix

Correct Answer:

verifed

Verified